Chun Yip Engineering Co (A Firm) v. Sil Vercord Ltd
Read the full judgment text of HCA 8535/1996 on BabelCite. This High Court CFI judgment was delivered on 26 February 1997.
2. The Plaintiff took out an Order 14 application on 21 August, 1996. On 16 September, 1996, Interlocutory Judgment was entered in favour of the Plaintiff with damages to be assessed. This is the Judgment on the assessment of damages.
|
HCA008535/1996
IN THE SUPREME COURT OF HONG KONG HIGH COURT -----------------
----------------- Coram: Master Chung in Court Date(s) of Hearing: 17 February 1997 Date of Judgment: 26 February 1997 --------------------------------------------------- ASSESSMENT OF DAMAGES ---------------------------------------------------
The Plaintiff's claim in this action is for interim payments for work done by the Plaintiff as the Defendant's sub-contractor in various construction works orders placed by the Hong Kong Government as the employer and for interest thereon. There was also a claim for loss of profits which has been abandoned. 2.The Plaintiff took out an Order 14 application on 21 August, 1996. On 16 September, 1996, Interlocutory Judgment was entered in favour of the Plaintiff with damages to be assessed. This is the Judgment on the assessment of damages.
3.At the beginning of the hearing, Mr. Cheuk Tit-hop asked for leave to represent the Defendant company in the hearing for assessment. Mr. Cheuk claimed that he had been authorized by the Defendant to represent it. However, when the Court asked for the circumstances under which he was authorized, it became clear that Mr. Cheuk was only "orally authorized". There was no board or other resolution by the Defendant to such effect and the only written authorization for Mr. Cheuk to represent the Defendant was (according to Mr. Cheuk) given some 2 years ago in relation to another unrelated action. 4.In the circumstances, I refused Mr. Cheuk's application for leave to represent the Defendant. Technically speaking, therefore, the Defendant is absent. However, seeing that Mr. Cheuk was present at the hearing, I allowed him to participate for the benefit of the Defendant. On that basis, he was allowed to ask questions of the Plaintiff's witness(es) and to make submissions to the Court. In any event, no relevant question was put to the witness and no submissions were made.
5.The following heads of claim have been set out in the Statement of Claim of this action:-
At the beginning of the hearing, Mr. Mak for the Plaintiff informed me that the claim for loss of profits is abandoned. I therefore need only to deal with the heads of claim set out in sub-paragraphs (a) and (b) above.
6.This head of claim arose from a number of works orders of the Hong Kong Government. The Government would contract these works orders to one Collections Interior Limited ("CIL") which in turn would sub-contract them to the Defendant. The Plaintiff was a sub-contractor of the Defendant responsible for building work in these works orders. 7.The basis of this head of claim was set out in the Statement of Claim as follows: "the Defendant undertook to pay to the Plaintiff 84% of all contract sums within 7 days upon its [the Defendant's] receipt of the same from CIL and/or the Architectural Services Department" (para. 3(c)(1) thereof). 8.It became apparent in the course of the hearing (from the testimony of Mr. Chan Chi-tak) that this is based on an oral agreement made between one Mr. Leung Hung-pong of the Plaintiff and one Mr. Chan Kai-hung of the Defendant in about March, 1993. The gist of the agreement is as follows:-
This is quite different from what has been pleaded in the Statement of Claim (although the averment in this part of the Statement of Claim has in fact been repeated in the affirmation in support of the Order 14 application as well as in Mr. Chan's witness statement (which he adopted as his testimony)). Nevertheless, for present purposes, I shall consider that the difference was the result of the misunderstanding on the part of the drafter(s) of these court documents. 9.The quantum of this head of claim was originally set out in Schedule II of the Statement of Claim. However, at the beginning of the hearing, Mr. Mak informed me that that was inaccurate and a revised "Schedule of Interim Payment withheld by the Defendant" ("the revised schedule") was submitted by him to replace the said Schedule II.
10.It is the Plaintiff's case that the Defendant is liable to pay to the Plaintiff interest for these outstanding sums from the respective times when they fell due and payable and up to the date of payment. The Plaintiff said the rate of interest should be at 2% above the prime rate by reason of an agreement made between the parties by way of a course of dealing.
11.In relation to the claim for a portion of the Interim Payments, the following evidence was adduced by the Plaintiff:-
12.The testimony of Mr. Chan was not challenged by Mr. Cheuk who indicated that he had only one question for the witness. The only question raised by Mr. Cheuk was that some of the works orders had not been finalised. However, in view that this is only a claim for interim payments and that there is no counterclaim, I disallowed this question as irrelevant. The relevant works orders can be found at pp. 39 to 119 of the Bundle of Documents. 13.There are 2 points which the Plaintiff needs to establish in relation to this head of claim:-
14.According to Mr Chan's testimony, the Plaintiff's portion of the interim payments was agreed between the Plaintiff and the Defendant (this has been set out in para. 8 above) being such proportion which the estimated value of the builder's costs as set out in each works order bears to the total estimated value for that order. 15.However, when calculations were made on this basis, it was found that the portion of interim payments which the Plaintiff would have been entitled to for the various works orders in question would be quite different from those set out in the revised schedule. I will set out the differences below:-
16.There are other differences further to the ones set out above. At pp. 1 to 22 of the Bundle of Documents are (according to Mr. Chan) the "Interim Payment Certificates" of the main contractor, CIL. Mr. Mak submitted that these documentary records prove (a) the percentage of the share which the Plaintiff was entitled to under the agreement; and (2) that the amounts claimed in this action were due and owing. These documents were included in a Hearsay Notice dated 14 February, 1997. As the Hearsay Notice was served out of time, Mr. Mak applied, and was given an order, for an extension of time for doing so. After examining these documents, it appears that they were periodic records showing inter alia cumulative amounts payable to the Plaintiff. 17.For some of the works orders, the percentage share under the column "% of builder's works" in the "Interim Payment Certificates" of CIL are different from those set out in the revised schedule. Discrepancies can be found in relation to the following works orders:-
18.None of these discrepancies have been drawn to my attention at the hearing and they were only discovered when I examined the documents afterwards. Naturally, none of these discrepancies have been dealt with or explained by the Plaintiff. At present, therefore, the matter is in a highly unsatisfactory state. 19.Further, the Plaintiff's evidence on the issue of whether or not the interim payments claimed have fallen due and payable is also highly unsatisfactory. The only evidence relating to this is hearsay in nature. Mr. Chan testified he had been told that the relevant interim payments had been released by the employer to the main contractor. There is no hearsay notice covering this part of Mr. Chan's testimony. In the circumstances, I do not think that it is right for me to have regard to this piece of evidence in the absence of any supporting documentary evidence. It is, moreover, unclear as to whether the sums stated in the column "Net Amount to Chun Yip" of CIL's "Interim Payment Certificates" refer to:-
Even if I give the benefit to the Plaintiff and find the sums to refer to those already received by CIL, it still does not prove that these sums are already due and owing to the Plaintiff. This is because according to the Plaintiff's evidence, those sums would only be payable to the Plaintiff after they have been received by the Defendant. Such evidence is at present totally lacking. I cannot be satisfied on the materials now before me that the sums set out in the revised schedule are and were at the commencement of this action due and owing by the Defendant to the Plaintiff.
20.The evidence purporting to support this head is as follows:-
21.In summary, Mr. Mak submitted that the Plaintiff is entitled to claim the rate of interest set out in the Statement of Claim because the Defendant used to charge the Plaintiff this rate of interest. He submitted that there was an agreement reached between the parties by way of a course of dealing between the two. However, this "course of dealing" was only related to the interest charged by the Defendant on the Plaintiff. No evidence was adduced to prove (nor was it otherwise suggested) that there was a course of dealing where the Plaintiff has previously charged the Defendant this rate of interest. 22.It must be borne in mind that for the Court to imply a term (assuming that an agreement exists), the implied term must be one which is not only reasonable but also necessary so as to give business efficacy to the agreement. It may be reasonable that because the Defendant used to charge this rate of interest, the Defendant should pay the Plaintiff the same rate of interest. However, such a term is not necessary for there to be a loan agreement. With this in mind, I do not see how the Plaintiff can establish this head of the claim. Whilst it may (subject to satisfactory evidence) eventually be appropriate to award interest at the normal judgment rate from the date of Write to date of judgment and thereafter at judgment rate until payment, it is not necessary, for the reasons set out below, for me to come to a definitive view at this stage.
23.Having come to the conclusions set out above, it seems to me there are at least 2 options open to me:-
24.Having considered the circumstances of this case, I find that I should adopt the second course in the exercise of my discretion. In so deciding, I took into account the following matters in particular:-
25.The parties agree that a costs order nisi can be made pursuant to R.S.C. Ord. 42 r. 5B(6). 26.In view of my earlier observations, I consider that it appropriate to make the following costs order nisi:-
In default of such a date being fixed by Messrs. Siao, Wen & Leung within the said period, an order will be made in terms of sub-paragraph (c) above.
Representation: Mr. B. Mak i/s by Messrs. Siao, Wen & Leung for the Plaintiff Defendant absent (Mr. Cheuk Tit-hop, Timothy present) Register Decision File |