Nin Hing Electronic Engineering Ltd v. Aoki Corporation
Read the full judgment text of HCA 4628/1987 on BabelCite. This High Court CFI judgment.
1. This is an appeal from a Master's Decision. He heard two summonses. The 1st was the Plaintiff's application for summary judgment under Order 14 and the 2nd was the Defendant's application for a stay of the proceedings for arbitration. The master entered judgment for the Plaintiff in the amount claimed and dismissed the Defendant's application.
|
HCA004628/1987 HEADNOTE Non-domestic arbitration - the factors which have to be considered in deciding whether it can be said that a dispute has arisen or whether the matter can be disposed of under an application for summary judgment under Order 14. The extent to which it is permissable to set off payments against an interim certificate issued by an Architect. What constitutes an Architect's certificate. Held.
IN THE SUPREME COURT OF HONG KONG HIGH COURT ___________ BETWEEN
___________ Coram: Hon. Mayo J. in Chambers Date of Hearing: 7th & 8th December, 1987 Date of Delivery of Judgment: 17th December 1987 __________ JUDGMENT __________ 1. This is an appeal from a Master's Decision. He heard two summonses. The 1st was the Plaintiff's application for summary judgment under Order 14 and the 2nd was the Defendant's application for a stay of the proceedings for arbitration. The master entered judgment for the Plaintiff in the amount claimed and dismissed the Defendant's application. 2. The litigation concerns a building dispute in respect of the development of property at Manderley Gardens Shouson Hill. 3. The main contract was dated 7th May 1985 and is between a company called Queboton Ltd. (The Employer) and the Defendant (Aoki). There is also a sub-contract between Aoki and the Plaintiff (Nin Hing). 4. It is Nin Hing's case that Aoki received $466,320 from the Employer in relation to sub-contracting work undertaken by them. Two Architects' certificates have been issued in respect of this work and Nin Hing claim that Aoki have failed to pass on these moneys to them in accordance with the terms of the sub-contract. Standard forms of contracts have been adopted and where appropriate the sub-contract adopts the terms of the main contract. 5. It is common ground that if there is to be an arbitration it would be a non-domestic one. Accordingly the scope of the court's discretion to decline to order a stay is narrowly circumscribed. It may be of assistance to consider the approach to be adopted in determining the extent to which a Plaintiff has to satisfy the court that there is not in fact any dispute between the parties. Kerr L.J. considered the test at page 1401 of Sethia Liners Ltd. v. State Trading Corporation of India(1).
6. Section 6A of Chap. 341 is in similar terms to section 1 of the 1975 Act. I accept that this is a correct statement of the law. 7. I accept that if all that is involved is the determination of a point of law and there are no problems with the facts it is in order for a judge or master to resolve the question of law on Order 14 proceedings. That however seems to me to be far from the position in the present case. 8. As I am in effect hearing these summonses de novo and the burden is placed upon Nin Hing to establish that there should be no stay I think that the most satisfactory approach is for me to consider the submissions which were advanced by Mr. Pennicott on their behalf. I will deal with these under separate headings. 1. The Employer had no right to make any deduction of moneys payable to Aoki. 9. For this submission Mr. Pennicott placed reliance upon the provisions contained in clause 22 of the main contract. This reads:
10. The point which Mr. Pennicott makes is that there is no evidence of any architect's certificate being issued as is required under the clause. Indeed it is common ground that no such certificate exists. 11. Mr. Pennicott went on to argue that the deductions which had been made were unauthorised. Aoki had a contractual right to be paid in full on both of the relevant certificates which were C20 and C21A. The fact that Aoki had not chosen to assert their rights could not constitute grounds or good authority to justify their making deductions in respect of payments to Nin Hing. 12. I regret that I do not think that this submission has any prospect of success. The most obvious objection is that no direct contractual nexus exists between Nin Hing and the Employer. Put rather more elegantly there is no privity of contract. I accept that Clause 12 of the sub-contract provides:
13. However, I understand that Nin Hing have not made any request to Aoki to assist them in this connection. 14. Also perhaps even more important Nin Hing have not pleaded Clause 22 of the Main Contract in their Statement of Claim. Their claim is framed on Aoki's failure to account to them with moneys due and owing to them in accordance with the Architect's certificates referred to. That is the claim they have chosen to make and that is the claim I will consider in the context of this appeal. 15. Mr. Scott who represented Aoki argued that it would be wrong not to have regard to the realities of the situation. 16. Negotiations were still proceeding between the Employer and Aoki under the Main Contract. If Aoki was to commence proceedings in respect of allegedly unauthorised deductions of amounts due they would almost inevitably be met with an application for a stay under section 6A. 17. It was also unrealistic to contemplate separate litigation for every individual dispute which arose under the main contract and the various sub-contracts. It would be far more satisfactory for an arbitrator to be appointed in due course to consider and arbitrate upon all these matters in consolidated arbitration proceedings when it was appropriate that the issues should be ventilated. I reject Mr. Pennicott's contention under this head. Perhaps it is more relevant to state that Nin Hing totally fail to meet the criteria laid down by Kerr L.J. in Sethia which I have referred to. 2. That payments of moneys in respect of certificates C20 and C21A had been received by Aoki and that accordingly they had no right to make any deductions from the amounts payable to Nin Hing under the said certificates. 18. The most formidable difficulty which Mr. Pennicott encounters under this head is that Mr. LEE Chun-tin on behalf of Aoki states on affirmation that no such payments have been received by Aoki. He directly contradicts the unsupported assertion by Mr. Mak of Nin Hing to this effect which he made in the supporting affidavit to the Order 14 summons. 19. It is of course no part of either my function at this stage or the Master's to attempt to determine the veracity or otherwise of affidavits which have been filed or where there are conflicts of evidence where the truth lies. Mr. Pennicott endeavoured to overcome this difficulty by referring to the 2 certificates and examining the surrounding correspondence which was exhibited. So far as certificate C20 was concerned it was evident from the Employer's letter of 19th January 1987 that the total amount under the certificate was $1,282,500 and that $248,000 odd had been deducted. It could be seen from this that Aoki had received a sum in excess of $1M. Mr. Pennicott argued that in the absence of a certificate under Clause 8(a) of the sub-contract blaming Nin Hing for delay it must be assumed that their money was part of the balance I have above referred to. In this situation no justifi-cation had been shown for a deduction to be attributable to Nin Hing. 20. A similar argument was adopted in relation to payments under certificate C21A. In this case the total moneys received by Aoki were $1,038,032 from which a deduction of $341,000 odd had been made leaving a balance of approximately $695,000. Mr. Pennicott did not produce any authority for the proposition that a burden was placed upon Aoki to prove the manner in which all moneys received by them had been applied. 21. A more basic difficulty arises from the part of the submission referring to the absence of a Clause 8(a) certificate. I will be dealing with this under the next head of the submission made by Mr. Pennicott. 22. Suffice it to say that for the reasons I will be giving I am satisfied that a valid certificate has been issued under Clause 8(a) of the sub-contract. In that certificate the blame for at least part of the delay complained of is fairly and squarely placed upon Nin Hing. I reject the contention that Nin Hing have established that Aoki have in fact received the relevant payments under C20 and C21A. 3. Has a valid certificate been issued under Clause 8(a) of the sub-contract. 23. This clause reads as follows:
24. It is true that when these applications were before the Master, no such certificate was in existence. 25. However, in the interim period between the respective hearings Aoki have filed additional evidence. They have exhibited to an affidavit a letter from the Architect which reads as follows:
26. Subsequent to this certificate being issued there was an exchange of correspondence between Nin Hing and the Architect. I do not think that it is necessary for me to go into any detail on the matters raised. It is sufficient to state that the Architect did say that if representations were made by Nin Ring in the matter they would be prepared to reconsider the matter. From this, it can be taken that to an extent it is possible that the position stated in the letter of 2nd November is not necessarily immutable. 27. In this connection I would add that up to the date of the hearing before me Nin Hing have not made any representations to the Architect. 28. Mr. Pennicott argued that as there was a possibility that the so called certificate may still be varied it could not be regarded as a certificate for the purposes of Clause 8(a). His authority for this was a passage which appears at p.238 and 239 of H.K. Teakwood Works Ltd. v. Shui On Construction(2).
29. It can immediately be seen that the letter which Mr. Justice Hunter was considering in that case was entirely different to the Architect's latter here. There is nothing on the face of the Architect's letter to indicate that the determination or certificate that is being made is of a provisional nature. 30. Equally I don't think that the correspondence exchanged between Nin Hing and the Architect takes matters further. There is nothing in Clause 8(a) to say that any certificate given under the clause must be final and beyond any appeal. The fact that the Architect is prepared to given the matter further consideration is neither here nor there. 31. The result of this is that almost certainly the Architect's letter is in such a form as to comply with the requirements of Clause 8(a). Put another way it is undoubtedly arguable that it does constitute an Architect's certificate under the clause which is all that Aoki have to establish. Mr. Pennicott's submission under this head cannot succeed. 4. It is not permissable to set off payments against an interim certificate issued by an Architect in respect of work which has been performed. 32. The landmark decision concerning this proposition is the House of Lords case Gilbert Ash Ltd. v. Modern Engineering Ltd. (3). 33. There had been a whole series of cases where Courts had held that an interim certificate was virtually sacrosant. This perhaps being best demonstrated by Lord Denning in Dawnays v. Minter (4). Here he said:
34. This principal was not accepted in Gilbert Ash. At page 85 Lord Dilhorne dealt with Dawnays' case as follows:
35. This line of reasoning was also followed by the other members of the Court. There is a particularly helpful summary of the position given in Lord Salmon's speech at page 100 of the report. 36. Mr. Scott in the course of a most helpful submission referred me to a number of other cases on the point. I do not think that it is necessary for me to refer to these other authorities for the purposes of this judgment save to referring to H.K. Teakwood Works Ltd. v. Shui On(2), a local case where Mr. Justice Hnnter applied the principals in a situation which was in many respects similar to the present one. 37. It is a particularly helpful case as it would appear that similar contract forms were adopted. In that case reference was made to "receipt of payment". 38. Clause 11(b) of the sub-contract in our case reads:
39. Mr. Justice Hunter was satisfied that difficult issues were involved and that it was appropriate that the dispute should be the subject of arbitration. He was disposed to follow the authority of Gilbert Ash Ltd. v. Modern Engineering Ltd.(3). 40. There is a further matter to be considered. There is a dispute in the present case as to whether Aoki have in fact received payment. For the reasons I have already given I am satisfied that this is still an open question. For the purposes of this exercise I must proceed on the assumption that it has not been established that Aoki have received payment. This is yet another matter which would be a proper matter for reference to an Arbitrator. 41. I have no doubt in the present case that Mr. Scott has demonstrated that a dispute has arisen which should be referred to arbitration in accordance with the agreement between the parties. 42. I am also mindful of the approach which has been adopted in other cases in Hong Kong. Again in another case which in many ways is not dissimilar to the present one the Court of Appeal found that the dispute which arose must be referred to arbitration. I refer to Schindler Lifts v. Shui On Construction Co. (5). That case involved a domestic arbitration whereas the present one is a non-domestic arbitration. There are accordingly even more compelling reasons why it is appropriate that such a reference should be ordered. 43. Certainly if consideration is given to the guidance laid down by Kerr L.J. in Sethia it becomes clear that this matter must proceed by way of arbitration. 44. The consequence of this is that this appeal must succeed. I therefore order that the Order 14 judgment must be set aside and the Defendant's application for a stay must be granted. I will hear the parties on costs.
(1) [1986] 1 WLR 1398 (2) [1984] HKLR 235 (3) 1 BLR 73 (4) 1 BLR 16 (5) [1985] HKLR 188 Representation: Mr. Ian Pennicott instructed by McKenna & Co. for Plaintiff/Respondent Mr. John Scott instructed by Denton Hall Burgin & Warrens for Defendant/Appellant | ||||||||||||||||||||||||||||||||||