Tin Shui Wai Development Ltd v. Yiu Sun Hung
Read the full judgment text of DCCJ 569/2003 on BabelCite. This District Court judgment was delivered on 17 December 2004.
1. This is an application by the plaintiff to strike out the Defence and Counterclaim of the defendant under Order 18 rule 19 of the Rules of the District Court.
Cites 3 cases
|
DCCJ 569/2003 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 569 OF 2003 -------------------- BETWEEN
-------------------- Coram: His Honour Judge L. Chan in Chambers Dates of Hearing: 13 to 15 April, 2004 Date of Handing down Judgment: 17 December 2004 _____________ JUDGMENT _____________ 1.This is an application by the plaintiff to strike out the Defence and Counterclaim of the defendant under Order 18 rule 19 of the Rules of the District Court. Background2.In 1985, the government granted the plaintiff seven lots of land in Tin Shui Wai designated as TSWTL No. 1 to 7. They were to be developed in stages and to be known as Kingswood Villas. Lot No. 6 was to be developed as Maywood Court. Under clause 16(a)(iii) of the conditions of grant (“the Grant”), the plaintiff was restrained from disposing of or entering into any agreement to dispose of any part of the lot until the conditions of grant had been complied with to the satisfaction of the Director of Lands save as provided in clause 16(b) of the Grant. The relevant parts of the two clauses stated as follows:
3.In March, 1997, the plaintiff obtained the requisite consent to enter into agreements for the sale of parts or shares of Lot No. 6 together with exclusive right to occupy the residential units and car parks in Maywood Court. By an agreement of sale and purchase dated 16 April, 1997 (“the Agreement”), the plaintiff agreed to sell and the defendant agreed to purchase Flat E on the 6th Floor of Block 3 of Maywood Court (“the Property”). In entering into the Agreement, both the plaintiff and the defendant were represented by Woo, Kwan, Lee & Lo, the third party herein. The purchase price for the Property was HK$2,958,000. The defendant paid 30% as deposits and part payment. The remaining 70% or HK$2,070,600 was payable within three months of the defendant being notified in writing that the plaintiff was in a position validly to assign the Property to the defendant. However, the defendant was entitled to call for the conveyance of the Property within 14 days from the notification. Clauses 4, 5 and 16 of the Agreement are relevant to this action and their relevant parts are as follows:
4.The effect of clauses 4(4)(a) and 4(4)(b) of the Agreement is that if the plaintiff should fail to complete the development by 31 December, 1997, the defendant would have 28 days to rescind the Agreement and get back the deposits and part payment with interest. If the defendant did not rescind within the 28 days, she would be deemed to have elected to wait for the completion. If the plaintiff should still fail to complete the development within the next 6 months after 31st December, 1997, the defendant would have another option under clause 4(4)(c) to rescind the Agreement and get back the payments with interest or to continue to wait for completion. 5.On 22 December, 1997, the Building Authority issued the plaintiff with an occupation permit that covered Blocks 1 to 8 of Maywood Court which included the Property. On 23rd December, 1997, the plaintiff through the third party applied to the Director of Lands for consent to assign. On 26 March, 1998, the District Lands Officer, Yuen Long wrote to the third party on this application and referred to a site visit on 6 March, 1998 which revealed that the construction works for the kindergarten, external and internal finishing of the residential blocks, ancillary facilities including tennis and basketball courts and swimming pool and landscaping were outstanding. The plaintiff on 4 June, 1998 gave the government an undertaking to complete on or before 30 September, 1998 some minor external finishing works, minor landscaping works and minor internal finishing works at the common area of the lot which were acknowledged to be outstanding. Pursuant to the undertaking, the plaintiff also gave the government a bond issued by the Bank of East Asia for HK$55,000,000 to secure the plaintiff’s performance of the undertaking. On 17 June, 1998, the Director of Lands issued to the plaintiff a consent to assign pursuant to clause 16(b)(iv) of the Grant. 6.Under clause 5 of the Agreement, the plaintiff was obliged to notify the defendant within one month after the issue of the consent to assign that it was in a position to validly assign the Property to her. The plaintiff should also complete the assignment at the office of the third party within 14 days of such notification. The third party on behalf of the plaintiff by letter of 30 June, 1998 notified the defendant that the plaintiff was in a position to validly assign the Property to her and asked her to complete the purchase within 14 days. By another letter of the same date but issued by Kingswood Property Services Ltd. on behalf of the plaintiff, the completion date was extended to on or before 30 September, 1998. The defendant did not respond to these two letters and did nothing. The third party on behalf of the plaintiff wrote to the defendant on 9 October, 1998 pursuant to clause 16(1) of the Agreement giving her another 21 days to pay the balance of the purchase price and to complete the purchase. The defendant again did not respond to this letter. On 3rd November, 1998, the third party on behalf of the plaintiff gave the defendant notice to determine the Agreement under clause 16(2) thereof. The plaintiff then resold the Property on 8 December, 1998 at a smaller price of HK$1,528,000. The action 7.On 29 January, 2003, the plaintiff instituted this action against the defendant payment of HK$549,920 plus interest of HK$22,918.42 or alternatively HK$555,295. These sums were arrived at after giving credit to the defendant for the deposits and part payment. The defendant issued a third party notice on 25 April, 2003 and filed and served her defence and counterclaim on 2 May, 2003. The plaintiff then issued a summons under Order 18 rule 19 of the Rules of the District Court to strike out the defence and counterclaim on the grounds that it discloses no reasonable cause of defence; it is scandalous, frivolous and/or vexatious; it may prejudice, embarrass or delay the fair trial of the action; and/or it is otherwise an abuse of process of the court. Defence and counterclaim 8.By her defence and counterclaim, the defendant pleaded that the purchase of the Property was subject to the “consent scheme” which was established to protect members of the public who purchase uncompleted flats. Under this scheme, the plaintiff, as the vendor of uncompleted flats, was required to incorporate certain standard terms into the Agreement. She therefore pleaded that in order to enable her to exercise her rights of rescission given to her by clause 4 of the Agreement meaningfully pursuant to the purpose and intent of the consent scheme, there was an implied term that the plaintiff was obliged to answer her questions or requisitions concerning whether the development had in fact been completed in accordance with clause 4(1)(c) of the Agreement on or before 31st December, 1997. Mr. Lee S. C. in the course of submissions clarified that the implied term did not require the plaintiff to answer requisitions as such, but it required the plaintiff to answer questions concerning whether the development had in fact been completed by 31st December, 1997. Mr. Lee confirmed that the defendant’s case was not built on requisition. 9.The defendant further pleaded that she had made two enquiries with the staff of the plaintiff and of the third party. The first one was in about late 1997 when she enquired with the plaintiff’s staff at the plaintiff’s office on when the Property would be delivered to her for her use. The plaintiff’s staff told her to the effect that the Property would soon be ready for delivery to her. She made the same enquiry again in about early January, 1998 with the staff of the third party. She was told to the effect that possession of the Property was ready for delivery to her and she was asked her to wait for further notice. Acting on the faith of these representations, she did not exercise her rights under clause 4(4)(a) of the Agreement. 10.The defence and counterclaim goes on to say that after she was served with the writ of summons, she discovered that the plaintiff had not completed the development in accordance with clause 4(1)(c) on or before 31st December, 1997. There were some documents which suggested that works in connection with the development had not been completed even by 4 June, 1998. She also pleaded the undisputed fact that the plaintiff could only deliver possession of the Property to her sometime in July, 1998. She then pleaded that the plaintiff had breached the implied term by failing to answer her questions concerning whether the development had been completed in accordance with clause 4(1)(c) by 31st December, 1997. She also accepted the plaintiff’s breach of the Agreement and/or rescinded the Agreement by the filing of her defence and counterclaim. 10. She further pleaded that by reason of the plaintiff’s breach of the implied term and/or its failure to complete the development in accordance with clause 4(1)(c) on or before 31st December, 1997, the plaintiff was not ready or able to complete the sale and purchase of the Property and was not entitled to serve any notice under clause 5(2) or 16(1) for completion. She also pleaded that during the period of delay, the property market had suffered a severe downturn and it was unfair and inequitable for the plaintiff to insist that the defendant should complete the purchase of the Property and to pay the balance of the purchase price. 11.In addition, she also pleaded a misrepresentation by the plaintiff’s agent on about 14 April, 1997 which induced her to enter into the Agreement, an averment that the two representations made at the end of 1997 and early January, 1998 were fraudulent, or, as an alternative to fraud, these representations entitled her to rely on section 2 of the Misrepresentation Ordinance for relief in the Counterclaim. These averments were however abandoned by Mr. Lee in the course of submissions. Evidence on misrepresentation 12.The defendant filed an affirmation on 30 January, 2004 to oppose the plaintiff’s application to strike out. She referred to the two enquiries and related matters as follows:
Defendant’s further point 13.In addition to the above points, Mr. Lee and Mr. Cheung in their supplemental submission for the defendant also raised the point that the meaning of the words “in a position to validly assign” in clause 5 of the Agreement should mean not only the plaintiff’s ability to give a good title to the Property, but also its ability to convey a physically completed flat to the defendant. They submitted that the consent to assign only had a deeming effect for clause 4 and not clause 5. Thus for the purpose of clause 5, the consent to assign was no proof that the Property was completed and was in a physical position to be delivered to the defendant pursuant to and in performance of the Agreement. They further relied on the plaintiff’s undertaking to the government and the bond issued by the Bank of East Asia as evidence that the Property had not been completed on 4 June, 1998 and thus inferred that it was not completed by 30 June, 1998. 14.The defendant’s oral submissions visited an even larger territory than that covered by the defence and counterclaim and the supplemental submission. At my request, Mr. Lee and Mr. Cheung very helpfully provided me with a summary of the defendant’s submissions after the conclusion of their oral submissions. Summary of defendant’s submissions 15.The summary firstly referred to the implied term and the alleged breach of it as pleaded in the defence and counterclaim and referred to above. It then sought to rely on the prevent principle which was explained in detail and applied by the Court of Final Appeal in Kensland Realty Ltd. v. Whale View Investment Ltd. [2002] 1 HKLRD 87. The summary stated that the plaintiff had given wrong answers to the defendant’s enquiries and committed a breach of the implied term. This caused the defendant not to exercise her right to rescind under clause 4(4)(a) and thus kept the Agreement alive with dire consequence to the defendant but advantages to the plaintiff. The prevention principle should prevent the plaintiff from benefiting itself from its own wrong and thereby exonerate the defendant from such consequence. This principle should apply regardless whether there was the implied term. The third point was the misrepresentation of fact by the plaintiff in its answers to the defendant’s enquiries. It was said that this plea could operate independently of the implied term or the prevention principle. By itself, it would give the defendant the right to damages. If the defendant should succeed on any one of these three points, she would be entitled to a set-off and a counterclaim for damages. 16.The summary then said that the notice to complete issued by the third party on 30 June, 1998 was bad. It provided two arguments. The first argument was that under clause 4(6) of the Agreement, the plaintiff was only entitled to apply for the consent to assign when the development had been completed in all respects in compliance with the conditions of grant. The application for consent to assign submitted by the third party on behalf of the plaintiff on 23rd December, 1997 was thus an invalid application. Thus, the plaintiff could not rely on the consent issued by the Director of Lands on 17 June, 1998 so as to have the benefit of the deeming provision in clause 4(7). Hence, when the notice to complete was issued on 30 June, 1998, the development had not been completed or deemed to be completed. The notice to complete was thus invalid pursuant to clause 5(1) of the Agreement. 17.The second argument was that the deeming effect of the consent to assign pursuant to clause 4(7) only applied to clause 4 and not clause 5. The consent to assign could not prove for the purpose of clause 5 that the plaintiff was “in a position validly to assign” on 30 June, 1998. When the notice to complete was issued on 30 June, 1998, the development had not been completed. The notice was thus bad. 18.If the notice was bad, the plaintiff could not have by notice of 3 November, 1998 determined the Agreement. That was a repudiation of the Agreement. The subsequent resale of the Property brought the Agreement to an end and the defendant was entitled to have her deposit back. 19.Before going further, I should mention that Deputy High Court Judge Longley had in Yau Chin Kwan and Yuen Suk Kuen v. Tin Shui Wai Development Ltd. HCA 11520 of 1999 struck out various parts of a statement of claim by a purchaser of another flat in this development. That action was based on an agreement for sale and purchase which was materially the same as the Agreement in this action. The plaintiffs in that case appealed to the court of Appeal and the appeal was dismissed in Yau Chin Kwan and Yuen Suk Kuen v. Tin Shui Wai Development Ltd. CACV 3970 of 2001. A number of matters discussed in the two judgments are relevant to the present application and I shall refer to them below when appropriate. Implied term 20.The law on when a term can be implied into a contract has been summarized by Lord Simon in B. P. Refinery (Westernport) Pty Ltd. v. President and Councillors and Ratepayers of Shire of Hastings (1978) 52 ALJR 20 (PC) at 26E:
21.I also refer to the earlier judgment of the House of Lords in Trollope & Colls Ltd. v. North West Metropolitan Regional Hospital Board [1973] 1 W. L. R. 601 where Lord Pearson at 606 referred to the judgment of Scrutton, L.J. in Reigate v. Union Manufacturing Co. (Manufacturing Co. (Ramsbottom) Ltd. [1918]1 K. B. 592 at 605:
22.Lord Pearson also referred to a passage in the opinion of Lord Wright in Luxor (Eastbourne) Ltd. V. Cooper [1941] A.C. 108 at 137:
23.The learned Judge then referred at 608 to the judgment of Lord Denning given in that case in the Court of Appeal:
24.The learned Judge then said at 609:
25.The first point taken by Mr. Yu, S. C. for the plaintiff is that the Agreement was workable without the need to imply the term as sought by the defendant. It was thus unnecessary to imply the term. He argued that if the building had to reach 20 storeys but the construction had only reached the 15th floor by 31 December, 1997, it was obvious to the defendant that the plaintiff had failed to complete the development by that date and she could rescind. Without the implied term, it was in some circumstances more difficult for the defendant to tell whether she could rescind or not, but that did not make the Agreement unworkable. It was desirable to have the implied term. However, the above authorities show that desirability or benefit to one party is insufficient to imply a term. 26.The defendant argued that without the implied term, it was difficult for her to tell whether the development had been completed in all respects. If she could not tell with some degree of certainty that the development had not been completed, she could not have rescinded and the Agreement could not work. Mr. Lee also referred to the plaintiff’s undertaking to the Government and the bond issued by its banker and the fact that they were not registered at the Land Registry. He thus fortified his submissions that there was no way for the defendant to find out whether the development had been completed. 27.The defendant also referred to the judgment in Yau Chin Kwan and Yuen Suk Kuen v. Tin Shui Wai Development Ltd. HCA 11520 of 1999 wherein Deputy High Court Judge Longley appeared to have said something in favour of implying their term. It was a case of the purchasers of another flat in Maywood Court suing the same developer Tin Shui Wai Development Limited for return of the deposit and part payments. The purchasers there also tried to rely on their rights of rescission under clauses 4(4)(a) and (b) of the sale and purchase agreement which were the same as those in the Agreement. They also pleaded implied terms. However, they had not made any enquiry as had been made by the defendant herein, their implied terms were thus not exactly the same as the one sought here. The terms they sought to imply into their agreement read as follows:
28.The third term is materially the same as the one sought here. Since the purchasers there had not made the enquiries as had been made by this defendant, the establishment of the third term would not have helped them at all, they had to successfully argue for the first and second terms. For this reason, the developer there did not appear to have really argued against the implication of the third term. In paragraph 48 of the Judgment, the learned Deputy Judge recorded Mr. Yu (who also appeared in that case for the developer) as having submitted to the effect that:
29.It was in that context that the learned Deputy Judge said in paragraph 55 of the judgment:
30.Mr. Yu has revised the plaintiff’s position in this case. He strenuously argued that the Agreement could work without implying the term. I must agree with him that if the construction of the building had not even reached the requisite number of storeys, the defendant would have no difficulty in saying that completion had not taken place and therefore to rescind. In such circumstances, there was absolutely no need to imply the term and the Agreement could have worked without it. The imply term would only be useful and desirable when the development was about to be completed. But if the term need only be implied or take effect when the development was about to be completed, it would be difficult to tell at what time or stage of the construction works that it should be implied or take effect. It would also be difficult to formulate its content in order to time its application. This problem of formulation of when the term would bite rendered it incapable of clear expression. 31.The next attack by Mr. Yu is on the imprecision of the term sought to be implied. I have already referred to one aspect of imprecision which is the time when the term would apply. Mr. Yu submitted that there could at least be three ways to formulate the term. He also added a fourth way at a later stage. These possible formulations are:
32.I agree that there are at least these alternatives for the formulation of the term sought. It is tempting to argue that the first formulation is not a real alternative as not any utterance will do. But if the first formulation cannot be satisfied by any answer, should the answer be an honest one or a correct and accurate one or one that was given with reasonable care? The second to fourth alternatives give rise to different obligations. If it cannot be decided whether the first formulation is the same as one of the other three options, then it must be a possible formulation in its own right. If there are so many possible formulations of the implied term and all creating different obligations, then the conditions in B. P. Refinery (Westernport) Pty Ltd. for implying a term cannot be satisfied and no term should be implied. 33.Mr. Yu further argued that if the term could be implied, the plaintiff would have to answer any question however informal or general. However, I am of the view that if the term can be formulated with precision, there would not be difficulty to identify the questions that can come within its scope. 34.Apart from the problem of imprecision, Mr. Yu also says that the defendant cannot surmount the ‘it goes without saying’ test as referred to in B. P. Refinery (Westernport) Pty Ltd. and Luxor (Eastbourne) Ltd. I agree with him. If the implied term cannot be formulated with clarity, I do not think it can pass this other test. Even if the term can be formulated with clarity, I still do not think the parties would take it as something that ‘goes without saying’. 35.Finally, Mr. Yu argued that the defendant was trying to imply a term that would have permitted her to rescind notwithstanding the absence of any notice to rescind served within 28 days as required by clause 4(4)(b) and that was impermissible as such imply term would be contrary to the express term in clause 4(4)(b). I do not agree with this point. The defendant only sought to imply a term requiring the plaintiff to provide answers to her enquiry. No objection has been taken that such term is contrary to the express term of the Agreement. The right to rescind as contended for is a right to follow upon a breach of the term, the defendant does not contend that such right was part of the implied term. 36.In the premises, I find that the implied term as contended for by the defendant cannot be implied into the Agreement. Prevention principle 37.The defendant then argued that if there was the implied term, the defendant would have been able to rely on the Prevention Principle. The application of the Prevention Principle would prevent the plaintiff from benefiting from its own wrong, that was by giving incorrect information to the defendant to cause her not to exercise her right of recession, thereby keeping the Agreement alive with consequences dire to the defendant but advantageous to the plaintiff. 38.Alternatively, the defendant says that, even without the implied term, the Prevention Principle would still apply by reason of the incorrect answers given by the plaintiff and its agent the third party. 39.The Prevention Principle has been explained by Ribeiro, PJ. of the Court of Final Appeal in Kensland Realty Ltd. v. Whale View Investment Ltd. & Another [2002] 1 HKLRD 87. This was a case involving the sale and purchase of a property. Completion was scheduled to take place between 10 a.m. to 1 p.m. on 2 September 1997. The agreement provided that time was of the essence. It also gave the vendor the power to give a split cheque direction, that was to direct in whose favour the balance of the purchase price was to be paid, but did not lay down a deadline for the such direction. Despite earlier requests for such direction by the solicitor of the purchaser, the direction was only given at 11:13 a.m. with a correction at 11:48 a.m. on 2 September. The direction was passed to the purchaser's bank which processed the drawing down of the loan and issued the cashier orders at 12:48 p.m. The cashier orders were only delivered to the vendor’s solicitors and 1:06 p.m. The vendor refused to accept the cashier orders as the deadline had already passed. The Court of Final Appeal decided that business efficacy demanded that there be an implied term that the split cheque direction should be given so as to allow the purchases solicitor reasonable time to comply with it prior to completion. In breach of the implied term, the time allowed by the vendor was not reasonable and the purchaser’s inability to tender completion by 1 p.m. was caused by the vendor’s breach. The vendor’s breach of the implied term was the direct cause of the purchaser’s failure to meet the deadline. Therefore, in seeking to invoke the time of the essence clause, the vendor was seeking to take advantage of a consequence flowing from its own breach. The Prevention Principle operated to prevent reliance on that clause. It followed that, by virtue of section 11 of the Law Amendment and Reform (Consolidation) Ordinance, the equitable rules on time stipulations applied. Under these rules, the purchaser’s failure to meet the completion deadline was not repudiatory in itself, provided that the purchaser completed or showed its willingness to complete within a reasonable time thereafter. 40.Ribeiro, PJ. said in paragraphs 94 to 100 as follows:
41.To invoke the Prevention Principle, there must be a breach of a term of the contract. Since I have held that there can be no implied term as contented by the defendant and the defendant has not alleged that there is a breach of any other term by the plaintiff which would have invoked this principle, there is no room for this principle to operate. I also disagree that this principle can operate independently of any breach of any term of a contract. 42.In any event, when the defendant received the notice to complete in early July, 1998, she should have full knowledge by then that the development was only completed in late June, 1998. If she wanted to seek any remedy that might have flowed from the failure to complete, she should have done so within a reasonable time after her receipt of the notice. She was given three months from 30 June, 1998 to complete. She did not complete, nor did she complain about the incorrect information she was given in late December, 1997 or early January, 1998. She just allowed the time to pass. I do not think the Prevention Principle can come to her aid in these circumstances. Misrepresentation 43.The defendant further argued that her evidence of misrepresentation relating to her inquiries with the staff of the plaintiff and of the third party as referred to above would support a plea of misrepresentation independently of the plea of breach of implied term and/or the Prevention Principle. On this basis, the defendant said that she would be entitled to a set off and counterclaim for damages. However, she did not rely on fraud or section 2 of the Misrepresentation Ordinance, nor did she allege any duty of the plaintiff to advise her or any duty of care on the part of the plaintiff when dealing with her. I therefore cannot perceive any cause of action that can arise from the alleged misrepresentation. Notice to complete 44.Finally, the defendant attacked the notice to complete dated 30 June 1998. She firstly argued that under clause 4(6), the plaintiff should only apply for the consent to assign when it had completed the development in all respects in compliance with the Grant. If the development had not been so completed, the plaintiff was not in a position to apply for the consent. Since the plaintiff had not completed the development on 23 December 1997, the application for consent to assign under clause 4 (6) was invalid. Since clause 4(7) was not intended to benefit a developer in breach of its obligations to complete, the plaintiff could not have relied on the consent to assign so as to take the benefit of clause 4(7). Thus when the third party issued the notice to complete on 30 June 1998, the development was not completed or deemed to be completed and the notice was bad pursuant to clause 5(1). 45.The defendant’s second argument on the notice to complete was that the deeming effect in clause 4(7) was limited to clause 4 and was irrelevant to clause 5. Therefore the plaintiff would only be “in a position validly to assign” the Property to the defendant pursuant to clause 5 if the development had actually been completed. Since when the notice to complete was issued, the development had in fact not been completed and the deemed completion under clause 4(7) did not extend to clause 5, the plaintiff was then not “in a position validly to assign” the Property to the defendant. The notice to complete was thus bad. 46.The effect of this argument is that if the notice to complete was bad, the defendant was not in default of the Agreement when she failed to complete as per the notice. It then followed that the plaintiff's determination of the Agreement on 3 November 1998 was a repudiation of the Agreement. As the plaintiff had sold the Property after repudiating it, the defendant was entitled to get back her deposit. 47.In order to analyse this argument, I have to refer to paragraph 65 of the judgment of Deputy Judge Longley in Yau Chin Kwan as follows:
48.I fully agree with Deputy Judge Longley and do not think that the application for consent to assign could only be made when the development had been completed or that the consent could only be issued by the Director after he had been satisfied that the development had been completed. The requirement in clause 4(6) of the Agreement that the plaintiff should apply for the consent to assign within 14 days of the completion of the development only imposed a deadline for the making of the application, it did not mean that the application could not have been made before the development had been completed. 49.Regarding clause 5, it required the plaintiff to notify the defendant within one month of the issue of the consent to assign that the plaintiff was in a position validly to assign the Property to the defendant. If there was the consent to assign, the Property could be assigned to the defendant. Otherwise, the mechanism for the issue of the consent or the consent itself would not make sense. The protection to the defendant lies in the need for the plaintiff to obtain the consent to assign from the Director of Lands. I do not think the notice to complete was bad for the reasons advanced by the defendant. 50.In the premises, I should strike out the Defence and Counterclaim of the defendant and I so order. I further give judgment for the plaintiff for damages to be assessed. I also make an order nisi that the defendant should pay the plaintiff costs of this action with certificate for leading counsel.
Present : Benjamin Yu, S. C., instructed by M/s Hobson & Ma for the plaintiff Martin Lee, S. C. and Earnest W. H. Cheung, instructed by M/s Ho & Tam for the Defendant. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Further hearings and rulings under DCCJ 569/2003