Hong Kong Inter-asiaengineering Ltd v. Yau Luen Metal Works Ltd
Read the full judgment text of DCCJ 2098/2005 on BabelCite. This District Court judgment.
1. This is the Defendant’s application to strike out the statement of claim in this action pursuant to Order 18, rule 19 of the Rules of the District Court and the inherent jurisdiction of the court on the ground that it is an abuse of the process of the court.
Cites 2 cases
|
DCCJ2098/2005 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 2098 OF 2005 -------------------- BETWEEN
-------------------- Coram : Deputy Judge J. Ko in Chambers Date of Hearing : 7th September 2005 Date of Handing Down Decision : 16th September 2005 DECISION 1.This is the Defendant’s application to strike out the statement of claim in this action pursuant to Order 18, rule 19 of the Rules of the District Court and the inherent jurisdiction of the court on the ground that it is an abuse of the process of the court. 2.The Plaintiff relies on one single cause of action in this case, namely, a claim on 4 dishonoured cheques drawn by the Defendant. 3.It is the Defendant’s contention that the Defendant had already satisfied its liability under those 4 dishonoured cheques by the time of the writ. Hence, the Plaintiff may not maintain the present action based on those 4 dishonoured cheques and the statement of claim should be struck out. Background 4.The parties were engaged in 2 projects in Kowloon Bay (hereinafter called the “Kowloon Bay Project”) and Penny’s Bay (hereinafter called “Disneyland Project”) respectively at the material times. It is common ground that the 2 projects are distinct projects. 5.On 20th April 2005, the Defendant drew 4 cheques in favour of the Plaintiff. It is common ground that cheque no. 805533 in the sum of $45,000 was in settlement of the final account for Kowloon Bay Project and cheque nos. 805534, 805535 and 805536 in the total sum of $150,046 were in partial settlement of the amount due by the Defendant to the Plaintiff in Disneyland Project 6.The 4 cheques were dishonoured upon presentment on 21st April 2005. On 7th May 2005, the Plaintiff issued the writ in this action against the Defendant to claim for the total sum of $195,046. 7.It is the Defendant’s case that it has settled its liability under those 4 dishonoured cheques by the following payments:
8.The Defendant submits that since its liability under the 4 dishonoured cheques have been fully discharged as at the date of the writ, the Plaintiff is not entitled to claim against the Defendant on the 4 dishonoured cheques in this action. 9.The Plaintiff admits having received the 2 payments from the Defendant. However, the Plaintiff says that the said payments were made in compliance with the payment obligation imposed by the Plaintiff in its letters dated 22nd, 25th and 29th April 2005 respectively and has been treated by the Plaintiff as partial settlement of the amount due by the Defendant to the Plaintiff in Disneyland Project. The main issue 10.The main issue in this application is what the said 2 payments made by the Defendant to the Plaintiff were for. This involves a consideration of the law on appropriation of payments. The relevant legal principles 11.The relevant legal principles on appropriation of payments have been summarized by the learned editors of Chitty on Contracts, 29th ed. (2004), para.21-059 and 21-061 as follows:
12.These principles have been accepted by the Court of Appeal in Murdoch Investments Inc. v. Yangtze Coaxial Cable Ltd., CACV 123/2000 as correct. Discussion 13.It is common ground that the Defendant did not expressly communicated to the Plaintiff what the 2 payments were for. 14.As I have noted above, the Plaintiff’s position is that the 2 payments were made in compliance with the payment obligation imposed by the Plaintiff in the Plaintiff’s letters dated 22nd, 25th and 29th April 2005 respectively. Is that the case? 15.Mr. Wong, the solicitor representing the Plaintiff, has taken me through the correspondences between the parties to illustrate that there had been a dispute between the parties in relation to Disneyland Project as early as in November 2004 and that the Plaintiff had on various occasions alleged different amounts then owed by the Defendant to the Plaintiff in relation to Disneyland Project. 16.In particular, Mr. Wong draws my attention to the following letters:
17.Mr. Wong is quite unable to explain at the hearing the difference in the outstanding amounts alleged in these letters. There is also no evidence that the Defendant has ever accepted the amounts stated in those letters to be due from the Defendant. 18.Mr. Wong is also unable to illustrate how the 2 payments made by the Defendant can be said to relate to these letters. In any event, the payment of $45,000 made on 26th April can certainly not be referable to the demands made subsequently in the Plaintiff’s letter dated 29th April and 4th May. 20.The Plaintiff has failed to satisfy me that the 2 payments made by the Defendant were made in compliance with any payment obligation imposed by the Plaintiff in the said letters. 21.I now turn to the Defendant’s contention. Miss Cheung, counsel for the Defendant, submits that the Defendant’s intention has always been that the 2 payments were made to settle the Defendant’s liability under the 4 dishonoured cheques. She relies on the fact that:
22.Miss Cheung therefore submits that the Defendant has impliedly elected to appropriate the payment of $45,000 on 26th April 2005 to extinguish the Defendant’s liability under cheque no. 805533 and appropriate the payment of $150,046 on 30th April 2005 to extinguish the Defendant’s liability under cheque nos. 805534, 805535 and 805536. 23.Is the Defendant’s contention acceptable in law? In other words, can the Defendant impliedly elect to appropriate the 2 payments to settle its liability under the 4 dishonoured cheques by reason of the identical amounts? 24.Similar question came before the Court of Appeal in Murdoch Investments Inc. v. Yangtze Coaxial Cable Ltd., CACV 123/2000. That was a distraint case. The relevant facts have been summarized by Keith JA as follows:
25.After quoting the legal principles from Chitty on Contracts stated above, Keith JA continued as follows:
26.In his judgment, Keith JA said:
27.Returning to the present case, I accept Miss Cheung’s submission that the amount of the 2 payments were identical to the amount of the 4 dishonoured cheques. In the circumstances, I have no doubt that the 2 payments was impliedly made to settle the Defendant’s liability under the 4 dishonoured cheques. 28.At one stage, Mr. Wong submits that the reduction of the outstanding amount from $628,133 alleged in the letter dated 29th April 2005 to $478,133 alleged in the letter dated 4th May 2005 is clear evidence that the Plaintiff has elected to appropriate the 2 payments totaling $195,046 to Disneyland Project. 29.To start with, given my above ruling that the Defendant has made an implied election, the Plaintiff’s right of appropriation did not arise at all. In any event, it is clear that $628,133 (per the letter dated 29th April 2005) minus $478,133 (per the letter dated 4th May 2005) equals $150,000 and not $195,046! Mr. Wong is quite unable to explain the discrepancy in the figures. 30.Lastly, the Plaintiff’s contention that the $45,000 paid by the Defendant on 26th April 2005 was not in settlement of cheque no. 805533 is clearly contradicted by its own receipt. According to the Plaintiff’s receipt dated 26th April 2005, the sum of $45,000 was received in payment of “Kowloon Bay footbridge”. This is clear evidence that the Plaintiff has in fact appropriated the $45,000 to Kowloon Bay Project (which is in line with the Defendant’s argument) but not Disneyland Project. Mr. Wong attempts to salvage the situation by submitting at the hearing that the receipt was issued in June 2005 after the parties have concluded a global settlement of all their disputes in both projects and the receipt was backdated to 29th April 2005! Mr. Wong’s submission is not supported by the evidence filed by the Plaintiff and should be disregarded. 31.By reason of the above, I find that the Defendant has impliedly elected to appropriate the payment of $45,000 on 26th April 2005 to extinguish the Defendant’s liability under cheque no. 805533 and to appropriate the payment of $150,046 on 30th April 2005 to extinguish the Defendant’s liability under cheque nos. 805534, 805535 and 805536. 32.Consequently, as at the date of the writ (i.e. 7th May 2005), the cause of action based on the 4 dishonoured cheques was extinguished and the Plaintiff may not maintain its claim in this action. Whether the statement of claim should be struck out? 33.Given my above ruling, should I make an order to strike out the Plaintiff’s statement of claim? 34.In Hutchvision Asia Limited v. Asia Television Limited, HCA 6757/1992, Godfrey J (as he then was) has this to say about the court’s jurisdiction to strike out a defence (in the context of that case) on the ground that it is bound to fail:
35.The above decision of Godfrey J applies mutatis mutandis to applications to strike out pleadings. 36.In my view, this is a case in which I should order the statement of claim to be struck out. My above analysis is based on either admitted or undisputed facts, including documentary evidence. The conclusion that the Plaintiff’s claim is bound to fail is simply inevitable. The fact that the Plaintiff chose to issue the writ to claim on the 4 dishonoured cheques when the Defendant’s liability thereon had already extinguished is an abuse of the court’s process. 37.There is one more matter that I should mention in passing. Mr. Wong has informed me that according to his instructions the parties have concluded a global settlement in the end of May 2005 settling all their disputes concerning Kowloon Bay Project and Disneyland Project including the Plaintiff’s claim in this action and he has instructions to discontinue this action. The Plaintiff has written to the Defendant proposing to withdraw its claim in this action by consent with no order as to costs. The Defendant, whilst not denying the global settlement, maintains that the scope of the global settlement does not cover the claim herein and that the issue of the costs of this action is very much a live issue between the parties. I need not express any view on this latest dispute in the context of this application and it would indeed be inappropriate for me to do so. Suffice it for me to say that my above analysis and conclusion is not influenced by the alleged global settlement. Conclusion and order 38.For the above reasons, I order that the Plaintiff’s statement of claim be struck out under Order 18, rule 19 of the Rules of the District Court and under the inherent jurisdiction of the court on the ground that it is an abuse of the process of the court. 39.Miss Cheung, on a very optimistic note, asks for indemnity costs in the event that a striking out order is made. She relies on various observations in the Hong Kong Civil Procedure 2004 and submits that an order for indemnity costs is justified by reason of the Plaintiff’s conduct in commencing the present action notwithstanding the 2 payments by the Defendant back in April 2005, which is a clear abuse of the court’s process. 40.I do not think I need to go into the authorities in any great detail. It is trite law that the normal basis of taxation should be party and party. An order for taxation on an indemnity basis may be ordered when the circumstances is appropriate. Although I have ruled in favour of the Defendant in its contention that the Defendant has made an implied appropriation for the 2 payments, that conclusion is only reached after examining the circumstances of this case with the benefit of authorities and submission from both sides. In my view, this is not an appropriate case to order indemnity costs. The situation may have been different if there was an express appropriation on the part of the Defendant at the time of payment. 41.I therefore make a costs order nisi pursuant to Order 42, rule 5B(3) of the Rules of the District Court that the costs of the Defendant’s Amended Summons dated 2nd June 2005 be to the Defendant payable forthwith, to be taxed if not agreed and with certificate of counsel.
Mr. Joseph K. Wong of Messrs. Or & Company for the Plaintiff. Miss Janine Cheung instructed by Messrs. Lam and Lai for the Defendant. |
Cases cited in this judgment