Carrier Hong Kong Ltd v. Dickson Construction Co Ltd
Read the full judgment text of HCCT11/2005 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 7 October 2005 before Hon Burrell J.
Construction law — Contract formation — Arbitration agreement — Whether binding contract existed with arbitration clause — Letters headed 'subject to contract' — Unresolved terms and ongoing negotiation — Commencement of work as evidence — Back to back contracts. Dickson Construction Company Ltd (“Dickson”) tendered for a project with ASD naming Carrier Hong Kong Limited (“Carrier”) as nominated HVAC subcontractor with an agreed price of $33 million. Carrier disputed that a binding contract containing a written arbitration agreement existed. The arbitrator found such contract existed incorporating a standard form domestic subcontract with arbitration clause 18.2. Carrier applied to the High Court under RHC Order 73 rule 3(2) to challenge this finding, arguing key terms remained unresolved, ‘subject to contract’ letters prevented agreement, work was preparatory and not evidential, and uncertainty as to applicable arbitration clause. Applying established legal principles, the Court held: a binding contract may exist despite unresolved non-essential terms; ‘subject to contract’ wording was conditional on ASD acceptance which occurred; lengthy work performance supported contract existence; minor post-formation price adjustments do not negate contract; and the arbitration clause incorporated by the blue form subcontract is applicable notwithstanding back-to-back main contract arbitration provisions. Carrier’s application was dismissed with costs to Dickson.
Legal issues: Existence of binding arbitration agreement · Effect of 'subject to contract' wording on contract formation · Whether ongoing negotiations and unresolved terms preclude contract formation · Whether commencement of work constitutes evidence of contract · Certainty of applicable arbitration agreement
Outcome: Carrier’s application under Order 73 rule 3(2) dismissed; arbitrator’s jurisdictional finding upheld
|
HCCT11/2005 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.11 OF 2005 -------------------------
BETWEEN
---------------------- Before : Hon Burrell J in Court Date of Hearing : 28 September 2005 Date of Judgment : 7 October 2005 ----------------------- J U D G M E N T ----------------------- 1.This is an application by Carrier H.K. Ltd (“Carrier”) who is the respondent in an arbitration, for a declaration under RHC Order 73 rule 3(2). The claimant in arbitration, Dickson Construction Company Ltd (“Dickson”) has instituted proceedings against Carrier under the Arbitration Ordinance, Cap. 341. Carrier has challenged the fact that there is any arbitration agreement which binds the parties. Consequently the parties agreed to submit to an arbitrator, Ms Teresa Cheng SC, a preliminary question namely whether the parties were bound by a contract which contained an arbitration agreement. On 7 January 2005 the arbitrator published a partial final award in which she found that a binding contract did exist, that it contained an arbitration agreement in writing and therefore, that she had jurisdiction to hear the dispute between the parties. 2.Carrier now seeks a declaration from this court that the arbitrator’s declaration that she had jurisdiction was wrong. 3.By RHC Order 73 rule 3(2) this court may re-hear the arguments. It can receive evidence which was not before the arbitrator. It is a hearing de novo in which the court can confirm or reverse the arbitrator’s finding. Before the arbitrator the onus was on Dickson to establish that an arbitration agreement which bound the parties existed. The same onus applies in this hearing. Both sides have filed further evidence since the publication of the partial final award. The further evidence relates to one sub-issue only. One of the issues before the arbitrator was the nature and extent of the works actually carried out by Carrier when they were on-site between October 2002 and March 2003. Carrier’s case was that it was of a limited and preparatory nature. Dickson’s case was that it was more than preparatory. The further evidence is on this subject. It adds little to the key questions to be answered. 4.Carrier have been represented by Mr Peter Graham both before the arbitrator and in this application. Mr Rimsky Yuen SC leading Mr Victor Dawes, neither of whom appeared below, have appeared on behalf of Dickson. BACKGROUND 5.As this is, in effect, an appeal by way of a re-hearing it is necessary to set out exactly what the arbitrator’s decision and findings were. However, in order properly to understand them, a brief outline of the background will help to put them in context. 6.Dickson, in early 2002 were putting together a tender to the Architectural Services Department (“ASD”) who was the employer in a forthcoming project. The deadline for the tenders was 3 May 2002. Dickson had invited Carrier to be it’s nominated HVAC sub-contractor (Carrier bearing on the ASD approved specialist sub-contractors list). In its tender to ASD Dickson was required to name its chosen sub-contractor and to disclose the agreed sub-contract price. There can be no doubt that prior to 3 May 2002 Carrier knew that they were being nominated by Dickson, knew that a price of $33 million had been entered in the tender, knew the scope of the works to be carried out, knew that Dickson was hoping to be appointed as main contractors by ASD and knew that, if successful, that would be a “back and back” contract with ASD. ARBITRATOR’S FINDINGS AND DECISION 7.It is common ground that not everything was agreed in early May 2002. Some matters were outstanding. One in particular was referred to by Carrier by its letter of 2 May 2002. That was the right to vary the price depending on the variations in foreign exchange rates affecting the purchase of equipment. A second matter, which emerged later, was the price, if any, of variation orders. 8.Nonetheless, the arbitrator found that the essential terms had been agreed. She found that Carrier had intended to be bound and not only did they know that $33 millions was the price that had been submitted to ASD but also that Carrier had agreed that price. It was one of those familiar situations in the Hong Kong construction industry where a sub-contractor had to make a decision whether it wanted the job or not. If it did, it was well known to an experienced sub-contractor such as Carrier that its proposed contract with Dickson would be a “Standard Form Domestic Sub-contract” using the “blue form” which necessarily incorporated a written arbitration agreement in clause 18. 9.In addition to finding these matters outlined in the “background” above, the arbitrator, in support of her finding that Carrier knew that $33 million was the agreed price on 2 May 2002 made a specific finding that on 2 May 2002 in the course of telephone conversations Mr Hung of Carrier offered to do the work for $33 million and Mr Chin of Dickson accepted the offer. Mr Chu of Dickson corroborated this evidence. All the evidence before the arbitrator was by affirmations and documentation. Both parties were invited to call witnesses before the arbitrator. Neither accepted the invitation. The re-hearing before this court has been on the same basis. CARRIER’S COMPLAINTS 10.Carrier’s primary submission is that the arbitrator was wrong to conclude that Dickson had satisfied the onus upon it to demonstrate that a binding contract containing a written arbitration agreement had come into existence which thereby founded the jurisdiction upon which the disputes between the parties could be resolved by arbitration. 11.The main issues, which they submit should have caused her to reach a different decision are as follows :
APPLICABLE LEGAL PRINCIPLES (a) For an arbitration agreement to bind the parties it must be clear that both parties so intended and the agreement must be in writing 12.This principle is spelt out in Aughton Ltd v. M.F. Kent Services (1991) 57 BLR where it was stated that :
13.It is also a requirement by section 2 AC of the Arbitration Ordinance Cap. 341. (b) An agreement to carry out works may be complete and binding in spite of the fact that a number of details have yet and be agreed or finalized. This is particularly so in the construction industry. A binding agreement may, in any given case depending on its own facts, be inferred from a consensus on the basic, albeit essential, terms 14.The 29th edition of Chitty on Contracts refers to this issue in the following way :
15.The point is also made in Matsui Babock Energy Ltd v. John Brown Engineering Ltd (1996) 51 Con LR 129 :
16.In a more recent decision, Ward LJ (in ACT Construction Ltd v. E Clarks & Sons (2002) BWCA 11) went further still and stated that even a failure to finalize the price and scope of works was not necessarily fatal to a finding of an agreement :
(c) The consequence of Carrier’s letters of 2 and 4 May 2002 being headed “subject to contract” 17.The meaning of the phrase is not as strict as contended for by Carrier. Carrier relies on a conveyancing case for its meaning (Mui Foon v. Land Development Corporation, HCMP6219/1998). I find it more helpful to apply Hudson’s Building Engineering Contracts 11th edition :
THE FACTS 18.Having set out some of the important legal principles I turn to an outline of the facts. Many of the facts were not in dispute. On a consideration of all the evidence, both on affirmation and in the documents, particularly the correspondence, I am satisfied of the following facts, which form the basis of my decision :
THE DECISION 19.In my judgment, the application of legal principles to the facts, summarized (not comprehensively) above results in Carrier’s application being dismissed. The essential reasons being as follows :
20.In summary, I agree with the conclusions reached by the arbitrator. I have come to the same conclusions for the same reasons. Carrier’s application under Order 73 rule 3(2) is dismissed with a costs order nisi in Dickson’s favour.
Mr Peter Graham, instructed by Messrs Deacons, for the Applicant Mr Rimsky Yuen, SC leading Mr Victor Dawes, instructed by Messrs Peter Lau & Co., for the Respondent | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||