Li Lo Sha Rosa v. The Incorporated Owners of Hiu Kwong Court and Hiu Ming Court
Read the full judgment text of DCCJ 1728/2004 on BabelCite. This District Court judgment.
1. This is an application by the plaintiff for interlocutory judgment with damages to be assessed under Order 14 rule 1 of the Rules of District Court. After hearing submissions from counsels from both parties, I gave unconditional leave to defend. I now state my reasons.
Cites 2 cases
|
DCCJ 1728/2004 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO. 1728 OF 2004 -------------------- BETWEEN
-------------------- Coram: Deputy Judge A. Chow in Chambers Date of Hearing: 6th June 2006 Date of Handing Down Judgment: 8th June 2006
_________________ JUDGMENT _________________ 1.This is an application by the plaintiff for interlocutory judgment with damages to be assessed under Order 14 rule 1 of the Rules of District Court. After hearing submissions from counsels from both parties, I gave unconditional leave to defend. I now state my reasons. The claim and defence 2.The plaintiff is the owner of the premises known as Flat No. 12, 5th floor, Hiu Ming Court, No. 30 Hiu Kwong Street, Kowloon Hong Kong (the “Premises”). The plaintiff alleged water and foul liquid leaked into the Premises through damaged common sewage pipe of the Building. The plaintiff seeks damages for nuisance against the defendant for an amount to be assessed. 3.The defence was a simple general denial. The plaintiff's argument 4.The plaintiff's case was there is no arguable defence because there are overwhelming evidences that the source of the water leakage was the common sewer pipes. 5.The plaintiff's overwhelming evidence are:
6.The defendant's argument was there are other possible sources for the water leakage. 7.The defendant's evidence are:
8.The defendant's expert report identified four other possible sources for the water leakage in the Premises:
The law 9.The legal principle is well known: The defendant must show that there are triable issues. He has to satisfy the court that he has a 'real or bona fide defence.' If he makes an allegation, it must be credible or believable in the light of the evidence placed before the court. [Para 14/4/9 Hong Kong Civil Procedure 2006]. 10.Clearly, there are considerable disputes as to facts, all of which must be investigated and considered in a full trial. Specifically, the experts disagreed on what was the source or sources of the water leakage. These expert opinions must be subjected to cross-examinations and they must be allowed to clarify their positions. 11.To determinate liability at this stage would inevitably require a “mini trial” on the affidavit, which is totally inappropriate. 12.As to the appropriate costs order, I invited counsels for the parties to address me on costs after I held that there would be unconditional leave to defend. 13.Mr. Cheung, for the plaintiff, simply said since I have not dismissed the application, costs should be in the course. 14.Mr. Lee, for the defendant, submitted a letters from the defendant's solicitors to the plaintiff's solicitors, dated 25/5/2006, two weeks after the defendant's affirmation in opposition to the O.14 application was served on the plaintiff. This latter invited the plaintiff to withdrew the summons and vacate this hearing. The plaintiff failed to do so and Mr. Lee argued I should dismiss the application and order costs for the defendant, payable forthwith. 15.I am fully cognizant of the fact that O.14 r.7 specified that I may order the plaintiff to pay costs of this application forthwith, if before the issue of the summons the plaintiff knew that the defendant has an arguable defence; however, this is without prejudice to the general power to order costs under O.62 r.4 (1). [Para 14/7/4 Hong Kong Civil Procedure 2006]. 16.Here the plaintiff filed the O.14 summons on 2/6/2004, almost immediately after pleadings were closed. At the time the summons was filed, the two expert reports, relied heavily by the plaintiff in this application, were not even prepared. The Brooks Report was not commissioned until 29/7/2004 and the PWL Report not until 25/10/2005. On 2/6/2004, the plaintiff had little or no evidence on what was the source of the water leakage. 17.In other words, when this summons was filed, the plaintiff did not know its own case, let alone whether the defendant had an arguable defence. 18.Mr. Justice Godfrey J.A. in Man Earn Ltd. v. Wing Ting Fong [1996] 1 HKC 225 stated:
19.Mr. Justice Godfrey J.A., in Skink Ltd (in liq.) v. Comtowell Ltd. & Another [1994] 2 HKC 286, also stated:
20.The plaintiff clearly did not pay heed to Justice Godfrey's warnings. 21.In view of the fact that as soon as the defendant's affidavit is served, it should have been obvious to the plaintiff that there are conflicting expert reports and clear factual disputes. This was clearly not an appropriate case for an O.14 application, yet the plaintiff refused to withdraw this application when invited by the defendant's solicitors to do so. 22.Under the circumstance, it is appropriate for me to exercise my discretion and order costs against the plaintiff, payable forthwith. Order
Mr. Victor C.F. Cheung instructed by Messrs. Kitty So & Tong for Plaintiff. Mr. James Lee instructed by Messrs. Kwok & Chan for Defendant. |
Cases cited in this judgment