Wh-scg Jv Ltd v. Hong Kong Construction (Holdings) Ltd
Read the full judgment text of HCCT 48/2006 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 9 August 2006 before Hon Reyes J in Chambers.
Construction law — Sub-contracts — Arbitration agreements — Whether arbitration clause in the main contract applies to sub-contract disputes — Interpretation of contract clauses about substitution of parties — No clear wording to extend arbitral rights between sub-contractor and main contractor — Refusal to rectify contract without irrefragable evidence. AP City engaged HKC as main contractor for residential development; HKC subcontracted WH-SCG JV Limited. WH-SCG claimed unpaid sums under the sub-contract. HKC sought to stay the court action to refer disputes to arbitration under the main contract’s conditions, which included an arbitration clause. The court analyzed the wording of Particular Conditions clause 1, rejecting the argument that WH-SCG and HKC were parties to the arbitration agreement by virtue of substitution mechanisms. Arbitration was not an obligation or liability undertaken but a dispute resolution means. The court declined to read the arbitration clause so as to bind WH-SCG and HKC without clearer language, and rejected the request for rectification due to inadequate evidence. Outcome: HKC’s stay application dismissed; costs to be determined.
Legal issues: Whether the arbitration clause in Conditions cl. 35 applies to disputes between WH-SCG and HKC
Outcome: HKC’s application to stay proceedings and compel arbitration dismissed
Cited by 1 case
|
HCCT 48/2006 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 48 OF 2006 ______________________ BETWEEN
______________________ Before : Hon Reyes J in Chambers Date of Hearing : 9 August 2006 Date of Judgment : 9 August 2006 ______________________ J U D G M E N T ______________________ I. INTRODUCTION 1.In November 1999 AP City as Employer engaged Hong Kong Construction (HKC) as Main Contractor for a Stubbs Road residential development. HKC sub-contracted the work to WH-SCG. 2.WH-SCG claims that certain amounts are due under its sub-contract with HKC. HKC denies this. WH-SCG accordingly commenced this action against HKC for the amounts said to be due and unpaid. 3.By its application today, HKC seeks to stay WH-SCG’s action to arbitration. According to HKC, under the Sub-Contract, WH-SCG agreed that disputes would be referred to arbitration. The question is whether HKC is right. II. BACKGROUND 4.Clause 1 of the Particular Conditions of the Sub-Contract (the Particulars) provides as follows:-
5.The Conditions of Contract (the Conditions) forming part of the Main Contract were annexed to the Sub-Contract. 6.Clause 35 of the Conditions provided for the arbitration of disputes under the Main Contract as follows:-
III. DISCUSSION 7.Mr. Simon Westbrook SC (appearing for HKC) argues that, under the Sub-Contract, it was intended that WH-SCG should perform HKC’s obligations under the Main Contract. 8.This plainly means (Mr. Westbrook submits) that the parties intended by Particulars cl. 1 that WH-SCG’s and HKC’s names should be substituted for the words “Main Contractor” and “Employer” respectively wherever they appear in the Conditions (including cl. 35). 9.The result (Mr. Westbrook says) is that Conditions cl. 35 (as modified by Mr. Westbrook’s interpretation of the effect of Particulars cl. 1) would constitute an arbitration agreement between WH-SCG and HKC. 10.Mr. Westbrook accepts that, taken literally, Particulars cl. 1 would not have the result for which he contends. Particulars cl. 1 only provides at most for the substitution of WH-SCG’s name for that of HKC in the Conditions. Nothing is said in Particulars cl. 1 about reading HKC’s name in place of references to the Employer in the Conditions. 11.But (Mr. Westbrook reasons) to read Particulars cl. 1 so literally would lead to an absurd result as far as Conditions cl. 35 is concerned. That is because (Mr. Westbrook points out) WH-SCG as Sub-Contractor has no contractual relationship with either the Employer or the Architect. Absent a direct contractual nexus, there could be no dispute arising out of the Sub-Contract which was capable of arbitration between WH-SCG and the Employer. 12.I am not persuaded by Mr. Westbrook’s argument. I think that the meaning and effect of Particulars cl. 1 are plain. 13.By the 1st paragraph of Particulars cl. 1 WH-SCG agreed to assume “all obligations and liabilities” of HKC under the Main Contractor. 14.As far as arbitration is concerned, it would be odd to describe arbitration as either an “obligation” or “liability” of HKC under the Main Contract. 15.Arbitration is rather a means of resolving disputes relating to the performance of HKC’s obligations and liabilities under the Main Contract. 16.Thus, it would be straining language to say that by the 1st paragraph of Particulars cl. 1 WH-SCG agreed to undertake HKC’s “obligation” or “liability” to arbitrate under Conditions cl. 35. 17.The 2nd paragraph of Particulars cl. 1 provides that whenever the term “Main Contractor” is used in the Main Contract (including the Conditions) it shall be treated as referring to WH-SCG. It seems to me that this paragraph has to be read as impliedly subject to the 1st paragraph. It is the means by which the parties have chosen to implement the responsibilities assumed by WH-SCG under the 1st paragraph. 18.Thus, in the absence of clear words, I do not think that the 2nd paragraph necessarily applies to all appearances of the term “Main Contractor” in the Conditions. The 2nd paragraph must be read as implicitly subject to a qualification. The expression “Main Contractor” in the Main Contract is to be treated as a reference to WH-SCG insofar as it makes sense to do so, in light of the obligations and liabilities which WH-SCG has agreed to undertake under the 1st paragraph. 19.The 3rd paragraph of Particulars cl. 1 must be read as similarly qualified. The expression “Contract” wherever it appears in the Main Contract should be deemed to refer to the Sub-Contract, insofar as it makes sense to do so in light of WH-SCG’s undertaking in the 1st paragraph. 20.The 4th paragraph of Particulars cl. 1 gives WH-SCG a means of redress against the Employer in the event of any dispute over its performance of HKC’s obligations as Main Contractor. By the 4th paragraph HKC agrees (among other matters) to allow WH-SCG to use HKC’s name to obtain any rights available under the Main Contract. 21.The right to have disputes arbitrated is one such right of HKC under the Main Contract with the Employer. To circumvent the fact that no privity of contract exists between WH-SCG and the Employer, HKC will lend its name so that WH-SCG can (say) arbitrate disputes relating to its performance of relevant works with the Employer. 22.Nothing in the remaining paragraphs 5, 6 and 7 of Particulars cl. 1 affects the foregoing analysis. I do not find any absurdity (contrary to what Mr. Westbrook suggests) in reading Particulars cl. 1 along the lines which I have sketched out. 23.I appreciate that it is tempting to read Conditions cl. 35 in the way that Mr. Westbrook advocates. But I do not see how I can do so without clearer words to such effect. 24.The particulars fail to specify that references to “the Employer” in the Conditions should be taken to mean HKC. It is not the Court’s function to make up for the alleged deficiency in drafting without much stronger indication that such is actually what the parties here intended. This is especially the case where the parties have chosen to adopt a precise mechanism (reflected in Particulars cl. 1) for imposing HKC’s obligations and liabilities under the Main Contract on WH-SCG. This is not a case where the parties have used vague, general words and the Court is asked to do its best to construe those words. 25.It seems to me that in this case Mr. Westbrook is effectively asking me to rectify the parties’ agreement. He is saying that the specific mechanism of Particulars cl. 1 fails to reflect the parties’ true intentions. 26.I bear in mind the test for rectification. Before it can rectify, the Court requires “irrefragable” evidence that what has been recorded in a written contract does not reflect the parties’ true agreement. I do not think that the evidence here comes anywhere near meeting the test for rectification. 27.Both sides have referred to background material indicating that HKC and WH-SCG intended the Sub-Contract to be “back-to-back” with the Main Contract. The words “back-to-back” were actually used in negotiations between HKC and WH-SCG. 28.But “back-to-back” is at best a vague expression. It is neither a legal nor a technical term. I derive little help from it as an aid to construing Particulars cl. 1. 29.“Back-to-back” can mean many things. It may simply mean, for example, that it was envisaged that WH-SCG would undertake, “back-to-back,” all HKC’s performance obligations and liabilities under the Main Contract. Use of the expression does not necessarily imply that the arbitration agreement in Condition cl. 35 was intended to apply between HKC and WH-SCG. IV. CONCLUSION 30.HKC’s application for a stay is dismissed. I shall now hear the parties on costs.
Mr Jeevan Hingorani, instructed by Messrs Simmons & Simmons, for the Plaintiff Mr Simon Westbrook, SC and Ms Rachel YK Lam, instructed by Messrs Woo, Kwan, Lee & Lo, for the Defendant | ||||||||||||||||||||||||||||||||||||||||||
Other judgments that cite this case