Chow Kee James t/a Tapbo Civil Engineering Co v. Transway Construction & Engineering Ltd t/a Wo Kee Construction & Engineering Co
Read the full judgment text of HCCT 11/2006 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 19 December 2006 before Deputy High Court Judge Gill.
建築合同 — 分包合同與主合同之背靠背條款解釋 — Delayed completion and liquidated damages — Interpretation of variation orders and daywork records — 勞工工資拖欠與法定責任 — 罰金條款與預估損失的區別 — 拒絕承認超出合同範圍的額外收費 — 分包合同終止及餘工責任。本案中,Tapbo作為主承包商與WSD簽訂公共水管工程合同並將主要工程分包予Wo Kee。二者因工程延誤、材料及服務費用結算產生爭議。法院確定分包合同明確採用back-to-back條款承接主合同義務,Wo Kee須對工程延誤負責,遲延罰金非罰金性質並採用合理日率計算。Wo Kee須為其遲延及相關款項承擔責任。法院批准Tapbo對部分燃料及服務費用請求,否定部分不符約的收費。法院支持Tapbo以合理理由終止分包合同,並允許其以第三方完成餘下工程後向Wo Kee求償。最終判決Wo Kee須向Tapbo支付淨額346,853.84港元,並由Wo Kee負擔3/4訴訟費用。該判決於2008年上訴駁回。
Legal issues: Interpretation of back-to-back provisions in subcontract · Liquidated damages是否構成罰金條款 · Wo Kee是否對延遲負責 · 物料及服務費用的計算及扣除 · 分包合同終止及剩餘工程責任
Outcome: 判決Tapbo勝訴,確認Wo Kee對其應付款346,853.84港元負有支付責任。Wo Kee須承擔Tapbo 3/4的訴訟費用。
Cites 1 case
|
HCCT 11/2006 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 11 OF 2006 (Transferred from DCCJ No. 3565 of 2005 and HCA No. 1203 of 2005) ____________ BETWEEN
____________ Before: Deputy High Court Judge Gill in Court Dates of Hearing: 13-16, 20-22, 28-29 November 2006 Date of Judgment: 19 December 2006 ______________ J U D G M E N T ______________ 1.The plaintiff, Tapbo, is a construction company whose sole proprietor is authorised to tender for public works contracts. Through Tapbo, he tendered to lay a line of waterpipes to run underneath Castle Peak Road, New Territories, and was successful. This resulted in a contract with the Water Supplies Department (WSD) designated WSD Contract 13/WSD/01. I shall call this the Main Contract. It was dated 5 December 2001. The contract sum was $7,171,000, subject to adjustment. 2.Tapbo caused some preliminary work to be carried out, then sub-contracted the balance of the project to the defendant, Wo Kee. This was recorded on a single page letter from Tapbo to Wo Kee, incorporating 9 schedules. Wo Kee endorsed its acceptance on the letter. The date of the letter, and thus of the subcontract, was 1 March 2002. I shall call this the Subcontract. 3.Details of the Subcontract will follow. Suffice for the meantime to note that in schedule 2 headed “Basic Conditions and Specifications” it was recorded that the documents were to be “back-to-back” the contract documents in the Main Contract, but subject to departures therefrom set out in the remaining schedules. The Subcontract sum was $6,653,709, subject also to adjustment. 4.Work proceeded. But during the course of the project Tapbo received notice that certain employees of Wo Kee and of Wo Kee’s subcontractors had filed claims for wages not paid, and thus it became statutorily bound to meet what was owing out of the Subcontract price. Having done so it looked to Wo Kee for reimbursement. When that was not forthcoming it brought this action. 5.The sum pleaded for being $282,250.74, Wo Kee does not challenge its obligation to meet this debt, together with further sums associated with the wages claims. The dispute concerns its counterclaim, or set-off, for a far greater sum, which it claims to be owing as the balance of the Subcontract price as adjusted. 6.Tapbo’s challenge to this was that it had suffered financial loss as a result of delays by Wo Kee and other breaches of the Subcontract. Further, that it was owed money for materials and services supplied to Wo Kee and for more wages it was asked to pay, and attendant administration charges, to the extent that allowing for what had been paid Wo Kee was entitled to nothing more; indeed it had been overpaid. 7.Following the filing of the action and through to mid-trial, the parties’ through their legal representatives were constantly negotiating to narrow their differences, and did achieve significant agreement. 8.I shall come to the particular areas of dispute and in detail the amounts claimed and counterclaimed. Suffice for the meantime to state that the issues broadly speaking fall into two areas; the first, an interpretation of the terms of the Subcontract; for instance, what is meant by back-to-back with the Main Contract? The second, findings of fact from which to calculate what is due to Wo Kee under the Subcontract, how much Tapbo is entitled to set-off for materials and services supplied, and what went wrong, and who is responsible and liable. 9.Before going into details it is apparent that difficulties that became insurmountable leading to this action stem from the circumstances whereby the parties primarily involved, namely WSD as employer/payer and Wo Kee as contractor/payee were not and are not now contractually joined, so that issues as they developed had to be dealt with through the middleman Tapbo. And Tapbo’s role, apart from protecting its profit in the “sale on” of the lion’s share of the Main Contract, was a supervisory one. 10.I come now to look at the essential terms of the two contracts, and how they came into being. The Main Contract 11.The primary documents are the following:
The Tendering Process 12.The standard procedure is that the tenderer receives the above documents for consideration. The Bills of Quantities will spell out the work to be carried out. In this tender it included a breakdown of the preliminary work, site clearance, watermains laying and dayworks. 13.The employer, in this case the WSD, assesses the expected quantity of works to be undertaken in respect of each Bill. It then falls to the tenderer to fix upon a rate it is prepared to charge for the performance of each Bill; the sum total of that plus a contingency fee becomes the tendered amount and, if accepted, the contract price. 14.Thus it was that Tapbo submitted a total tender of $7,171,000 which was accepted and thus became the Main Contract Price. 15.An important feature of the costing of a contract of this sort is that under the General Conditions it is agreed that the quantities set out in the Bills of Quantities are estimates only. The actual amount of work carried out for each individual work description is established by an Engineer appointed by the employer; in this case the WSD. 16.Thus the final Main Contract Price may very well vary from the amount tendered and accepted, not because the rate has been changed, but because, as determined by the Engineer, the quantity has become an exact instead of approximate calculation. 17.It would not be productive to summarize more than the bare essentials of the Main Contract. Suffice for the meantime to highlight particular characteristics by bullet points:
The Subcontract 18.The letter of 1 March 2002 recording the offer and acceptance, I come to summarize the contents of the schedules; at least those material to the dispute. Schedule 1 Headed “Subcontract Particulars” it recorded the extent of the work to be undertaken at a rate established in the Preambles to the Bills of Quantities and the Bills of Quantities settled between the parties. It recorded the Subcontract sum. It provided for the duration — 180 days from 4 March 2002; that it is, to 30 August 2002. It recorded under the sub-heading “Extension of Time” back-to-back from Main Contract between WSD and Tapbo, and under the sub-heading “Liquidated Damages” back-to-back from schedule 2. It provided for a maintenance period of 12 months. Schedule 2 This recorded under the head “Basic Terms and Conditions” — all documents in this schedule to be back-to-back to the documents of the Main Contract, except that the contents of schedules 1 and 3 to 9 shall take precedence where there is a clash. Schedule 3 This is a particularly significant schedule having regard to the areas of dispute; I propose thus to repeat its contents verbatim as follows:
Schedule 4 Under the head “Contract Drawings Specification and Construction Information” is reference to numerous drawings and site investigation reports, and under the sub-heading ‘Others’ — “Wo Kee is deem(ed) to (be) responsible for design (temporary works whole pipejacking works and method of construction) supplies (all materials except those to be supplied by WSD) execute, test inspect and commission the whole works in full compliance to the captioned in terms of their implied physical, technical, time and quality requirements.” Schedule 5 This incorporates the Preambles and Bills of Quantities, broken down into preliminary activity and site and works management and supervision, classified unmeasurable, and the excavation and pipelaying and assorted works which were subject to remeasurement. Schedule 6 and 7 The contents of these are not significant to the dispute. Schedule 8 Under the head “Schedule of Contra-Charges” are listed the charge out rates for materials which had to be bought from Tapbo under clause 3.4 schedule 3, for which no administration charge was to be incurred. Schedule 9 The contents of this schedule are not relevant either. The Cast 19.Those who played a particular role during the history of events include the following: Peter Yeung. He was an employee of Tapbo under the title of project manager and a sometime appointed Site Agent, as approved, on the site. Jason Poon. Also an employee of Tapbo, he was designated project manager, whose role was to act as a co-ordinator between WSD and Wo Kee, and be answerable to Lam Shiu Ming. Lam Shiu Ming. He is a director of Great Bill Limited, a company associated with Tapbo and responsible for administration and the management of Tapbo. He did not have direct involvement in the project, but Jason Poon was required to report to him. He had the capacity and authority to produce documents of contract, correspondence and other documents in the custody of Tapbo. Danny Lam. He is a director of Wo Kee and supervised Wo Kee during the course of the project. Tony Fung. He is a QS by profession and was employed by Wo Kee during the period September 2002 to April 2003. Alfred Lau. He is an office administrator employed by Wo Kee, and was responsible for correspondence relating to the project and other administrative duties. 20.Of the above, all but Peter Yeung and Jason Poon made witness statements and gave evidence. Messrs Yeung and Poon have since left the employ of Tapbo and were not available to participate. The Work was Substantially Carried Out 21.WSD’s Engineer certified substantial completion on 12 February 2003, some time after the scheduled due date. By this time the parties were in significant dispute over claims for moneys said to be due to Wo Kee on the one hand and contra charges claimed by Tapbo on the other. Wo Kee was ordered off site and Tapbo undertook the remainder of the work outstanding. 22.So, there remained to be resolved what was owing, and by whom, to whom. 23.What was agreed, up to midway through the trial, was that Wo Kee was entitled to charge, subject to any counter charges and additional charges, for work carried out, the sum of $4,342,465.83, made up as follows:
24.I come now to deal with those matters in dispute. The Disputed Amounts 25.Against the agreed sum of $4,342,465.83 Tapbo claims the right to withhold $4,302,882.58 made up as follows:
26.I come next to analyze those of the above claims and counterclaims which remain in contention. Materials Supplied by Tapbo 27.In respect of this series of charges, $1,426,919.30 is agreed. The remaining items in dispute totalling $389,336.27, now follow. 28.Industrial diesel oil — $131,912.15. It is not disputed that this was utilized in generators of Tapbo to supply electricity to the site. It is contended by Wo Kee that to charge for the cost of the fuel to provide electricity is to be in breach of paragraph 1.4(a) of schedule 3 which records that the supply of temporary electricity to the site was to be free of charge. But that fails to recognize the exception, being the cost of fuel, specifically set out in 1.4(a). Whether or not this took Wo Kee by surprise, on an ordinary meaning of the sub-paragraph, Tapbo is entitled to be reimbursed this amount in full. 29.Traffic signs — $7,660, TTA Materials — $29,374.45 Miscellaneous — $3,685.80. Wo Kee claims protection from this cost under 1.4(c) of schedule 3, the signs being an integral part of the TTA equipment as required on the approved TTA plans. The response from Tapbo is that it does not dispute that it was not able to pass on the cost of TTA equipment on the TTA plans as originally approved. But this was the cost of signage on a revised 3-stage TTA plan. It is not disputed this was approved by 25 April 2002. What is disputed is by whom it was applied for. But Wo Kee contends that even if (which is denied) it initiated the request the Subcontract did not permit a charge. It seems to me and I so find that the revised TTA plan was required to accommodate Tapbo’s decision to revise the original programme from 5 stages to 3. The signs supplied fell within the category of TTA equipment provided free of charge. The charge of $3,685.50 was for material used during the implementation of TTA. Thus, there should be no charge for these items. 30.Steel H-beams and Sheet Piles — $67,506.50. Wo Kee relies on a letter written on behalf of Tapbo to Wo Kee of 3 March 2003 by Jason Poon, the onsite employee of Tapbo. It is pertinent to note that this equipment was in effect borrowed by Wo Kee and that it was made available free of charge in order to speed up the pipe jacking works. Direct evidence on the point came from Danny Lam who said Jason Poon promised this and support for this is found in the letter itself. It seems that this equipment ‘disappeared’ from site after use; but there is nothing to suggest that Wo Kee took it without authority. I accept the explanation of Wo Kee; there shall be no remuneration under this head. 31.Miscellaneous — $5,750, Gully and Channel Gratings, valve pit cover — $1,830. These minor amounts were said to be for items acquired after the Subcontract had been terminated. I accept this to be so; the charge is disallowed. 32.Asphalt — $141,617.37. Wo Kee’s complaint about this item is that at least part of it is for work carried out after 17 April 2003, by which time the Subcontract had been terminated. There was no breakdown, and no evidence to show when, how and for what purpose the charge was incurred. If, as was suggested, it was used for reinstatement of the road pavement after the outstanding pipe laying had been completed, then this would have been included in the contract rates for this remaining work. Tapbo should have been paid for this and should not be entitled to further recompense. I am not satisfied that Tapbo has made out this charge; I disallow it. Materials Supplied 33.With one of these claims made out in the sum of $131,912.15, this, together with the amount already agreed of $1,426,919.30 now totals $1,558,831.45. Additional Services Provided by Tapbo 34.$636,720.95 is agreed. The remaining items in dispute coming in all to $1,296,426.55, now follow. 35.TTA traffic consultancy — $12,330. The argument against this charge is that it falls into the same category as TTA services to be provided by Tapbo free of charge under paragraph 1.4(c) of schedule 3. I agree; this charge is disallowed. 36.Penalty Charge for Damaging an Existing Water Main — $177,974.90. This is a particularly contentious item. It is not disputed that there was damage to an existing water pipe, during the excavation process, on four separate occasions between 24 August 2002 and 3 January 2003. Liability by Wo Kee is denied. But its primary case is that Tapbo should have reported the matter to its insurer, made a claim and been reimbursed the cost of making good the damage. It contends that Tapbo chose not to; Danny Lam attested that the reason was to avoid having to pay an enhanced premium for future cover. But there was no corroboration of this allegation. It was further its case that the Site Agent, then Peter Yeung of Tapbo, in reporting the incident attached no fault to Wo Kee. In fact, the water pipe was old and in a fragile condition and there was no fault by Wo Kee. Mr S M Lam for Tapbo gave evidence on the point. He claimed the damage was by reason of the negligence of Wo Kee. Of the damage caused on 24 August he stated in his witness statement:
And he gave similar evidence in respect of each of the remaining three incidents. Danny Lam in response said that Wo Kee had taken all necessary steps, including an underground utility survey, and the damage was not due to its negligence. The parties are caught by the provisions of the Main Contract, by virtue of the back-to-back ties with that contract. Under clause 22(1) and (2) of the General Conditions of Contract it is stated:
The remainder of the clause (including sub-clause (3) is not relevant to the circumstances of these incidents. There is nothing to suggest that in anyway WSD or its Engineer caused or contributed to the damage. As I find from the evidence, Wo Kee, using Danny Lam, “shadow wrote” the reports of the incidents and would hardly have made any admissions of liability. Tapbo through Jason Poon wrote this to Wo Kee reverting to the first three incidents:
Danny Lam from the witness box nailed the coffin down when he admitted that Wo Kee did not know the exact location of the water pipe. And, that it was damaged on four separate occasions, tells its own story. Finally, clearly Tapbo was under no contractual or other obligation to report the incidents to its insurance company; in any event, this would have done no more than transfer the claim from insured to insurer. This charge is allowed in full. 37.Settlement Monitoring — $11,875. Wo Kee complains that this falls into the category of surveying undertaken by the plaintiff free of charge, under paragraph 1.4(b) of schedule 3. The counter to this is that it was not surveying for which the charge was rendered, but a separate service altogether, being monitoring during construction, under clauses 26.10 to 26.12 of the Particulars Specifications in the Main Contract. This was thus outside the range of services provided free of charge. I agree. This charge is allowed. 38.Provision of ICE Services — $61,650. This is another disputed charge which turns on a construction point. Wo Kee contends that this service falls into the category of a free of charge service under paragraph 1.4(e) of schedule 3 — and I repeat the provision — “supply of once-off ICE services (second certification due to 1st failure to be back-charged at Wo Kee account)”. The services of an ICE were called upon a number of times through the course of the works. It is the contention of Wo Kee that this was to be free to Wo Kee provided that a second visit was not required for which it would have to pay. This may have been intended by Wo Kee in the negotiating process but it is, in my view, not possible to attribute that to an ordinary interpretation of the words. “Once-off” is clear enough as to what is meant. I find this charge to be made out. 39.Extension of Insurance — $190,639.08 I shall revert to this topic. 40.Provision of Site Agent — $398,606.52. The presence of a Site Agent as a superintendent engaged by the contractor is set out in the GCC at clause 17, thus:
Tapbo’s assertion is that its obligation to appoint a Site Agent under the Main Contract passed to Wo Kee because of the back-to-back provisions of the Subcontract. Wo Kee’s response is that it was under no contractual obligation to provide the Site Agent. Historically, the circumstances surrounding the engagement of a Site Agent during the course of the Main Contract was as follows:
It is pertinent to note that although it recorded an enhanced management team on site Wo Kee did not propose an alternative Site Agent to Mr Yeung. Indeed, he was referred to as Deputy Project Manager. This it did not address the contractual obligation in the Main Contract that there had to be a Site Agent. Thereafter, as an incontrovertible fact, Peter Yeung remained as Site Agent until completion of all the Subcontract works. Although there was some evidence to question whether Mr Yeung thereafter properly fulfilled his duties on site, which he was not called to rebut (he having subsequently left the employ of Tapbo and no longer traceable) there was no complaint raised by WSD about that; certainly nothing was produced. As I find, applying the back-to-back provisions, Wo Kee was contractually bound to appoint a Site Agent and was aware of Tapbo stepping into the breach when it failed to do so and the financial consequences of that. Yet it took no steps to replace Mr Yeung with an appropriately qualified person from its own workforce. Mr Tony Fung was not engaged for the purpose and his name was not put forward as a candidate for approval by WSD. From an originally significantly larger claim Tapbo’s existing claim is not challenged as to quantum. I find its entitlement to this charge made out. 41.Outstanding Works — $443,351.05 (During closing addresses this was reduced by $1,179.36 to $442,171.69). This represents the sum total of three accounts paid by Tapbo to alternative subcontractors following the termination of the Subcontract. It is Wo Kee’s case that the Subcontract was wrongfully terminated on the grounds of slow progress and that it should not be liable for any of Tapbo’s costs following 17 April 2003. The picture painted by Tapbo is a different one, and there is a series of letters which support its cause. The first is of 18 February 2003 complaining of delays totalling nearly half a year, giving final notice to complete ten separate items of work, and directing that Wo Kee vacate the site by 25 March 2003. This was followed by a letter of 26 March and another of 4 April and yet another of 7 April complaining of poor progress. A letter of 8 April extended the deadline to 21 April, save for the construction of a deep washout chamber and associated works, which Tapbo required to be undertaken by its workforce. It is also apparent from the correspondence that WSD was pressing Tapbo to complete and complained of lack of activity on site. I am satisfied that Tapbo has established breach by Wo Kee and an entitlement to the amount claimed for. Liquidated Damages — $546,584 42.This claim derives from the chronic delay in the time taken to complete the work and achieve a certificate of substantial completion. WSD charged Tapbo, applying the daily rate as calculated, by using the formula set out in the Main Contract. This came to $4,019 per day. Tapbo applying the ‘back-to-back’ provision of schedule 1 claims from Wo Kee $4,019 x 136, being the number of days in default, which comes to $546,584. Wo Kee defends the claim on a number of grounds, as follows:
Dealing with these points in turn; first, as to whether the liquidated damages amounted to a penalty. Prima facie, the words may be supposed to mean what they say. The parties to the Main Contract agreed to a formula to establish a daily rate. And as was said by Dickson J in the Canadian case, Elsey v J G Collins Insurance Agencies Ltd (1978) 83 DLR (3d) 1 at p. 15:
Whether a sum stipulated is a penalty or not is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged at the time of the making of the contract; see Dunlop Pneumatic Tyre Co. Ltd v New Garage and Motor Co. Ltd [1915] AC 79. It was stated that to assist in the task of construction there are various tests which may in a given case be helpful or even conclusive, as follows:
But on the other hand:
Turning to this case, which is of course a public works contract, it is, I think, not possible to regard a formula which throws up a daily rate of a little more than $4,000 in a contract worth several millions of dollars as extravagant and unconscionable, as per paragraph (a). Paragraph (b) is not applicable; nor is paragraph (c), for this is not payment of a single sum. In my view, and I so find, the liquidated damages, as agreed, was a meeting of the minds of the parties to achieve a genuine pre-estimate of loss to be suffered per diem. Secondly, as I find, Wo Kee was responsible for the delay. Whatever Tapbo had achieved or not prior to the arrival on the scene of Wo Kee had no bearing or relevance. The history from the time Wo Kee came to the project as revealed by correspondence and evidence adduced points the finger squarely at Wo Kee. Thirdly, if Wo Kee had no knowledge of how the rate was calculated, then it was because it chose not to explore the detail. It signed the Subcontract with knowledge of the existence of a liquidated damages clause. It was entitled to look into this. Fourthly, it would be difficult to show that the back-to-back provision had no application in the Subcontract when it was specifically referred to as being applicable in schedule 1. That the dates of completion of the two contracts are different does not affect things. It was the daily rate that was to be applied. That the rates in the Bills of Quantities are different with no specified daily rate in the Subcontract are matters that Wo Kee could have negotiated to change, if it was thought to be unfair. If it did not know the rates in the Main Contract it was because it chose not to enquire. A compelling feature of a back-to-back provision in a contract is that it requires careful examination of documents stated to be binding on the parties outside the contract itself. I am satisfied the claim for liquidated damages in the sum of $546,584 has been made out. Additional Services Provided by Tapbo 43.I return to this category to deal with the remaining matter; Extension of Insurance — $190,639.08. This stems from Wo Kee’s delay in completing the Subcontract. With that liability established it follows that this charge is a valid one also. 44.I can now total up the amount Tapbo is entitled to for services provided. This comes to $1,282,917.19. Adding this to the agreed sum of $636,720.95, the total is $1,919,638.14. Non-Returned Materials — $6,895.51 45.Tapbo claims this amount for pipe materials which were to be returned to WSD and were not and were thus charged for with 20% on-cost added. Whilst the existence and value of this material is not disputed it was submitted on behalf of Wo Kee that it was not allowed to take the material and did not. In the circumstances I am not satisfied that this claim has been made out and decline it. Wo Kee’s Materials Left on Site — $29,441.60 46.It was Mr Fung’s evidence that when Wo Kee was required to leave the site in April 2003 it left behind eight items of materials valued at this amount. These were identified and recorded in interim payment certificates which were produced. I am prepared to accept this as adequate evidence to establish the charge, and allow it. Variation Order No. 3 — $688,044.21 47.This is the third of three variation orders applied for by Wo Kee. The first two at $80,228.40 have been agreed. VO3 stemmed from a directive from the Engineer pursuant to section 60 of the GCC which gave him power to vary any part of the works necessary for the completion of the works. It arose because of the need to revise the profile of the pipeline at a designated position, known as CH.2 + 85. This was because there were existing utility pipes and services along the intended path of the water pipes being laid. A decision having been made that these were not to be diverted, the direction required a deepening of the required excavation beneath these existing services. The order from WSD came forward on 29 November 2002. Under the Main Contract, the charging for work carried out under a directive issuing under section 60 is determine by section 61, which I record in full:
As to how these charges translate to the Subcontract, one refers back to schedule 3 and therein paragraphs 3.2 and 3.3. From these it is apparent that Wo Kee was required to submit a daywork record sheet to both Tapbo and WSD for approval of its rate for carrying out the work and the overall charge. However, as in the Main Contract, the final arbiter is the Engineer. Wo Kee duly carried out the work. Then it applied to Tapbo for payment. Its total claim was for $1,351,274.47, less a deduction of $259,935.25 for work done in accordance with certain of the BQs and already certified by WSD. Thus the charge was for $1,091,339.22. It is not disputed that in submitting this claim Wo Kee was effectively employing a rate in excess of the contract rate; this upon the basis that in order to negotiate around the existing services excavation by hand had to be undertaken. But WSD rejected this proposition. By letter of 1 March 2004 it responded to Tapbo:
This was passed on to Wo Kee in a letter of 18 March 2004 which concluded with the following paragraph:
It appears this was not responded to; nor was there a response to a letter in similar vein sent on 8 May 2004. And there the matter appears to have been left; at least on paper. At the trial, those representing Wo Kee reiterated why it was that a new rate above the Subcontract rate was justified. But no steps were apparently taken to persuade the man whose decision mattered under the contract; the Engineer. It was argued that a reasonable price should be awarded based on quantum meruit. But that does not work. Quantum meruit cannot arise where there is an agreed sum or an agreed formula from which to arrive at an agreed sum. In this case, Wo Kee had a contractual right to confer and to try to persuade the Engineer to go above the contract rate. No attempt was made to do so. The Engineer’s word on the topic remains final. Is there anything due at all on the VO3? The answer to that is not clear. No attempt seems to have been made to resubmit a claim using approved rates. It was not explained to me as to why the original claim had become $688,044.21. And there was a conflict, from the bar table, as to whether Wo Kee had already been paid the sum of $259,935.25. In the absence of anything definitive, I have to disallow this claim in total. Wo Kee’s Claim for Prolongation Costs — $665,238.91 48.This derives from Wo Kee’s claim that the Subcontract was not completed on time and the resultant delay put it to extra expense which totalled this figure. Mr Yip sumitted for Tapbo that the assertion is defeated by a pleadings point; that the delay is not blamed on Tapbo. And there was no or no adequate evidence to attach responsibility to Tapbo either. I was referred to the case of Toptech Company Limited v Tse Wang Cheung Peter trading as Deluxe Design and Contracting Company (unreported) 1998 CT 17 where Findlay J, in dealing with the defendant’s claim for prolongation costs, said:
I agree that a claim under this head has not been made out, and reject it also. Conclusion
49.There shall be judgment in favour of Tapbo for the amount claimed of $282,250.74, set-off against judgment in favour of Wo Kee in the sum of $629,104.58, to leave a net balance due to Wo Kee of $346,853.84. Costs 50.These are nisi. 51.The lion’s share of the disputed issues were resolved in favour of Tapbo; accordingly, I order 3/4 of Tapbo’s costs to be met by Wo Kee. Liberty to Apply 52.There is liberty to apply if my mathematics do not measure up. Counsel 53.I wish to record my thanks to counsel for both sides, Mr K Yee for the plaintiff and Mr C Y Liu for the defendant, for the extraordinary amount of time and effort they put into their respective roles. The detailed submissions, both opening and closing, accompanied by aide memoire charts were of considerable assistance to me.
Mr K Yee, instructed by Messrs Foo, Leung & Yeung, for the Plaintiff Mr C Y Liu, instructed by Messrs C L Chow and Mackison Chan, for the DefendantAppeal dismissed: see CACV36/2007 dated 21 May 2008 |
Cases cited in this judgment
Further hearings and rulings under HCCT 11/2006