Sam Woo Bore Pile Foundation Ltd v. China Overseas Foundation Engineering Ltd
Read the full judgment text of CACV 113/2006 on BabelCite. This 高等法院上訴法庭 judgment was delivered on 15 March 2007 before Hon Rogers VP, Le Pichon JA, Chu J.
Civil Procedure — Appealability of striking out orders — Application test vs order test — Striking out part of claim interlocutory and not appealable as of right under section 22(1)(a) of Court of Final Appeal Ordinance. Contract Interpretation — Bills of Quantities, Standard Method of Measurement (SMM), Particular Preamble — Whether general principles established applicable to all re-measurement contracts — Court holds decision confined to particular bespoke subcontract, not general application. Contract Interpretation — Meaning of 'min' (minimum) in construction contract — Whether risk of work beyond minimum falls on contractor — Court holds phrase in subcontract assigns such risk to subcontractor as required work below minimum unacceptable; excess to be remeasured. Questions of Public Importance — Court declines to grant leave to appeal on basis that matters are not of great general or public importance due to specific nature of contract. Background: Plaintiff’s claim for extra over work for toeing-in piles struck out in part and appeal dismissed by High Court. Plaintiff sought leave to appeal to Court of Final Appeal; application refused. Legal issues concern appealability of interlocutory orders, contractual interpretation of construction contract documents. Outcome: Leave to appeal refused; appeal dismissed. No final appellate change to construction contract interpretation or procedural stance on interlocutory strikeout orders.
Legal issues: Whether the strikeout order was interlocutory or final · General application of construction principles regarding Bills of Quantities, SMM and Particular Preamble · Interpretation and significance of 'min' in construction contract descriptions · Whether the matter engaged a question of great general or public importance
Outcome: Appeal to Court of Final Appeal dismissed; leave to appeal refused
Cited by 2 cases · Cites 3 cases
|
cacv 113/2006 in the high court of the hong kong special administrative region court of appeal civil appeal no. 113 of 2006 (on appeal from HCCT NO. 76 of 1996) ______________________ BETWEEN
Before: Hon Rogers VP, Le Pichon JA and Chu J in Court Date of Hearing: 15 March 2007 Date of Judgment: 15 March 2007 Date of Handing Down Reasons for Judgment: 21 March 2007 ___________________________ REASONS FOR JUDGMENT __________________________ Hon Rogers VP: 1.I agree with the reasons given by Le Pichon JA. Hon Le Pichon JA: 2.This was an application by the plaintiff for leave to appeal to the Court of Final Appeal from the order of this court dated 24 October 2006 dismissing the plaintiff’s appeal from the order of Reyes J striking out parts of the plaintiff’s claim relating to “extra over for toeing-in of piles” into bedrock. Leave was refused for reasons to be given in writing later which we now do. 3.The background facts sufficiently appear from the judgment of this court and I do not propose to repeat them here. As of right 4.This was the first ground relied on by the plaintiff and turned on whether the order below (confirmed by this court) made on the strikeout application of the defendant was interlocutory or final. The first matter to note is that the order made below and confirmed by this court was to strike out part of the plaintiff’s claim. It was not an order made under Order 14A. 5.The two tests which historically have been propounded for deciding whether a judgment is final or interlocutory, namely ‘the application test’ and ‘the order test’, are well known. The former involves an examination of the nature of the application to say whether the order would, whether it failed or succeeded, determine the whole action. The latter looks at the nature of the order made by the court below rather than the nature of the application and if the order finally disposes of the rights of the parties it is final. It is evident that it is important that there be clarity and certainty as to which of the tests is applicable from the perspective of litigants as well as the public interest in the efficient deployment of judicial resources. 6.It is well settled that in Hong Kong as in England the ‘application test’ applies and that an order for the striking out of an action for disclosing no reasonable cause of action under Order 18 rule 19 has always been regarded as interlocutory. See the determination of the Appeal Committee of the Court of Final Appeal (Litton ACJ, Ching and Bokhary PJJ) in Wai Hung Stationary Co & others vHKSAR & others [1998] 2 HKC 229 at 231F-G and (Li CJ, Bokhary and Chan PJJ) in B+B Construction Ltd v Sun Alliance and London Insurance PLC [2001] 1 HKLRD 1 at 4E-F where it was explained that the reason why a striking out order was interlocutory was because such an order would not have the effect of finally disposing of the cause or matter if the outcome was in favour of one party and not the other. I do not read the later decision of the Court of Final Appeal in Shell Hong Kong Ltd v Yeung Wai Man [2003] 3 HKLRD 62 (which concerned Order 14A) as in any way departing from or jettisoning the ‘application approach’, at any rate, so far as summary judgment and strikeout applications are concerned. 7.For these reasons, I consider that the plaintiff is not entitled to appeal to the Court of Final Appeal under section 22(1)(a) of the Court of Final Appeal Ordinance. Questions of great general or public importance 8.Two such questions are said to arise:
9.So far as the first question is concerned, Mr Coleman SC who appeared for the plaintiffs submitted that the effect of the judgment is that in a re-measurement construction contract a [Bill of Quantities (“BQ”)] description can override provisions of the SMM and/or the Particular Preamble and whenever a BQ description does not follow the SMM, the BQ description can override SMM. 10.The premise of the submission was that the judgment of this court laid down general principles of construction involving the interrelationship of BQ descriptions, SMM and Particular Preamble. On any fair reading of the judgment, I do not consider that one could reasonably arrive at that conclusion. This court was construing a particular contract relating to the project in question. Special condition 1(j) was of central importance in the interpretation of the subcontract entered into by the parties. I cannot see that the proper interpretation of this subcontract can be said to be of general application to other contracts unless they be identical in all material respects. The subcontract in question was tailor-made and it is misleading and simply wrong to suggest that it was in any way ‘standard form’. 11.It would appear that Mr Coleman also considered that the judgment supported the following propositions:
12.Again, that submission has no valid basis. In the subcontract under consideration, the effect of special condition 1(j) when read together with item 4 in BQs 5 and 10 is that the SMM provisions are not followed with regard to extra over for toeing-in into bedrock. That was not dependent on there being any Particular Preamble. Mr Coleman’s first proposition is accordingly incorrect. As to his second proposition, quite simply, whether and, if so, how any “error or omission” is to be addressed must again depend on the terms of the particular contract.
13.This court dealt with the significance of the drawings provided to all tenderers before the tenders were submitted and, in particular, of notes 6 to 8 in paragraphs 8 to 9 of its judgment. It is against that factual matrix and the terms of the subcontract that the expression “1.5m in depth (min)” was construed. 14.The plaintiff relies, inter alia, on an article appearing in the Surveyor’s Times by JB Molloy of James R. Knowles (Hong Kong) Limited. Ironically, it transpires that in 1995, Mr Molloy had rendered advice on the effect of the subcontract to the defendant and came to a view that is entirely consistent with what this court has held, namely, that the phrase “1.5m in depth (min)” in the BQs meant that the risk of a greater depth of toeing-in fell on the subcontractor. This necessarily undermines his more recent views as expressed in the Surveyor’s Times which, in any event, were based on the Government Standard Form of Civil Engineering Contract rather than the subcontract. 15.I do not doubt that the manner in which the subcontract has been construed by this court is of a matter of importance to the plaintiff but that cannot be transmuted into a matter of great general or public importance. Hon Chu J: 16.I agree.
Mr Russell Coleman SC & Ms Queenie W S Ng, instructed by Messrs Hau, Lau, Li & Yeung, for the Plaintiff/Applicant Mr Peter Clayton SC, instructed by Messrs Ho & Ip, for the Defendant/Respondent Appeal to Court of Final Appeal dismissed: see FAMV21/2007 dated 8 June 2007 |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under CACV 113/2006