Crowning Success Ltd v. Brightland Corporation Ltd and Another
Read the full judgment text of HCA 1445/2005 on BabelCite. This High Court CFI judgment was delivered on 3 April 2009.
1. These proceedings concern a confirmor sale of commercial premises known as “Unit C” on the 45 th floor of Convention Plaza, 1 Harbour Road, which failed to complete on the due completion date of 22 July 2005.
Cited by 4 cases
|
HCA1445/2005 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NOS. 1445 AND 1540 OF 2550 ----------------------------- BETWEEN
----------------------------- (Actions consolidated by Order of Master Lung dated 9 June 2006) Before : Hon Burrell J in Court Dates of Hearing : 12, 13, 16, 17, 19 and 20 March 2009 Date of Judgment : 3 April 2009 ----------------------- j u d g m e n t ----------------------- 1.These proceedings concern a confirmor sale of commercial premises known as “Unit C” on the 45th floor of Convention Plaza, 1 Harbour Road, which failed to complete on the due completion date of 22 July 2005. 2.The 2nd defendant (Banhart) was the head vendor who, on 30 December 2004, had agreed to sell the property to the 1st defendant (Brightland) for $14.8 million. The agreed completion date was to be 22 July 2005. 3.On 18 January 2005, Brightland agreed to sell to the plaintiff (Crowning Success) under a sub-sale agreement for $17,800,000. The completion date was the same, 22 July 2005. As can be seen from the figures involved, the property market at the material time was rising. The agreed valuation at the time of completion was $19.54 million. 4.In December 2004, Unit C was an open space forming part of the 45th floor. There was no partitioning in place. However, by a “rider” to the agreement, signed by both parties, a floor plan showing the location of the unit, its dimensions and shape was annexed to the Head agreement. The plan also confirmed, as part of the “rider”, that the saleable area of the unit was not less than 144.402 sq. metres. This was certified by a professional architect. For ease of reference, a copy of the plan is included in this judgment as appendix “A”. 5.The on-sale to Crowning Success was intended to be a back-to-back arrangement. Put simply, Crowning Success agreed to buy from Brightland the same as Brightland had agreed to buy from Banhart. 6.However, when Crowning Success came to the premises to inspect prior to completion on 22 July differences between the unit on site and the unit on plan were detected. Concerned that it was not getting what it had agreed to purchase, measurements were taken and a further plan drawn up. The plaintiff’s case is that Appendix “B” is what was being offered on the date of completion. The key differences were :
7.For these reasons (and for one additional reason which I deal with later under the heading “Requisition”) Crowning Success did not complete with Brightland and Brightland were correspondingly unable to complete with Banhart. 8.Banhart’s position is that the area of Unit C on 22 July was 144.402 sq. metres and that there was no agreement as to exactly where the 144 sq. metres would be located on the 45th floor. In particular, there was no agreement that Brightland was entitled to the habour view from the windows within the “indigo strip” area. 9.On 27 July 2005, a plan was prepared on behalf of Banhart by a Mr Li Man Ying. That plan is appendix plan “C” to this judgment. It is Banhart’s case that plan C represents accurately what was offered at the proposed time of completion on 22 July. It is Banhart’s case that their contractual obligation was to provide a unit of not less than 144.402 sq. metres which was approximately, but not exactly, located within the area shown on plan “A”. Banhart submits that there was no obligation to include the two windows in the “indigo strip” neither was there any obligation to provide the space called the “indigo strip”. The remaining significant difference between plan “A” and plan “C” is that the partition walls on plan C are double partition walls with an 800 mm cavity between the two partitions. It is Banhart’s case that these partition walls were in place at the time of completion on 22 July. 10.For the reasons which follow, my findings on the evidence are that on 22 July :
Reasons 11.(a) Mr Li Man Ying’s plan was prepared on 27 July, five days after the completion date. His plan records his findings on that day. More importantly he was not called as a witness. Banhart’s only witness as to fact was Ms Lillian Oung, the owner of the property (she was also the owner of the entire 45th floor). She was able to provide no good reason why Mr Li was not called as a witness. Given the crucial factual issues at the heart of this case little weight can be attached to his written evidence. Banhart’s expert witness was Mr Wong Man Hong. He was only instructed in late 2008. It is therefore difficult to understand on what basis he was able to state that he was in “full agreement” with Mr Li’s report.
12.As can be seen from the above findings and reasons, the key issues are entirely factual and, I so find, entirely in Crowning Success and Brightland’s favour. 13.It follows that Banhart repudiated the head agreement, Brightland lawfully accepted the repudiation, Brightland were unable to deliver to Crowning Success who lawfully accepted Brightland resulting repudiation of the sub-sale agreement. Requisitions 14.This is a discrete issue. My judgment is that even if none of the above issues had ever arisen, Crowning Success would have still been able to terminate the sub-sale agreement with Brightland because of their failure to provide good title having failed adequately to answer a requisition. 15.In an assignment between Banhart and a company called Polytown Company Limited dated 19 September 1990, clause 2(2) provided that :
16.On 19 July 2005, the plaintiff’s solicitors wrote to Brightland’s solicitors requesting a certified copy of Polytown’s consent. 17.Brightland’s solicitors immediately made the same request of Banhart’s solicitors. Neither requisition was properly answered. Moreover, no objection was raised as to the timing of the requisition being three days prior to completion. Brightland therefore failed to show good title to Crowning Success. 18.This is merely a second string to Crowning Success’s bow. Given the strength of their case on the main issue it is somewhat academic. Crowning Success’s entitlement to a lien 19.Crowning Success seeks a declaration that it is entitled to a lien over the whole of the 45th floor of the building limited to the amount of the lien that Brightland could claim against Banhart for breach of the head agreement. Crowning Success seeks the lien directly against Banhart even though there is no contractual relationship between them. 20.Its argument is that whatever interest Brightland acquired from Banhart was assigned (because it was a back-to-back confirmor sale) to Crowning Success in equity. 21.There is authority for the argument that an equitable lien would be created, in such circumstances. However, in the absence of a contractual connection, I decline to make the declaration in this case for two reasons. Firstly, Crowning Success seeks the declaration in relation to the whole of the 45th floor. I am not minded to declare a lien over property which was not the subject of the transaction between any of the parties to the litigation. Secondly, declaring a lien over “Unit C” would be unworkable. “Unit C” was never defined in terms of undivided shares and a lien would be therefore unregisterable. “Unit C” is also no longer a definable area or space and, moreover, is no longer owned by Banhart (the parties having earlier come to terms about the lifting of the lis pendens registered by Crowning Success). It is because of these difficulties that Crowning Success seek a lien over the whole of the 45th floor. In my judgment such difficulties cannot be solved by a blanket lien over different property. Inducing a breach of contract 22.Crowning Success also claims directly against Banhart in tort for inducing a breach of contract. There is no doubt that Banhart’s breach of the head agreement led inevitably to the breach of the sub-sale agreement. I am satisfied also that Banhart knew of the sub-sale at the time of completion. Lillian Oung claimed that she did not know, however correspondence between solicitors suggests otherwise. However my evaluation of the whole of the evidence does not enable me to conclude that the motive for the breach by Banhart was in order to gain an economic benefit for itself. I am not persuaded that Banhart’s breach was deliberately done for its own advantage. Accordingly, the relief in this case must be confined to the return of deposits and damages for breach of contract. Relief 23.As to the measure of damages I consider it to be a straightforward arithmetic exercise. The only three relevant figures are (i) Brightland’s purchase price, (ii) Crowning Success’s purchase price and (iii) the agreed valuation on 22 July 2005. 24.Based on the agreement at trial that the property was worth $19.54 million on 22 July 2005, final judgment in the consolidated action shall be as follows :
25.Orders as to costs and interest shall be on a nisi basis.
Mr Jin Pao, instructed by Messrs Kao, Lee & Yip, for the Plaintiff Mr Eugene Fung, instructed by Messrs Vincent T.K. Cheung, Yap & Co., for the 1st Defendant Mr King Wong, instructed by Messrs Amelia Cheung & Co., for the 2nd Defendant Appendix Plan A
Appendix Plan B
Appendix Plan C
|
Other judgments that cite this case
Further hearings and rulings under HCA 1445/2005


