Ip Tsz Lam Ada v. Pearl Wisdom Ltd
Read the full judgment text of HCA 2482/2007 on BabelCite. This High Court CFI judgment was delivered on 2 April 2009.
1. On 2 April 2009 I dismissed the plaintiff’s application by summons dated 16 January 2009 for leave to amend the statement of claim with costs to the defendant. I indicated at the time that reasons would be given later. I now do so.
Cites 5 cases
|
HCA 2482/2007 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO. 2482 OF 2007 ----------------------
---------------------- Before : Hon Sakhrani J in Chambers Date of Hearing : 2 April 2009 Date of Judgment : 2 April 2009 Date of Handing Down Reasons for Judgment : 17 April 2009 ---------------------------------------------------- REASONS FOR JUDGMENT --------------------------------------------------- 1.On 2 April 2009 I dismissed the plaintiff’s application by summons dated 16 January 2009 for leave to amend the statement of claim with costs to the defendant. I indicated at the time that reasons would be given later. I now do so. 2.By a sale and purchase agreement dated 21 March 2006 (“the agreement”) between the plaintiff as purchaser and the defendant as vendor, the plaintiff purchased Flat G on the 23rd floor of Service Apartment Tower 1 of the development then under construction (“the property”) at the price of $4,431,000. 3.By clause 4(1)(c) of the agreement the defendant covenanted to complete the development in all respects in compliance with the condition of the Government Grant, the building plans and the agreement, incorporating in the property the fittings and finishes as set out in Schedule 5 to the agreement, on or before 31 August 2007 subject to such extension of time as may be granted by the Authorised Person in accordance with clause 4(5)(a). 4.By clause 4(5)(a) the defendant was entitled to such extensions of time for completion of the development beyond the date stated in clause 4(1)(c):
5.By clause 4(5)(b) the defendant covenanted to notify the plaintiff in writing within 14 days from the issue of any such extensions of time granted by the Authorized Person and furnish the plaintiff with a copy of the relevant certificate of extension. 6.Time was of the essence of the agreement (clause 15). 7.Pursuant to the agreement the plaintiff paid a total sum of $4,431,000 to the defendant in accordance with the terms of the agreement as varied by a supplemental agreement signed on 17 January 2007. 8.By a certificate dated 23 April 2007 (“the certificate”) the Authorized Person granted to the defendant an extension of 67 days beyond 31 August 2007 for the completion of the development (“the extension”). By a letter dated 30 April 2007 the defendant notified the plaintiff of the issue of the certificate. 9.The date of completion of the development was extended to 6 November 2007 by the certificate. The plaintiff’s pleaded case 10.The plaintiff’s case as pleaded in the statement of claim is that in breach of clause 4(1)(c) of the agreement the defendant failed to complete the development by 6 November 2007. The plaintiff became entitled to rescind the agreement pursuant to clause 4(4)(a) of the agreement and by her solicitors’ letter dated 7 November 2007 she gave notice of rescission to the defendant’s solicitors. The agreement was rescinded on 14 November 2007 and the plaintiff is entitled to repayment of the said sum of $4,431,000 with interest in accordance with clause 4(4)(a) of the agreement (paragraphs 15 to 17 of the statement of claim). The defence and counterclaim 11.The defendant denies that the plaintiff was entitled to rescind the agreement or to give the notice of rescission by her solicitors’ letter dated 7 November 2007 or otherwise. 12.The defendant further pleads that by a certificate dated 6 November 2007, the Authorized Person certified that the development had been completed in all respects in compliance with the conditions of the Government Grant in so far as they relate to the development and the building plans. By a letter dated 19 November 2007 the Authorized Person applied for the Certificate of Compliance to be issued in respect of the development. By a letter dated 18 December 2007 the Director of Lands gave the defendant the consent to enter into assignments in respect of the development (“consent to assign”) and by clause 4(7) of the agreement the issue of the consent to assign is conclusive evidence that the development has been completed or is deemed to be completed as the case may be (paragraph 6 of the defence and counterclaim). 13.There is also a counterclaim by the defendant for specific performance of the agreement with all necessary accounts and inquiries or damages in lieu, a declaration that the agreement has not been validly terminated by the plaintiff, damages, interest and costs. 14.Pursuant to clause 5(1) of the agreement, by its solicitors letter dated 20 December 2007 the defendant notified the plaintiff that the consent to assign had been issued and gave notice that the defendant was in a position to validly assign the property. The plaintiff has failed and refused to complete the sale and purchase of the property. The defendant is ready, willing and able to complete the sale and purchase. The defendant has suffered loss and damage as a result of the plaintiff’s breach of the agreement (paragraphs 14 to 17 of the counterclaim). The application to amend 15.The plaintiff applies to amend the statement of claim by adding a new cause of action. The substance of the amendments is pleaded in paragraphs 14 to 18 of the proposed amended statement of claim (“the amendments”) as follows:
16.The plaintiff seeks to amend the prayer for relief by including:
17.Mr Haddon-Cave, for the plaintiff, submitted that the plaintiff became concerned with the certificate extending the time for completion of the development and through her solicitors enquired from the Hong Kong Observatory about the weather for the relevant period. The reply from the Hong Kong Observatory showed that there were only 31 days of inclement weather as defined in clause 4(5)(a) of the agreement instead of the 67 days certified by the Authorized Person and because of this the plaintiff seeks to add a new cause of action by the amendments. 18.The principles governing applications to amend pleadings are well known and it is not necessary to repeat these here. 19.Mr Chan SC, for the defendant, submitted that the amendments were useless and ought not to be allowed. It seems to me that where it can be demonstrated that the amendments are liable to be struck out then the court should not allow the amendments to be made. 20.Mr Haddon-Cave made it plain that the new cause of action was in contract. He submitted that the defendant had a contractual duty of care to ensure that the Authorized Person’s certificate granting the extension of time that was passed onto the plaintiff was issued in accordance with the agreement. This was not an express term in the agreement. Mr Haddon-Cave submitted that the plaintiff was relying only on an implied term in the agreement that the defendant had a duty of care to ensure that the Authorized Person’s certificate granting the extension of time that was passed onto the plaintiff was issued in accordance with the agreement (“the implied term”). 21.Mr Haddon-Cave submitted that the plaintiff relied on two matters in asking the court to imply the implied term as follows:
22.As to (1), it is important to bear in mind that the agreement was a sale and purchase agreement in the standard form under the Consent Scheme. As such, it was agreed upon by the Director of Lands and the Law Society. That being so, I fail to see how it can seriously be suggested that because of the inequality of bargaining position between the plaintiff and the defendant the court should imply the implied term. 23.The standard form of sale and purchase agreement under the Consent Scheme has been held to be valid and enforceable in, inter alia, the cases cited by Mr Chan. These are Yau Chin Kwan & another v Tin Shui Wai Development Ltd [2003] 2 HKLRD 1; Liu Chung Fai v Tin Shui Wai Development Ltd [2007] 4 HKLRD 350; Tsang Man Chung v Kar Ho Development Co. Ltd (HCA 8534/1999; Chung J, 16 August 2001); Concord Property Development Ltd v Li Pui Leung and Lee Pui Ha (HCA 7923/2000; Deputy Judge Muttrie; 31 May 2005). 24.It seems to me that the first matter relied on in seeking to imply the implied term is unsustainable. 25.The second matter relied on is the fact that the plaintiff has relied on the statement in the certificate as being perfectly good when it was anything other than good. 26.The certificate is dated 23 April 2007. The plaintiff was given notice of this certificate by a letter dated 30 April 2007. Any reliance on the statement in the certificate can only have been on or after that date. 27.The plaintiff cannot rely on subsequent acts to ask the court to imply a term in the agreement. The agreement was made on 21 March 2006. The subsequent acts only occurred over a year later. The second matter relied on to ask the court to imply the implied term is also unsustainable. 28.I would observe that in Yau Chin Kwan it was held, inter alia, that the agreement was perfectly workable without the implied terms that the purchasers in that case were seeking to imply. It was held that there was no implied term that the vendor was obliged to:
29.It was also held that it could not be said that the parties would have agreed at the signing of the sale and purchase agreement that the implied terms “went without saying”. 30.In Liu Chung Fai it was held that the purchaser’s claim on the implied term was bound to fail. It was held that there was no implied term that the vendor shall answer the purchaser’s questions concerning the completion of the development. 31.As Le Pichon JA said at paragraph 16 of her judgment:
32.I would also refer to what Rogers VP said in Yau Chin Kwan at paragraph 18 of his judgment:
33.By clause 4(5)(a) of the agreement the defendant was entitled to such extensions of time for completion of the development as shall be granted by the Authorized Person “and appear to him to be reasonable” having regard to delays caused by, inter alia, inclement weather as defined in clause 4(5)(a)(iv). What would appear to him to be reasonable would be a matter of judgment for the Authorized Person and thus open to query and challenge. It seems to me that it would be stretching reality to suggest that it went without saying that the defendant would have agreed to the implied term. 34.It has been held by Chung J in Tsang Man Chung at paragraph 29 of his decision that in the context of an agreement under the Consent Scheme, the only proper bases for challenging the Authorized Person’s certificate granting the extension of time are:
I respectfully agree. 35.Tsang Man Chung was followed by Deputy Judge Muttrie in Concord Property Development Ltd. 36.There is no dispute that the certificate was issued by Daniel Lin Hsien Wen, the Authorized Person under the agreement. Mr Haddon-Cave confirmed that the plaintiff was not suggesting that the Authorized Person did not issue the certificate in good faith or that he did not purport to exercise the power conferred on him by the agreement to extend time. 37.Paragraph 14 of the amendments pleads the plaintiff relied on the representation in the certificate and induced thereby the plaintiff did not exercise its right of rescission under clause 4(4)(a) of the agreement immediately after the passing of the unextended deadline for completion of the development of 31 August 2007. And by paragraph 18 of the amendments and the amended prayer for relief the plaintiff seeks to terminate the agreement with effect from 31 August 2007. 38.However, as Chung J observed in Tsang Man Chung at paragraph 28 of his decision:
39.I would also refer to the passage of the Court of Appeal’s judgment in Kar Ho Development Co. Ltd v Axis Investment Ltd [2001] 1 HKC 86 cited by Chung J at paragraph 26 of his decision in Tsang Man Chung:
40.It seems to me that even if the extension of time beyond 31 August 2007 was disallowed that does not assist the plaintiff in seeking to terminate the agreement with effect from 31 August 2007. Clause 4(4)(b) of the agreement clearly provides that if the plaintiff does not rescind the agreement under clause 4(4)(a) within 28 days from 31 August 2007 she shall be deemed, without prejudice to her rights under clause 4(4)(c), to have elected to wait for completion of the development. The plaintiff has not given a notice to rescind within the 28 days provided for in clause 4(4)(b) and she is deemed, without prejudice to her rights under clause 4(4)(c), to have elected to wait for completion of the development. 41.The plaintiff further pleads at paragraph 16 of the amendments that the Authorized Person was employed by the defendant “to issue certificates for extension of time under clause 4(5)(a) of the Agreement and owed the Plaintiff a duty to ensure that such were correct”. This amounts to a plea that the defendant owed the plaintiff a duty of care to ensure that the certificate was correct because its employee issued the certificate and the defendant is vicariously liable for the acts of the employee. 42.Clause 4(5)(a) of the agreement provides that the defendant was entitled to such extensions of time as granted by the Authorized Person. It cannot realistically be suggested that the vendor under the agreement was entitled to extensions of time granted by its own employee. 43.The Authorized Person is defined in clause 1(1)(a) of the agreement as follows:
44.It is clear that the Authorized Person has got statutory duties under the Buildings Ordinance Cap. 123. 45.In my view, the Authorized Person was not a servant or employee of the defendant when he issued certificates of extension. 46.Deputy Judge Muttrie correctly analysed the Authorized Person’s position in agreements under the Consent Scheme when he said at paragraph 23 of his judgment in Concord Property Development:
47.To suggest that the Authorized Person was not exercising his independent judgment in granting the certificate but was issuing the same as a servant or employee of the defendant is, in my view, unsustainable. In his reply submissions Mr Haddon-Cave did not pursue the pleaded case at paragraph 16 of the amendments that the Authorized Person issued the certificate as employee of the defendant. He accepted that the Authorized Person’s role in issuing the certificate was as an independent professional. 48.It seems to me that the new cause of action added by the amendments is unsustainable and is liable to be struck out. 49.For the above reasons, I dismissed the application to amend. I also ordered that the plaintiff do pay the defendant the costs of the application as it seemed to me that costs should follow the event.
Mr Francis Haddon-Cave, instructed by Messrs Tang, Leung, Li & Tsang, for the Plaintiff Mr Edward Chan, SC, instructed by Messrs Chu & Lau, for the Defendant |
Cases cited in this judgment
Further hearings and rulings under HCA 2482/2007