Maple Leaf Investment Co Ltd v. Hong Kong Cyberport (Ancillary Development) Ltd
|
HCA891/2009 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO.891 OF 2009 ____________________ BETWEEN
Before : Hon Sakhrani J in Chambers Date of Hearing : 21 December2009 Date of Judgment : 21 December 2009 Date of Handing Down Reasons for Judgment : 30 December 2009 ______________________ REASONS FOR JUDMENT ______________________ 1.By summons dated 31 July 2009 the defendant applied to strike out the plaintiff’s statement of claim and asked for an order that the action against the defendant be dismissed. The defendant also applied for summary judgment on its counterclaim. 2.On 21 December 2009 I made an order that the plaintiff’s statement of claim be struck out and that the action against the defendant be dismissed. I also gave judgment to the defendant on its counterclaim as follows for:
3.I also made an order that the costs of the action and the counterclaim including the costs of the application be paid by the plaintiff to the defendant. 4.I indicated at the time that written reasons in writing would be given. This I now do. 5.This action concerns the property known as Flat B, 29th Floor, Tower 2 and Private Cars Car Park No. 216, Car Park Level5, Bel-Air No. 8, Bel-Air on the Peak, Island South (Phase VI), Hong Kong (“the property”). 6.The defendant was the developer of the residential project in which the property is located. At the time of the agreement the development was under construction. 7.The agreement dated 12 April 2007 was made between the plaintiff as purchaser and the defendant as vendor of the property whereby the defendant sold and the plaintiff purchased the property at the purchase price of HK$10,396,000.00 upon the terms and conditions contained in the agreement. The agreement was in the standard form under the Consent Scheme which was agreed upon between the Director of Lands and the Law Society. 8.In accordance with the terms of the agreement the plaintiff has paid the following sums to Messrs Woo, Kwan, Lee & Lo (“WKKL”) solicitors for the defendant :
9.The balance of the purchase price in the sum of HK$8,836,600.00 was payable by the plaintiff within 14 days of the purchaser being notified in writing that the defendant was in a position to validly assign the property to the plaintiff. 10.By clause 5(1) of the agreement it was provided that
11.By clause 5(2) it was provided that
12.By clause 1(1)(e) of the agreement “Certificate of Compliance” is defined to mean
13.The property was in Phase VI of the development. The development was defined in clause 1(1)(n) to mean
14.Phase VI was defined in clause 1(1)(w) to mean
15.Under recital (1) of the agreement it was recited that the defendant was obliged under Special Condition No. (12)(b) of the Government Grant to erect and complete upon the land before 30 June2008, inter alia,
16.The “Building” means the building or buildings comprised in Phase VI of the development(clause 1(1)(c)). 17.“Government Grant” means the Government Grant document specified in Schedule 2 (clause 1(1)(r)). Schedule 2 identifies the document as the Conditions of Grant No. 12572 and gives details of the parties, date, term, user and lot number. 18.By clause 4(1) of the agreement the defendant covenanted to :
19.The Authorised Person was Mr Robert P. H. Lam of Wong & Ouyang (HK) Ltd (“the AP”) (clause 1(1)(b)). 20.By letter dated 30 June 2008 from the Lands Department the defendant was granted a 3 months extension of time to comply with the building covenant under Special Condition No. (12)(b) of the Government Grant thereby extending the time from 30 June 2008 to 30 September 2008. The defendant had paid a premium of HK$109,663,100.00 for this extension. 21.By letter dated 13 October 2009 the AP certified, inter alia, that
22.By clause 4(5)(a) of the agreement the defendant was entitled to such extensions of time for completion of the development beyond the date stated in sub-clause (1)(c) as shall be granted by the AP and appear to him to be reasonable having regards to delays caused exclusively by,inter alia, inclement weather. 23.By clause 4(5)(b) of the agreement the defendant was required to notify the plaintiff in writing within 14 days from the issue of any such extension of time granted by the AP and furnish the plaintiff with a copy of the relevant certificate of extension. 24.By letter dated 23 September 2008 the AP granted an extension of time of 60 days to the defendant for the completion of Phase VI of the development in compliance with the Government Grant from 30 September 2008 to 29 November 2008 and stated that “such extension of time appears to me to be reasonable, having regard to delays caused by inclement weather which occurred during the construction of Phase VI of the Development from 26 January 2007 to 11 September 2008”. 25.Pursuant to clause 4(5)(b) of the agreement by letter dated 25 September 2008 WKKL notified the plaintiff that an extension of time was granted by the AP from 30 September 2008 to 29 November 2008 and enclosed a copy of the AP’s certificate of extension. 26.On 11 November 2008 the Lands Department issued the Certificate of Compliance certifying that all the positive obligations imposed under the General and Special Conditions of the Government Grant have been satisfactorily complied with. 27.By letter dated 28 November 2008 from WKLL to the plaintiff the plaintiff was notified that the defendant was in a position to validly assign the property to the plaintiff. The plaintiff was required to complete the purchase of the property on or before 12 December 2008 pursuant to clause 5(2) of the agreement. 28.The plaintiff failed to complete the purchase of the property on 12 December or at any other time. 29.By letter dated 20 December 2008 WKLL demanded the balance of the purchase price from the plaintiff and gave notice that unless the balance was paid with interest within 21 days the defendant may exercise its right under clause 16 of the agreement to forfeit the deposit already paid and determine the agreement and resell the property. 30.By letter dated 27 March 2009 WKLL notified the plaintiff that the defendant exercised its rights to determine the agreement, forfeit the deposit of HK$519,800.00 and that the defendant would retain the partial payment of HK$1,039,600.00 and apply it towards the settlement of damages as a result of the plaintiff’s breach of the agreement. 31.By an agreement for sale and purchase dated 30 March 2009 between the defendant as vendor and another party as purchaser, the defendant resold the property at the purchase price of HK$8,989,200.00. 32.By its statement of claim the plaintiff claims that thedefendant has been in breach of the agreement. The plaintiff’s primary claim is as pleaded at paragraph 8 of the statement of claim which pleads
33.Mr Wong, for the plaintiff, submitted that on the plaintiff’s primary claim there was a triable issue as to whether the defendant ought to have notified the plaintiff on 1 September 2008 that the defendant was in a position to validly assign the property on 15 September 2008. As it was only on 28 November 2008 that WKLL notified the plaintiff that the defendant was in a position to validly assign the property the defendant was, it was submitted, in breach of the agreement. The plaintiff claims a refund of the total sum of HK$1,559,400.00 paid by the plaintiff to the defendant, a declaration that the agreement has been validly rescinded by the plaintiff and damages to be assessed with interest and costs. 34.Mr Wong sought to argue that the AP’s letter of 13 October 2008 effectively certified that the issuance of the Certificate of Compliance or the consent of the Director of Lands to assign the property was only a matter of formality or procedure. It was submitted that the defendant should have notified the plaintiff on 1 September 2008 that it was in a position to validly assign the property and that completion should have been within 14 days of 1 September 2008. 35.I am unable to accept this submission. 36.In my view the plaintiff’s primary claim is misconceived. 37.When completion is to take place is clearly and unequivocally spelt out in the agreement. 38.Clause 5(1) of the agreement clearly stipulates that the defendant shall notify the plaintiff in writing that it is in a position to validly assign the property “within one month of the issue of the Certificate of Compliance or the consent of the Director of Lands to assign whichever shall first happen”. That is the time when the defendant is obliged to notify the plaintiff in writing that it is in a position to validly assign the property and not earlier. 39.And by clause 5(2) of the agreement the sale and purchase shall be completed at the offices of WKLL within 14 days of the date of notification to the plaintiff that the defendant is a position validly to assign the property to the plaintiff. 40.It is accepted by Mr Wong that the Certificate of Compliance was issued only on 11 November 2008 by the Lands Department. There is no evidence of the consent of the Director of Lands to assign the property. Hence on a clear reading of clause 5(1) of the agreement the defendant was required to notify the plaintiff in writing that it is in a position to validly assign the property within one month of 11 November 2008 which it did by the letter from WKLL dated 28 November 2008. And completion was to take place on or before 12 December 2008 which is within 14 days of the date of notification to the plaintiff that the defendant is in a position to validly assign the property to the plaintiff. 41.I see no merit in the plaintiff’s primary claim which, in my view, is unsustainable and ought to be struck out. 42.I would also observe that in his oral submissions Mr Wong accepted that the plaintiff has not rescinded the agreement. That being so, I fail to see how the plaintiff can even begin to claim a declaration that the agreement has been validly rescinded by the plaintiff. 43.The plaintiff’s alternative claim is pleaded at paragraph 9 of the statement of claim which pleads
44.Mr Wong submitted that there was a triableissue on the alternative claim of the plaintiff that the expiry date of 30 September 2008 for the completion of the development has not been extended. As the development was completed late without an extension being granted, it was submitted that the defendant was in breach of clause 4 of the agreement and that the plaintiff was entitled to rescind the agreement. 45.However, as I have observed, the plaintiff has not exercised its right to rescind under the agreement as is accepted by Mr Wong. On its alternative claim the plaintiff complains that the defendant failed to complete the development by the specified date of 30 September 2008 and that the development was completed late after that date without an extension being granted. 46.By clause 4(4)(a) of the agreement it was provided that if the defendant fails to complete the development by the date specified the plaintiff shall be at liberty by notice in writing to the defendant to rescind the agreement and upon service of the notice the agreement shall be rescinded within 7 days thereafter. And in clause 4(5)(b) of the agreement it was provided that if the plaintiff does not rescind the agreement under clause 4(4)(a) within 28 days from the specified date “he shall be deemed, without prejudice to his rights under sub-clause (4)(c) hereof, to have elected to wait for completion of the Development”. 47.The plaintiff has not given a notice to rescind within the 28 days period provided for in clause 4(4)(a) or at any other time. 48.As the plaintiff failed to rescind the agreement the plaintiff is, on a clear reading of clause 4(5)(b) of the agreement, deemed to have elected to wait for completion of the development. 49.By letter dated 23 September 2008 the AP has clearly granted an extension of time from 30 September 2008 to 29 November 2008 pursuant to clause 4(5)(a) of the agreement. There is no valid basis to challenge the AP’s certificate of extension. 50.There is no merit in the plaintiff’s alternative claim which, in my view, is unsustainable. 51.As the plaintiff’s primary claim and alternative claim are unsustainable the statement of claim should be struck out and the action against the defendant should be dismissed. 52.The plaintiff has also failed to raise a triable issue on the defendant’s counterclaim. 53.It is clear on the evidence that the plaintiff failed to pay the balance of the purchase price on completion or to make good its default when given notice to do so by the letter from WKLL dated 20 December 2008. 54.By the letter dated 27 March 2008 the defendant determined the agreement. 55.Upon determination of the agreement the defendant was entitled to:
56.The property was resold at the purchase price of HK$8,989,200.00 by the agreement for sale and purchase dated 30 March 2009. 57.The defendant is entitled to damages for breach of the agreement to be assessed. 58.The defendant is also entitled to interest on the balance of the purchase price from 13 December 2008 to 27 March 2009 at the rate of 2% per annum above the prime rate specified by HSBC amounting to HK$177,942.50. 59.The plaintiff has failed to raise a triable issue on the defendant’s counterclaim and the defendant is entitled to judgment on its counterclaim. 60.For the above reasons, I made the ordersand gave judgment to the defendant as set out above at paragraph 2.
Mr Patrick S L Wong, instructed by Messrs C. M. Mok & Co., for the Plaintiff Mr Jin Pao, instructed by Messrs Woo, Kwan, Lee & Lo, for the Defendant |
Cases cited in this judgment
Further hearings and rulings under HCA 891/2009