Cogi Enterprises Ltd and Others v. The Incorporated Owners of Malahon Apartments

Read the full judgment text of HCA 816/2004 on BabelCite. This High Court CFI judgment was delivered on 21 December 2010.

1. At trial there were four separate matters in dispute between the parties. The main dispute was in respect of the pipeworks.

Cites 1 case

Case No.HCA 816/2004
Court
High Court CFI
Date21 Dec 2010
Judge
Case Document
100%Judiciary

HCA 816/2004

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO. 816 OF 2004

________________________

BETWEEN

COGI ENTERPRISES LIMITED 1st Plaintiff
SPEEDY GAINER LIMITED 2nd Plaintiff
CHOW SHING KEE INVESTMENT COMPANY LIMITED 3rd Plaintiff
and
THE INCORPORATED OWNERS OF MALAHON APARTMENTS Defendant

Before : Hon Sakhrani J in Chambers

Date of Hearing : 21 December 2010

Date of Judgment : 21 December 2010

________________________

J U D G M E N T

________________________

1.At trial there were four separate matters in dispute between the parties. The main dispute was in respect of the pipeworks.

2.By my judgment dated 5 May 2010 I found in favour of the plaintiffs in relation to the pipeworks.

3.I gave judgment to the 3rd plaintiff on its claim for a mandatory injunction to compel the IO to remove the pipeworks and to reinstate the walls in shop 2A where the pipeworks pass through by 5 November 2010 with liberty to the parties to apply in case there is difficulty in complying with this order.  I also dismissed the IO’s counterclaim for a declaration and an injunction in relation to the pipeworks.

4.The IO has by its notice of appeal dated 20 May 2010 sought to appeal the orders I made.  I would observe that although the notice of appeal was filed on 20 May 2010 it was only on 9 December 2010 that the IO applied to fix a date for the hearing of the appeal. No satisfactory explanation has been provided to me as to why there has been this undue delay.

5.The summons before me is for a stay of the injunction order in respect of the pipeworks pending the disposal of the appeal.  That is what the summons says.  However, Mr Chan, for the IO, has this morning confirmed that he is no longer applying for a stay of the order pending the disposal of the appeal.  Instead, he is asking for an extension of time so that the IO can comply with the order.

6.The evidence before me shows that the IO has not been expeditious in trying to comply with the order. It was only on 5 November the last day for compliance of the order that this summons was taken out.  And the expert report has only been recently obtained although there had been inspections by the expert a few months ago.  No satisfactory explanation has been provided to me for this delay in seeking to comply with the mandatory injunction.

7.On the evidence before me it is likely that the costs of the reinstatement works may well exceed the cap of $200,000.00 provided for under s. 20A(2)(a) of the Building Management Ordinance (Cap. 344) as submitted by Mr Chan.  That means that there are procurement requirements under the Ordinance.  All that this means is that more time may be needed to obtain the necessary procurement.

8.Mr. Wright has fairly submitted in his submissions that from the expert report of the plaintiff the works should not require more than eight weeks to complete.  The plaintiff is prepared to accede to an extension of time limited to a maximum period of eight weeks. 

9.It seems to me that although the IO has not proceeded with reasonable expedition, more time is needed to comply with the order.  In view of the upcoming holidays and the intervening Christmas and Chinese New Year holidays I would be prepared to grant an extension of time up to 12 March 2011 for the IO to comply with the mandatory injunction.  That is the order I make.

10.Costs of the application to the plaintiffs.

(Arjan H. Sakhrani)
Judge of the Court of First Instance,
High Court

Mr Colin Wright, instructed by Messrs Orrick, Herrington & Sutcliffe, for the Plaintiffs

Mr Kenneth C. L. Chan, instructed by Messrs Tung, Ng, Tse & Heung, for the Defendant