Brington Engineering Ltd v. Cheerise Asia Ltd
Read the full judgment text of HCCT2/2010 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 18 August 2011 before Deputy High Court Judge Cheng, SC.
Construction and arbitration proceedings involving BRINGTON ENGINEERING LTD (Plaintiff) and CHEERISE ASIA LTD (Defendant). The court corrected the previous judgment paragraph to clarify that the plaintiff must pay the defendant $219,918.45 (being $751,918.45 less $532,000) with interest from the date of judgment. Costs are ordered against the plaintiff to pay the defendant on a party and party basis, taxed on District Court scale if not agreed. The corrigendum rectifies a prior error reversing the party liable for costs. Judgment date is 18 August 2011, with the corrigendum dated 30 August 2011.
Outcome: The plaintiff is ordered to pay the defendant a final sum of $219,918.45 with interest from the date of judgment.
|
HCCT2/2010 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 2 OF 2010 ------------------------------------ BETWEEN
------------------------------------ Before : Deputy High Court Judge Cheng, SC in Court Dates of Hearing : 12-15 April 2011 Date of Judgment : 18 August 2011 ------------------------------- C O R R I G E N D U M ------------------------------- The following paragraph to be added after paragraph 85 and becomes paragraph 86 on page 31:
The old paragraph 86 becomes new paragraph 87 on page 31:
Dated this 30th day of August 2011
| |||||||||||
Further hearings and rulings under HCCT2/2010