Wo Hing Engineering Ltd. V Tyco Engineering & Construction (Hong Kong) Ltd.

Read the full judgment text of CACV 1120/2000 on BabelCite. This 高等法院上訴法庭 judgment was delivered on 28 October 2002 before Hon Rogers VP, Le Pichon JA and Ma J.

Civil appeal concerning amendment of a Court of Appeal order under the slip rule. The plaintiff, Wo Hing Engineering Limited, was subcontractor under a contract valued at $80 million with a 3% profit entitlement. The defendant, Tyco Engineering & Construction (Hong Kong) Limited, failed to complete the work, causing Wo Hing to incur additional costs beyond the contract price. The initial Court of Appeal order specified a damages formula including '3% of the contract price plus any shortfall between actual costs and 97% of the contract price.' However, this formula did not correspond to the court’s intended principle that the plaintiff should receive its contracted 3% profit plus any additional incurred costs in full. Applying Order 20 rule 11 of the Rules of the High Court, the court allowed an application under the slip rule to correct the formula by deleting '97% of' to properly reflect the intended damages calculation. The order dated 17 April 2002 was thus amended accordingly.

Legal issues: Slip rule amendment of court order formula

Outcome: Order amended to delete the words '97% of' from paragraph 1(3) of the 17 April 2002 order

Cited by 7 cases

Case No.CACV 1120/2000
Court
高等法院上訴法庭
Date28 Oct 2002
JudgeHon Rogers VP, Le Pichon JA and Ma J
Case Document
100%Judiciary

CACV001120B/2000

CACV 1120/2000

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF APPEAL

CIVIL APPEAL NO. 1120 OF 2000

(ON APPEAL FROM HCCT NO. 40 OF 1999)

____________________

BETWEEN
WO HING ENGINEERING LIMITED Plaintiff
AND
TYCO ENGINEERING & CONSTRUCTION
(HONG KONG) LIMITED
Defendant

____________________

Coram: Hon Rogers VP, Le Pichon JA and Ma J

Date of Ruling: 28 October 2002

____________________

R U L I N G

____________________

1.This is an application under the slip rule to amend the order of the court dated 17 April 2002 and in particular paragraph 1(3) thereof which reads:

"The Defendant shall pay the Plaintiff further damages to be assessed by the Court below based on actual figures by applying the formula that the Plaintiff is entitled to 3% of the contract price plus any shortfall arising between actual costs incurred and 97% of the contract price."

2.This matter has been brought back before this court by notice of motion dated 30 July 2002. It has been occasioned by difficulties which arose in the court below on the interpretation of the order. In view of difficulties in reconvening the court with the counsel concerned, the parties have agreed that this matter be dealt with on paper following written submissions.

3.The background to this case is set out in the judgment of Le Pichon JA with which the other members of the court agreed. In brief, the plaintiff was a subcontractor in respect of works to be carried out for a lump sum of $80 million. The defendant became a sub-subcontractor and it was agreed that the plaintiff would be entitled to 3% of the contract price. The defendant did not complete the works and the plaintiff completed the works. The question then arose as to the extra costs involved over and above the contract price. At paragraph 10 of the judgment it was stated:

"Applying that principle to the facts of this case, had Tyco not been in breach, at a minimum, Wo Hing would have received 3% of the contract sum i.e. $2.4 million. If extra costs have had to be incurred in order to complete the contract, whether the cost of engaging a subcontractor to carry out the work or doing the work itself, as a matter of principle, Wo Hing is entitled to recover such additional costs."

Later in paragraph 11 when dealing with the question as to whether the plaintiff would be entitled to a profit of 10% on the project it was stated:

"But the fact that Wo Hing elected to perform the work itself did not, ipso facto, entitle it to earn a profit. In my judgment, what it is entitled to recover (apart from the 3%) would include any additional costs incurred: for, to that extent, it would have been out of pocket and should be reimbursed in order to be made whole."

4.The intention of the court was therefore clear. Unfortunately, in attempting to encapsulate that concept in a formula it was said:

"Expressed as a formula, Wo Hing is entitled to 3% of the contract price plus any shortfall arising between actual costs incurred and 97% of the contract price."

What was overlooked was that this formula did not encapsulate the intention of the court. The intention of the court in the passages quoted in paragraph 3 above was clear. It was that Wo Hing would be entitled to its contracted profit plus any extra costs. Those extra costs should have been calculated on the basis of the contract price since the 3% had already been taken into account. The words "97% of" in paragraph 1(3) were inserted into the formula in error. That error is obvious on reading the judgment. In the circumstances of this case it is appropriate to amend the order under the slip rule as an accidental slip under Order 20 rule 11 and of the Rules of the High Court. This court therefore orders that the order of 17 April 2002 be amended by deleting the words "97% of" in paragraph 1(3).

(Anthony Rogers) (Doreen Le Pichon) (Geoffrey Ma)
Vice-President Justice of Appeal Judge of the
Court of First Instance

Representation:

Mr Peter Graham, instructed by Messrs Deacons, for the Plaintiff/Respondent

Mr Peter Clayton, instructed by Messrs Denton Wilde Sapte, for the Defendant/Appellant