Wo Hing Engineering Ltd. V Tyco Engineering & Construction (Hong Kong) Ltd.
Read the full judgment text of CACV 1120/2000 on BabelCite. This 高等法院上訴法庭 judgment was delivered on 28 October 2002 before Hon Rogers VP, Le Pichon JA and Ma J.
Civil appeal concerning amendment of a Court of Appeal order under the slip rule. The plaintiff, Wo Hing Engineering Limited, was subcontractor under a contract valued at $80 million with a 3% profit entitlement. The defendant, Tyco Engineering & Construction (Hong Kong) Limited, failed to complete the work, causing Wo Hing to incur additional costs beyond the contract price. The initial Court of Appeal order specified a damages formula including '3% of the contract price plus any shortfall between actual costs and 97% of the contract price.' However, this formula did not correspond to the court’s intended principle that the plaintiff should receive its contracted 3% profit plus any additional incurred costs in full. Applying Order 20 rule 11 of the Rules of the High Court, the court allowed an application under the slip rule to correct the formula by deleting '97% of' to properly reflect the intended damages calculation. The order dated 17 April 2002 was thus amended accordingly.
Legal issues: Slip rule amendment of court order formula
Outcome: Order amended to delete the words '97% of' from paragraph 1(3) of the 17 April 2002 order
Cited by 7 cases
|
CACV001120B/2000 CACV 1120/2000 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 1120 OF 2000 (ON APPEAL FROM HCCT NO. 40 OF 1999) ____________________
____________________ Coram: Hon Rogers VP, Le Pichon JA and Ma J Date of Ruling: 28 October 2002 ____________________ R U L I N G ____________________ 1.This is an application under the slip rule to amend the order of the court dated 17 April 2002 and in particular paragraph 1(3) thereof which reads:
2.This matter has been brought back before this court by notice of motion dated 30 July 2002. It has been occasioned by difficulties which arose in the court below on the interpretation of the order. In view of difficulties in reconvening the court with the counsel concerned, the parties have agreed that this matter be dealt with on paper following written submissions. 3.The background to this case is set out in the judgment of Le Pichon JA with which the other members of the court agreed. In brief, the plaintiff was a subcontractor in respect of works to be carried out for a lump sum of $80 million. The defendant became a sub-subcontractor and it was agreed that the plaintiff would be entitled to 3% of the contract price. The defendant did not complete the works and the plaintiff completed the works. The question then arose as to the extra costs involved over and above the contract price. At paragraph 10 of the judgment it was stated:
Later in paragraph 11 when dealing with the question as to whether the plaintiff would be entitled to a profit of 10% on the project it was stated:
4.The intention of the court was therefore clear. Unfortunately, in attempting to encapsulate that concept in a formula it was said:
What was overlooked was that this formula did not encapsulate the intention of the court. The intention of the court in the passages quoted in paragraph 3 above was clear. It was that Wo Hing would be entitled to its contracted profit plus any extra costs. Those extra costs should have been calculated on the basis of the contract price since the 3% had already been taken into account. The words "97% of" in paragraph 1(3) were inserted into the formula in error. That error is obvious on reading the judgment. In the circumstances of this case it is appropriate to amend the order under the slip rule as an accidental slip under Order 20 rule 11 and of the Rules of the High Court. This court therefore orders that the order of 17 April 2002 be amended by deleting the words "97% of" in paragraph 1(3).
Representation: Mr Peter Graham, instructed by Messrs Deacons, for the Plaintiff/Respondent Mr Peter Clayton, instructed by Messrs Denton Wilde Sapte, for the Defendant/Appellant |
Other judgments that cite this case
Further hearings and rulings under CACV 1120/2000