Profit Success Development Ltd v. Appeal Tribunal (Buildings) and Another
Read the full judgment text of HCAL 94/2011 on BabelCite. This High Court CFI judgment was delivered on 8 November 2012.
1. This is the applicant’s application for judicial review against the decision (“the Decision”) of the Appeal Tribunal (Buildings) (“the Tribunal”) dated 3 August 2011. By the Decision, the Tribunal dismissed the applicant’s appeal against a demolition and re-instatement order dated 21 August 2009 (“the Order”) issued by the Building Authority (“the BA”) in respect of two building works located at an industrial building (“the Building”) in Kwun Tong.
Cited by 2 cases · Cites 1 case
|
HCAL94/2011 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST NO 94 OF 2011 _______________
______________ J U D G M E N T ______________ A. INTRODUCTION 1.This is the applicant’s application for judicial review against the decision (“the Decision”) of the Appeal Tribunal (Buildings) (“the Tribunal”) dated 3 August 2011. By the Decision, the Tribunal dismissed the applicant’s appeal against a demolition and re-instatement order dated 21 August 2009 (“the Order”) issued by the Building Authority (“the BA”) in respect of two building works located at an industrial building (“the Building”) in Kwun Tong. 2.The Order relates to the following two alleged building works at the Building:
3.The applicant now seeks to quash the Decision and for an order to require a differently constituted Tribunal to re‑consider the Decision in accordance with the law and allow the appeal. 4.The Tribunal as the respondent takes a neutral stance in this application and has not taken any parts in it. The BA is joined as the interested party and opposes the application. B. THE FACTS B1.1 The Building and the Structures 5.The applicant is the owner of the Building. Anderson Concrete Ltd (“ACL”) is the lessee. 6.The Building is situated near the sea and has been used by ACL for its concrete mixing operations. 7.Structure 1 is a container and fully enclosed. It is made of metal sheets and transparent panels that rest on metal frames. It is of approximately 9m x 4m and 3.5m and erected on 1/F carpark area of the Building. It weighs about 12,000kg. 8.Structure 2 is approximately 35m x 8m x 7m and consists of metal platforms of 6 levels together with linking staircases to all levels. It is erected above the ramped driveway from G/F to 1/F of the Building. 9.The Tribunal describes in the Decision the operations of ACL as follows: cements and aggregates of various sizes are delivered to the Building by sea and then loaded onto the “cement and aggregate storage bins” by bucket elevators. The cement and aggregates are then unloaded in precise quantities from “cement and aggregate bins”. Through the hopper, the metal weight scale and various other plant and equipment installed at the hopper room mix with water and admixture (supplied by the water tank and the 12 number of admixture tank sit on the metal platform of Structure 2), unto the ready-mix concrete trucks for delivery to construction sites. B1.2 The Buildings Ordinance 10.Under s 14(1) of the Buildings Ordinance (Cap 123) (“BO”), save some exceptions provided under the BO, no person shall commence or carry out, inter alia, any building works without having first obtained from the BA[1] (a) his approval in writing of building plans submitted to him in accordance with the regulations, and (b) his consent in writing for the commencement of the building works. 11.Under s 2 of the BO, “building works” is defined as follows:
12.S 24(1) of the BO provides effectively that, where any building works have been carried out in contravention of any of the provisions in the BO, the BA may issue an order in writing requiring the demolition of that building works and reinstatement. B1.3 The Order and the appeal before the Tribunal 13.On 21 August 2009, the BA issued the Order to the applicant under s 24(1) of the BO in respect of Structures 1 and 2 (collectively, “the Structures”). It is the BA’s position that the Structures were building works carried out in contravention of s 14 of the BO, as no approval of any building plans relating to these building works and consent for their commencement had been first obtained from the BA. 14.The Order requires the applicant to (amongst others):
15.On 9 September 2009, the applicant filed the Notice of Appeal against the BA’s decision to issue the Order. 16.After filing various documents and written representations, the appeal was heard before the Tribunal in March and May of 2011 for a total of 7 days. A site inspection was also carried out on 16 March 2011. 17.The Tribunal delivered the Decision in writing on 3 August 2011, dismissing the appeal. B1.4 The Decision 18.The applicant raised a number of grounds to challenge the Order before the Tribunal. 19.For the present purposes, two of these appeal grounds are more relevant to this judicial review. They can be summarised as follows:
20.The Tribunal in the Decision rejected all the grounds (including the above two grounds) raised by the applicant and dismissed the appeal. 21.On 1 November 2011, the applicant applied for leave for judicial review against the Decision, where leave was granted on 11 November. C. GROUNDS OF JUDICIAL REVIEW C1. Failure to give any or any adequate reasons 22.The first ground of the judicial review relates to the Decision in rejecting the building works ground. 23.There is no dispute between the parties that fairness requires the Tribunal as the body hearing the appeal to give adequate and intelligible reasons for its decision, and the failure to do so could amount to a valid ground in judicial review to quash the decision. See: Lo Yin Ming v Appeal Tribunal v Appeal Tribunal (Buildings) [2011] 3 HKLRD 586, paragraph 11 per Lam J (as he then was); Smart Gain Investment Ltd v Town Planning Board (unrep, HCAL 12/2007, 6 November 2007), at paragraphs 29-30, 82-85 per A Cheung J (as he then was); Oriental Daily Publishing Ltd v Commissioner for Television and Entertainment Licensing Authority (1997-98) 1 HKCFAR 279, at 288J‑292G per Li CJ. 24.It is the applicant’s contentions that in rejecting the building works ground, the Tribunal has failed to give any or any adequate reasons. The arguments run as follows. 25.In the appeal, it was the applicant’s submissions that whether certain works fell within the meaning of “building works” under the BO should be determined by reference to what was called the “functional test” as laid down in a number of English authorities relied on by the applicant. By applying the functional test (as further contended by the applicant before the Tribunal), Structures 1 and 2 should be regarded as “plant, machinery or equipment”. Once they are so properly regarded as plant, machinery or equipment under the Regulations, they are not building works. 26.The BA on the other hand submitted to the Tribunal that in determining whether the Structures fell within the meaning of building works, it should apply the test laid down in Leung Lai-so[2] by taking into account of all the circumstances of the case, which included the relevant factors (“the Relevant Factors”) such as[3]:
27.After setting out the contentions of the applicant and the BA at paragraphs 19 to 40 of the Decision, the Tribunal decided that (a) it should adopt the test in Leung Lai-so in determining whether the Structures amounted to building works or not, and (b) after taking into account of the Relevant Factors in the present case, it came to the finding that the Structures were building works. The Tribunal explained these at paragraphs 64 to 66 of the Decision as follows:
28.The applicant now submits that what the Tribunal had effectively said is simply that it had taken into account of the Relevant Factors in considering whether the Structures were building works, but the Tribunal had singularly failed to explain with any or any adequate reasons as to why and how after taking the Relevant Factors into account would have made the Structures building works. 29.In particular, the applicant complains that it is simply left in the dark to understand how and why, after taking into account of the Relevant Factors, the Tribunal had come to that finding. 30.I agree with the applicant. 31.In my view, by reading the Decision, and in particular paragraphs 64 to 66 thereof, one would not be objectively able to understand how, after taking into account of the Relevant Factors in the circumstances of the present case, it would have made the Structures building works but not plant or machinery:
32.For these reasons, in my view, the Tribunal has failed to give any or any adequate reasons as required by fairness to explain its bases in rejecting the building work ground. 33.Thus, I would allow the judicial review and quash the Decision on this ground. I would further remit the Decision back to the same Tribunal to reconsider the building works ground. C2. Error of law – the Tribunal misread or misunderstood Morrison v CIR 34.As mentioned above, under the building works ground, the applicant submitted that the test to be applied was the functional test. It relied on, inter alia, the authority of Morrison v Commissioner of Inland Revenue [1915] 1 KB 716. 35.In this ground of judicial review, Mr Ismail for the applicant submits that, in considering the intended use factor under the Relevant Factors, the Tribunal had misread Morrison and thus had taken into account of an irrelevant matter in its decision. This amounts to an error of law. 36.Mr Ismail develops his arguments as follows:
37.I reject these submissions:
38.I therefore reject this ground of judicial review. C3. Error of law – the Order is defective and reinstatement impossible 39.Under this ground, Mr Ismail contends that the Tribunal also misread or misunderstood the relevant approved building plans in its findings at paragraphs 69 and 70, 77 and 78 of the Decision. 40.Counsel then sets out in some details at paragraphs 57 to 61 of his skeleton submissions as to why he says the Tribunal had misread these building plans, and submits that the BA was “under a duty to ensure that relevant material was fairly and adequately presented to the Tribunal”. 41.The applicant then further submits that, as such, the Tribunal should have found that:
42.I have difficulty in understanding these submissions insofar as they are made to support that the Decision was made with an error of law:
43.I will therefore also reject these submissions. This ground of judicial review must similarly fail. C4. The Tribunal made mistakes of fact 44.The applicant says under this ground that the Tribunal made the following two errors of fact:
45.I find this ground in support of the judicial review wholly without merits:
46.I will therefore dismiss this ground with no hesitation. I must also say that I have serious reservation as to why counsel is prepared to advance such a ground which is clearly without merits. C5. The Tribunal erred in law in holding that the Order was not invalid, void or unenforceable 47.Under the invalidity ground, the applicant submitted before the Tribunal that the Order was invalid as itself was in breach of s 14(1) of the BO, because it required the applicant to commence demolition and reinstatement works (which were all building works under the BO) without first requiring it to obtain from the BA (a) his approval of the plans of the proposed works, and (b) his consent before commencement of these building works. 48.The Tribunal dismissed this ground and explained its reasons at paragraphs 67 to 68 of the Decision:
49.The applicant submits that the Tribunal erred in law under this part of its Decision in:
50.Mr Ng for the BA in this application does not appear to advance any arguments in support of this part of the reasoning of the Tribunal’s decision. I think rightly so. In my view the Tribunal’s above reasons are incorrect in law as submitted by the applicant. 51.However, Mr Ng submits that whether the Order is invalid is a matter of law and the court could decide it in this application. Counsel further contends that the Order is clearly in compliance with s 14(1) of the BO because:
52.In gist, the BA’s submissions are that the approval of the plans and the consent (as required under s 14(1) of the BO) in relation to the demolition and reinstatement works were already given by the BA at the time of the Order. 53.S 14(1) of the BO provides as follows:
54.As a matter of proper construction, I agree and hold that the wording of s 14(1) of the BO permits a situation where the BA can his approval and consent at the same time of issuing an order under s 24 of the BO. 55.However, as to whether (as a matter of fact) the demolition and reinstatement works specifically required to be carried out under the present Order need no further submission of any plans other than the previously “approved” plans, I do not know, as this relates to evidence. This is particularly so as demolition works themselves are “building works” under the BO, while at the same time the previously “approved plans” may be relevant only to the reinstatement works required under the Order. I have not been shown evidence which shows whether the previously “approved plans” can be properly regarded to cover and be relevant to the “demolition works” as well. This court is therefore not in a position to come a conclusion one way or the other as to whether (as a matter of fact) the necessary and relevant “approval” and “consent” under s 14(1) can be regarded as having already been given by the BA at the time of the Order. 56.For this reason, I would also quash the Decision on this basis, and remit this question back to the Tribunal to determine whether on the evidence and facts of the present case, the necessary approval and consent required under s 14(1) of the BO can been regarded as having already been given by the BA at the time of the Order. C6. The Tribunal failed to exercise its own independent discretion 57.S 50(2) of the BO provides the Tribunal with a discretion that, in determining an appeal, it may make an order confirming, varying or reversing the appealed decision, and make any such other order as it thinks fit. 58.The applicant now says the Tribunal simply failed to exercise this discretion independently, as the Tribunal said the following at paragraph 79 of the Decision:
59.These reasons (says the applicant) show that the Tribunal failed to exercise its discretion independently, as they are not proper reasons because:
60.With respect, there is nothing in this ground. 61.First, the matter must be looked at in the proper context and as a whole of the Decision. The Tribunal dismissed with its own reasons (rightly or wrongly) all the grounds advanced by the applicant in the appeal. As such, it had exercised its discretion under s 50 of the BO to confirm the Order. It clearly cannot be said that the Tribunal failed to exercise the discretion independently. 62.Second, the applicant’s above submissions amount to basically saying that the Tribunal’s reasons not to exercise its discretion in applicant’s favour are wrong. This is very different from saying that the Tribunal failed to exercise its discretion independently. 63.Thirdly, insofar as the applicant is challenging the Tribunal’s reasoning under Structure 2 as set out above, this again is in effect a challenge on a finding of fact based on the assessment of evidence, which is generally not permissible or available in judicial review (save if it amounts to an error of law, Wednesbury unreasonableness or irrationality). 64.I have no hesitation in dismissing this ground as well. C7. The Decision was irrational 65.As a cover-all ground, the applicant says for all the grounds it has advanced above, the Decision is also irrational in the public law sense. 66.As I said above, none of the grounds submitted above (including the grounds that I have allowed) supports a challenge that the Decision was irrational. I will also dismiss this ground. D. CONCLUSION 67.For the above reasons, I would allow this application and quash the Decision. I would further remit the appeal back to the same Tribunal for reconsideration of the following two questions:
68.As to costs, since the applicant is successful in this application, costs should generally follow the event. However, as indicated above, I am of the view that the grounds raised in support of this application and discussed at sections C3, C4, C6 and C7 above clearly have no merits and the applicant has thus unreasonably pursued them at the substantive hearing, which have incurred further costs and time. The applicant should not be entitled to recover these costs[5]. In the circumstances, in the exercise of my discretion, I think it is only just to make an order nisi that two-thirds of the costs of the present application be to the applicant, to be taxed if not agreed. The order shall be made absolute 14 days from today unless any of the parties applies by summons to vary it.
Mr Anthony Ismail, instructed by Mayer Brown JSM, for the applicant Attendance of the respondent was excused Mr Stanley Ng, instructed by the Department of Justice, for the interested party [1] Under the BO, the BA means the Director of Buildings. [2] Unrep, Appeal Tribunal (Building) Case No 44 of 2005, 31 October 2008. [3] See paragraphs 17 and 18 of the Reasons and Decision. [4] Cf: Lo Yin Ming v Appeal Tribunal v Appeal Tribunal (Buildings), supra,at paragraph 11 per Lam J (as he then was). [5] See: Re Elgindata Ltd (No 2) [1992] 1 WLR 1207. | |||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCAL 94/2011