Re Shunfeng Photovoltaic International Ltd
|
HCCW 194/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE COMPANIES (WINDING-UP) NO 194 OF 2012 ____________
____________
_______________ JUDGMENT _______________ 1.I have before me a petition issued on 5 June 2012 by Allen & Overy seeking a winding-up order against the Company on the ground of insolvency. Allen & Overy relied to prove insolvency on a statutory demand issued in respect of alleged outstanding professional fees incurred in connection with the initial public offering of the Company which was listed on the Stock Exchange of Hong Kong Limited on 13 July 2011. 2.At the commencement of the hearing I granted the Company leave to file two further affirmations of Mr Tse Man Kit Keith and Zhu Chunxiao in the face of opposition from the Petitioner although as matters transpired nothing turned on the contents of the new affirmations. 3.Allen & Overy’s claim arises in the following circumstances. In 2010 the Company had plans for listing in Hong Kong. It engaged Macquarie Capital Securities Limited (“Macquarie”) to assist it. The Petitioner was engaged by Macquarie. An engagement letter was prepared by Allen & Overy which is dated 13 January 2011 which was signed by Macquarie as client and the Petitioner. The Company also signed on the engagement letter to confirm its agreement to pay the Petitioner’s fees as set out in the engagement letter. The material provisions of the engagement letter are as follows:
4.As can be seen the engagement letter provided for a cap to Allen & Overy’s fees of US$850,000. In April 2011 Macquarie withdrew as sole bookrunner for the IPO. The Company then secured CMB International and Daiwa as joint bookrunners. In May 2011 the Petitioner produced a draft supplementary agreement which included an increased fee cap. There is no dispute that the Company refused to sign it. Nevertheless, after the Company’s successful listing on 13 July 2011, in October 2011 Allen & Overy sent its last invoice to the Company. The total amount billed was US$1,250,000 which exceeded the fee cap by US$400,000. 5.The Company refused to pay more than the agreed fee of US$850,000. It is the difference of US$400,000 which is the debt referred to in the statutory demand. During the course of argument, both counsel accepted that the petition falls to be determined on the construction of the terms of agreement I have referred to above. Allen & Overy argued that if any of the assumptions referred to in clause 9 applied for any reason, the fee cap no longer applied and Allen & Overy was entitled to charge for its professional services on a time charge basis at the rates set out in clause 7 of the engagement letter. 6.As will be apparent from what I have said above the listing took place 13 days after the date assumed in clause 9.1(a). Therefore, Allen & Overy argues that it is entitled to charge for its professional services on a time charge basis. The Company argues that the fee cap only ceased to apply if one of the assumptions ceased to apply and resulted in Allen & Overy having to do materially more work. It does not accept that Allen & Overy had to do materially more work although it accepts that assumption 9.1(a) on its face ceased to apply. 7.Ms Eva Sit who appeared for the Petitioner accepted that if I found the Company’s construction was clearly arguable, a bona fide dispute on substantial grounds would have been demonstrated and the petition should be dismissed. Conversely Mr Bernard Man who appeared for the Company accepted that if I was persuaded that the Petitioner’s construction was clearly correct, as the assumption in clause 9.1(a) had clearly ceased to apply, Allen & Overy were entitled to charge for their professional services on a time charge basis and the Company would pay the outstanding sum claimed of US$400,000. 8.Lord Hoffman considered how the court should approach the construction of the terms of a written agreement in Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896, 913B:
9.The question is therefore what should the parties be reasonably have taken to have intended by the relevant terms of the Agreement. Both counsel accept that I do not have to make final determination of the issue, what I should do is to determine whether the Company’s construction has sufficient substance that the matter should go to trial. In my view it does. Clause 6 provides that Allen & Overy would not charge more than US$850,000 “subject to our scope of work and principal assumptions” which are set out in clause 9. It seems to me that it is at least arguable that the parties would have understood this to mean that the fees were capped as long as Allen & Overy did not have to do more work than was anticipated at the time the agreement was made and that this is to be assessed by reference to the scope of work and the assumptions. It is therefore arguable that only if an assumption ceased to apply and as a result materially more work had to be done does the fee cap cease to apply. 10.It seems to me far from clear that any deviation from the assumptions, however small, would have been understood by the parties to allow Allen & Overy to charge for all its work on a time basis and I find nothing in the language used in clauses 6 and 9 that compels such an interpretation of the agreement. I will therefore dismiss the petition. The Petitioner shall pay the Company’s costs.
Ms Eva Sit, instructed by Allen & Overy, for the petitioner Mr Bernard Man, instructed by Baker & Mckenzie, for the company Attendance of the Official Receiver was excused |