Longest Profit (Hong Kong) Ltd v. Appeal Tribunal (Buildings)
|
HCAL14/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST NO 14 OF 2012 _______________
______________________________ REASONS FOR JUDGMENT __________________________ Introduction 1.Longest Profit (Hong Kong) Limited (“LPL”) is and was at all material times the registered owner of the remaining portion of Lot No 613 and Lot No 1229 of DD 453, Tsuen Wan, New Territories (“the Lots”). 2.On 23 March 2010, the Building Authority issued a demolition and reinstatement order in respect of the unauthorized building works carried out at the Lots under section 24(1) of the Buildings Ordinance[1] (“the Order”). On 12 April 2010, LPL appealed against the Order to the Appeal Tribunal. At the preliminary hearing on 11 October 2011 (“the Preliminary Hearing”), the Tribunal was satisfied that LPL had not show good cause for a full hearing and dismissed the appeal (“the Decision”). 3.The Decision was made pursuant to section 49 of the Buildings Ordinance, which provides :
4.On 5 June 2012, LPL obtained leave to apply for judicial review against the Decision. This is the substantive hearing of the judicial review. LPL sought to quash the Decision and for an order to require the Tribunal to re-consider the Decision in accordance with the law. 5.Although the Tribunal has been named as the respondent, it adopts a neutral stance. The Building Authority has been joined as an interested party and is opposing the application. 6.After hearing the parties, I dismissed the application for judicial review. These are the reasons for my judgment. Events leading to the issue of the Order 7.In February and March 2010, the Buildings Department received complaints about certain unauthorized building works being carried out on the Lots. On 27 February 2010, a surveyor firm engaged by the Buildings Department inspected the Lots and discovered that some building works were in progress although no access could be gained to them. Two buildings were under construction covered with green plastic sheet and scaffoldings. An advisory letter was posted up on site at the time of inspection, requesting the owner/occupier of the Lots to cease and to remove the unauthorized works. 8.On 11 March 2010, the Buildings Department carried out its own inspection of the Lots. It discovered construction of a 3-stroty structure (“the Structure”), 5 singles-storey structures and a retaining wall (“UBWs”). In particular, the Structure looked different from the structure depicted in the photographs taken of the Lots in about 1962 and 1999.[2] LPL has been making use of the Structure and the UBWs as columbarium in breach of the permitted land use of the Lots, which is agriculture. 9.On 16 March 2010, a further advisory letter was issued to LPL requesting it to remove the Structure and the UBWs. 10.On 23 March 2010, the Buildings Authority issued and served the Order to LPL and another occupier of the Lots, requiring them to remove the Structure and the UBWs and to reinstate the parts of the Lots affected by them. However, further inspections in April and June 2010 revealed that the Structure and the UBWs remained intact despite the Order. The Decision 11.As said, LPL appealed against the Decision to the Tribunal on 12 April 2010. At the Preliminary Hearing, as a result of LPL’s concession, the Structure was left as the only outstanding issue before the Tribunal. 12.LPL argued that the Structure had been in existence since 1960s. The works depicted in the photographs taken by the Building Authority were merely renovation works which did not involve the structure of the building. They were therefore exempted works under section 41(3) of the Buildings Ordinance. 13.The Building Authority contended that based on the evidence collected from the inspections, the Structure was a new building. Alternatively, even if it was an existing building as alleged by LPL, the on-going works carried out to it were not exempted works under section 41(3) of the Buildings Ordinance. They were thus unauthorized and should be removed upon the Building Authority’s order under section 24 of the Buildings Ordinance. 14.The Tribunal dealt with the matter thus :
Discussion 15.In mounting the present application for judicial review, LPL relied on two grounds, namely the Decision was irrational and procedurally unfair. As will be seen in a moment, it is not necessary for present purposes to deal with these grounds in great detail. It will be sufficient to briefly deal with them as follows. 16.On irrationality, Mr Cheung, counsel for LPL, argued that the Tribunal failed to appreciate that the question to be determined at the preliminary hearing is whether good cause has been shown for holding a full hearing. The issue raised by LPL on appeal is a factual one, namely, whether the Structure, the subject of the Order, was the same structure as depicted in the photographs in 1962 and 1999. A proper determination could be made only after a full consideration of all of the evidence available, including evidence from live witnesses. At the Preliminary Hearing, the Tribunal questioned LPL if there was any evidence to support its case that the Structure was the same old building existed since 1960. The Applicant offered to call its representative as a witness to give live evidence. But the Tribunal elected not to hear that evidence at all. It was therefore wrong for the Tribunal to conclude that LPL was unable to substantial its claim when it was not permitted to do so. The Tribunal had erred in refusing to consider evidence relevant to the factual issue raised by LPL. It was an irrational decision. 17.Ms Wu, for the Building Authority, submitted that the court, when exercising its supervisory jurisdiction in judicial review, will not lightly interfere with the function of a decision maker to resolve disputed matters of fact. Here, the Tribunal had taken into account all the evidence available, including the photographs, the various features of the Structure and the building depicted in the photographs, the differences in those features (which I would add are obvious) in coming to the finding that it was a new building. 18.In my view, the Tribunal was entitled to take into account all the evidence then before it to determine if it was necessary to hear LPL’s live witness on this issue. On the evidence then available, which was rather overwhelming objectively, I cannot say that the Tribunal’s decision not to hear the live witness tendered by LPL is one which had no reasonable basis which warrants the court’s intervention on judicial review. 19.On procedural unfairness, Mr Cheung argued that at the Preliminary Hearing, the Building Authority orally submitted that the Structure was built of concrete whereas the structure in the photographs taken in 1962 and 1999 was built of bricks. The Tribunal erred in relying on this unsubstantiated oral assertion because it had never been disclosed to LPL that the Building Authority had conducted the relevant investigation. Further, apart from the oral submission made at the Preliminary Hearing, there was no evidence to support the assertion that the structure in the photographs taken in 1962 and 1999 was built of concrete. It was procedurally unfair for the Respondent to raise such a matter for the first time at the Preliminary Hearing. It was unfair that LPL was put in a position where it was unable to address the allegation. the Decision was therefore procedurally unfair. 20.However, as rightly pointed out by Ms Wu, there was evidence to substantiate the Building Authority’s case that the old building was made of brick. And this was a not new point either. The photographs relied on had long been disclosed to LPL and were included in the hearing bundle for the Preliminary Hearing. LPL had ample opportunity to deal with it if so desired. And LPL had never raised any objection to the production and use of the materials now complained of at the Preliminary Hearing. It now lies ill in LPL’s mouth to raise procedural unfairness as a ground for judicial review. 21.There is a further fatal point against LPL’s application, which is this. Mr Cheung’s submissions based entirely on the finding by the Tribunal that the Structure was a new one. But in reaching the Decision, the Tribunal also accepted the alternative submission of the Building Authority that even if the Structure was a new one as contended by LPL, the buildings works carried out thereat were unauthorized in that they were not exempted works under section 41(3) of the Buildings Ordinance. LPL had been given more than ample opportunity to deal with this matter at the Preliminary Hearing but it was unable to do so. So even assuming that the Tribunal had erred in the way as it did in finding that the Structure was a new one, the decision not to hold a full hearing was still a correct one. The attack based on irrationality or procedural unfairness relating to the Tribunal’s finding that the Structure was a new one, even if substantiated, does not assist LPL a bit. 22.I would add that when LPL applied for leave at the ex‑parte hearing, it had not drawn my attention to the fact that the Tribunal had found that the works carried out of the Structure were unauthorized. That is material non-disclosure. Had LPL done so, I would not have granted leave because the intended application for judicial review would be plainly unarguable. Conclusion 23.For the above reasons, the judicial review against the Decision must fail. It was therefore dismissed.
Mr Albert Cheung, instructed by Wong, Fung & Co, for the applicant The respondent, absent Ms Teresa Wu, instructed by the Department of Justice, for the interested party [1] Cap 123. [2] The photographs of the Structure appear at the Bundle of Exhibits (BE) at pp 74‑75, that of the Property taken in 1962 and 1999, at BE/77 and BE/78 respectively. Please refer to CACV60/2013 for the relevant appeal(s) to the Court of Appeal. | |||||||||||||||||||||||||||||