Tim Lee Construction Engineering Co Ltd v. Kwong Wah t/a Super King Engineering Co
Read the full judgment text of CACV 120/2012 on BabelCite. This 高等法院上訴法庭 judgment was delivered on 15 March 2013 before Hon Fok, Lam JJA and McWalters J.
Contract Law — Sub-sub-contracting — Works Orders — Withdrawal and Reduction of Works — Proof of Damages — Evidence — Pre-judgment Interest — Costs — Burden of Proof. The Plaintiff, a sub-sub-contractor, claimed damages for wrongful withdrawal or reduction of works under certain Works Orders issued by The Link and sub-contracted by the Defendant. The trial court found the Plaintiff failed to prove the extent of the works withdrawn and its loss of profits, partly due to unreliable estimated values and the inadmissibility of financial statements due to late disclosure and insufficient supporting documentation. The appellate court upheld these findings, emphasizing the Plaintiff’s burden to present a full and clear case on damages. The appellate court also upheld the trial judge’s discretion to refuse pre-judgment interest from writ date to amendment date due to substantial amendments to pleadings that changed the claims’ clarity. Costs of the counterclaim were confirmed as included within costs of the action awarded to the Plaintiff. Appeal dismissed with costs.
Legal issues: Proof of damages for wrongful withdrawal or reduction of works · Discretion to award pre-judgment interest · Costs of counterclaim included in costs of action
Outcome: Appeal dismissed with costs
Cited by 1 case · Cites 2 cases
|
CACV 120/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 120 OF 2012 (ON APPEAL FROM HCCT NO. 18 OF 2010) ________________________ BETWEEN
________________________ Before : Hon Fok, Lam JJA and McWalters J in Court Date of Hearing : 15 March 2013 Date of Judgment : 15 March 2013 Date of Reasons for Judgment : 19 March 2013 _________________________ REASONS FOR JUDGMENT _________________________ Hon Lam JA (giving the Reasons for Judgment of the Court): 1.The Plaintiff was a sub-sub-contractor in respect of some maintenance works at housing estates under the management of The Link. The Defendant was the sub-contractor. The dispute between the parties is about some works orders issued by The Link which were sub-sub-contracted by the Defendant to the Plaintiff and the works done pursuant to the same. The case was tried before Recorder A Ho SC [“the Recorder”]. By a judgment of 20 April 2012 [“the Judgment”] as supplemented by his decision of 10 May 2012, the Recorder gave judgment in favour of the Plaintiff in the sum of $341,031.53 with interest from 27 July 2010 until date of judgment at 1% over the Hongkong Shanghai Banking Corporation’s best lending rate from time to time, thereafter at judgment rate until payment. 2.This is an appeal by the Plaintiff against that judgment. In a nutshell, the Plaintiff contended that the Recorder should also award damages in its favour in respect of some works orders for which the scope of works had been reduced or cancelled after orders had been issued. The Plaintiff also complained about the refusal of the Recorder to award it interests from date of writ (17 September 2007 to 27 July 2010) and the costs for the counterclaim. 3.Initially, the Plaintiff also appealed in respect of the costs of labour and granite tiles, see paras 1 to 3 of the grounds in the Notice of Appeal. Mr Chong (appearing together with Ms Yip for the Plaintiff) abandoned this part of the appeal. 4.After hearing the parties, we dismissed the appeal for reasons to be handed down later. Here are our reasons. 5.In respect of the giving instructions for works, the relevant facts are, as set out by the Recorder at paras 7 to 9,
6.There were other works orders for which there is no complaint regarding withdrawal or reduction of works. The reduction in works under Works Orders 1,2 and 3 7.The Recorder set out the complaints of the Plaintiff about Works Orders 1, 2 and 3 at paras 52 to 56, “52. Tim Lee alleged that there had been (i) a withdrawal of the entire 2nd WO; and (ii) a “scaling‑down” of the scope of works under the 1st and 3rd WOs5[[1]]. Tim Lee’s complaint was that such withdrawal or reduction in the scope of works had deprived it of the opportunity to complete the works and earn the corresponding profits.
8.Whilst accepting that withdrawal of works (either reduction in scope or removal of works) is capable of being a breach of the contract, the Recorder found that the Plaintiff had failed to discharge the burden of proof in establishing the extent of works withdrawn in respect of these 3 Works Orders. The reasons for such finding are at paras 62 to 65, “62. To begin with, the WOs contained only a general description of the works involved. It must be envisaged that details of the works would be supplemented by further instructions, including drawings or instructions on site by the project surveyor, or otherwise. Hence, for instance, the Notes in the WOs provided that the areas of works would be defined by drawings and to be clarified on site.
9.The Recorder also held that the Plaintiff had failed to prove the profit it would have earned on the alleged withdrawn works. The Recorder found that the methodology adopted by the Plaintiff to prove its profit margin was unsatisfactory, see paras 66 to 68 of the Judgment. 10.The Recorder further held that the 2 sets of financial statements which the Plaintiff sought to rely upon should not be admitted as evidence due to late disclosure and lack of proper supporting documentation. 11.Mr Chong submitted that the Recorder had found that the Defendant had breached the contract by withdrawing or reducing works from the Plaintiff at para 60 of the Judgment. With respect, that plainly was not what the Recorder found. His Lordship only accepted in that paragraph that withdrawal or reduction of works were capable of being a breach of contract. 12.Mr Chong then submitted that the Recorder found reduction in terms of the estimated values of the 3 Works Orders at para 55 of the Judgment. That is correct. Mr Chong then referred to para 53 of the Judgment where the Recorder found that the Plaintiff had taken steps to perform the works when the instruction to cancel Works Order 2 was issued. 13.Counsel contended in light of these findings the Recorder erred in holding that the Plaintiff had not proved which part of works had been withdrawn and that damages had not been proved. He submitted that one could proceed by using the differences in the estimated values as set out in para 55 of the Judgment as base figures and adopting the 7% reflected in the financial statements to work out the Plaintiff’s loss of profit stemming from such withdrawal of works. 14.We cannot accept these submissions. It must be borne in mind that in a contract claim, the burden is on a plaintiff to prove damages. A plaintiff who proved a breach but not damages (including the quantum) cannot get any substantial relief. In Born Chief Co v George Tsai [1996] 2 HKLR 188, Nazareth VP said at p.195,
15.In substance, what the Recorder found was that though there might be a substantial reduction in the scope of works, the extent of reduction could not be proved by comparing the estimated values. This is a finding perfectly open to the Recorder given his findings at paras 62 and 63 which Mr Chong did not even begin to challenge (and these are primarily finding of facts which can only be challenged on appeal if they are plainly wrong, see Ting Kwok Keung v Tam Dick Yuen [2002] 5 HKCFAR 336). 16.As submitted by Mr Clayton SC (appearing with Mr Yan for the Defendant) at para 3.4(1) of his written submissions, there are problems with reliance being placed on the estimated values,
17.Therefore the Recorder acted properly in requiring more precise proof of the reduction. As to that, unfortunately, the Plaintiff had nothing to offer. 18.As regards the 7 % profit margin, the Recorder held that the financial statements were inadmissible due to late disclosure. Mr Chong contended that the holding was wrong because the financial statements had been audited by independent auditors and filed with the Inland Revenue Department. As such, he contended that there was no prejudice to the Defendant to admit those statements. Mr Clayton did not accept that there was no prejudice arising from the late disclosure. At para 3.7 of his written submissions in this appeal, counsel referred to the non-disclosure of documentations relating to consultancy fees and the distortion such consultancy fees might produce on the profit margin. This was the point picked up by the Recorder at para 67 of the Judgment. 19.The decision to exclude the financial statements was a case management decision which this court would not disturb unless it is clearly wrong, see厦門新景地集團有限公司v Eton Properties HCMP 13 of 2012, 14 Feb 2012, para 9. Mr Chong accepted that the Recorder did exercise case management discretion in excluding such evidence. Counsel referred to the lack of prejudice on the part of the Defendant and other matters set out in his written submissions to challenge that exercise of discretion. However, he had not been able advance a submission by reference to one of the recognised grounds for challenging discretion set out at para 9 of Eton Properties. 20.In the present circumstances, we are not satisfied that Mr Chong had made out a case for interfering with this decision of the Recorder. On the contrary, it seems to us to be a correct decision. Given the submission of Mr Clayton on consultancy fee documentation, had the Recorder granted leave to the Plaintiff to use the financial statements, he would have to grant an adjournment to enable the Defendant to obtain the supporting documentation by way of discovery and that would disrupt the trial. It is also relevant to note that Mr Chong did not give any explanation on behalf of the Plaintiff as regards the late disclosure. 21.Without the financial statements, the Main Contractor’s bills (which the Recorder also addressed at para 70 of the Judgment) cannot prove anything. Mr Chong’s reliance on these documents to show that a profit margin of 7% is a reasonable one is neither here nor there. 22.As a fall-back position, Mr Chong asked the court to assess the damages as best as it can to do justice to the Plaintiff. We do not find that option to be viable. As observed by Nazareth VP in Born Chief a plaintiff is expected to present its entire case before the court. He cannot expect the judge (or the Court of Appeal for that matter) to engage in a speculative exercise to fill in gaps in terms of proof of damages when he did not prepare the necessary evidence for trial. Works Order 5 23.In respect of this Order, the Recorder found that the ceiling works and part of the toilet improvement works had been wrongfully removed from the Plaintiff by the Defendant. However, he found that the Plaintiff had failed to prove the quantum of its loss of profit because it adopted the same unreliable methodology as in the case of Works Order 1 to 3. 24.For the reasons already given, the Recorder was correct in so holding. Interest 25.The Recorder deprived the Plaintiff of interest on the judgment sum from date of writ to 27 July 2010 on the ground that the Plaintiff had completely revamped its pleadings on that date and the case as pleaded before that amendment was not clear. 26.The award of pre-judgment interest is a matter of discretion for the trial judge. An appellate court would not interfere with the exercise of such discretion unless one of the established grounds for interfering with the primary exercise of discretion can be shown, see Hong Kong Civil Procedure 2013 paras 6/L/9; 59/0/54. 27.Mr Chong submitted that in principle interest should run from the moment the cause of action accrued and, absent unwarrantable delay in the institution of legal proceedings, there should not be any departure from that. He cited para 15-078 of McGregor on Damages 18th Edn. 28.Whilst we accept the starting point is that interest should run from date of writ, we do not think the exercise of discretion is fettered by limiting it to cases where there is unjustified delay in the commencement of proceedings. We are of the view that it is in line with the spirit of the CJR and the underlying objectives in Order 1A Rule 1 for the court to exercise such discretion with reference to how the case has been pleaded at different stages of the action. Under Order 1A Rule 2(1)(a), the court shall seek to give effect to the underlying objectives when exercising any of its power and that, in our view, can include the power to award pre-judgment interest. Proper and clear formulation of one’s claims in pleadings is an important element in the furtherance of the underlying objectives. The Recorder was correct in law in taking account of the changes in the formulation of the Plaintiff’s claim at different stages in the exercise of his discretion on awarding interest. 29.Mr Chong submitted that the amendments in July 2010 did not materially affect any obligation of the Defendant and no new causes of action had been added. 30.With respect, we do not agree. The judgment awarded by the Recorder in favour of the Plaintiff is made up of three components,
31.We cannot find any claim for (a) in the pleadings prior to the 2010 amendments. Though there was a general plea for arrears at the original para 12 of the Statement of Claim, the Recorder was correct in saying that the paragraph did not clearly set out how the figures in the breakdown of those claims were arrived at in the manner as per the Re-amended Statement of Claim. 32.In the circumstances, we are not prepared to say that the Recorder erred in fact or law in the exercise of his discretion. Nor do we think his exercise of discretion was outside the generous range of reasonable differences on how interest should be awarded in such circumstances. Thus, we cannot interfere with the Recorder’s decision. Costs on the counterclaim 33.The Defendant abandoned the counterclaim at the court below. The Recorder gave the costs of the action to the Plaintiff, see para 151 of the Judgment and the formal sealed judgment. 34.Costs of the action include costs of the counterclaim. 35.This order nisi was varied by an order for costs on 28 August 2012. Paragraph 1(1) of that order made it crystal clear that the Recorder included costs of the counterclaim in the costs of the action. 36.The actual variations in the order of 28 August 2010 have no bearing on the issues before us. 37.We do not understand why the Plaintiff deemed it necessary to appeal in this respect when the Recorder’s order for costs on the counterclaim was in its favour. When Mr Chong was asked about this in the course of hearing, apart from saying that it was not clear whether costs of the action included costs of the counterclaim, he could not advance further submissions. The alleged uncertainty as to the scope of the expression “costs of the action” is manifestly a false point, especially in light of the terms of the order of 28 August 2010. In the end, Mr Chong accepted he could not pursue this ground of appeal. Disposition 38.For these reasons the appeal was dismissed with costs.
Mr K M Chong and Ms Yvonne Yip instructed by Lam, Lee & Lai, for the Plaintiff (Appellant). Mr Peter Clayton, SC and Mr Yan Kwok Wing instructed by Chan & Associates, for the Defendant (Respondent). [1] §11 & 3rd Sch, Re‑Re‑Re‑Amended Statement of Claim [2] §38(a), Re‑Re‑Re‑Amended Defence and Counterclaim [3] Para 6(b) of his witness statement – Bundle pp174 & 175. Mr Chong was cross-examined on Tim Lee’s use of the EVs in the claim. Tim Lee has failed to put the relevant transcript before the Court. However the disparity between EVs and final assessment can be demonstrated on the documents. [4] Para 28 of his supplemental witness statement – Bundle pp250 & 251. [5] Bundle p318. [6] The Court below found that the works were completed before the issue of the varied WOs – para 55 of the Judgment – Bundle pp137 & 138. [7] Bundle p347. [8] Bundle p364 – table at the top. |
Cases cited in this judgment
Other judgments that cite this case