Continental Zone Ltd v. More Glory International Ltd
Read the full judgment text of HCMP 446/2012 on BabelCite. This High Court CFI judgment was delivered on 18 April 2013.
1. This is a vendor and purchaser summons. The Plaintiff was the purchaser and the Defendant the vendor of Shop A (No. 27 Boundary Street) on Ground Floor, Hang Shun Building, Nos. 27-41 Boundary Street, Kowloon (“ the Property ”) under an agreement dated 23 June 2011 (“ the Agreement ”).
Cited by 6 cases · Cites 10 cases
|
HCMP 446/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE MISCELLANEOUS PROCEEDINGS NO 446 OF 2012 ____________
____________
____________
_______________ J U D G M E N T _______________ THE ORIGINATING SUMMONS 1.This is a vendor and purchaser summons. The Plaintiff was the purchaser and the Defendant the vendor of Shop A (No. 27 Boundary Street) on Ground Floor, Hang Shun Building, Nos. 27-41 Boundary Street, Kowloon (“the Property”) under an agreement dated 23 June 2011 (“the Agreement”). 2.The Originating Summons has been ordered by consent to be heard on the basis of the affirmations filed without cross-examination. On the day of the hearing, Ms Wong (for the Plaintiff) and Mr Li (for the Defendant) confirmed to me that they remained contented to do that. THE PARTIES’ RESPECTIVE CASE, AND THE RELIEF SOUGHT 3.It is the Plaintiff’s case that the Defendant has failed to showed and give title. In so far as the alleged failure to show title is concerned, it is said that the Defendant has failed to answer two alleged requisitions sufficiently or satisfactorily. I said “alleged” as the Defendant denies that they were properly formulated requisitions. I will come to that. The two alleged requisitions related to certain unauthorized building works within the Property. The first one was requisition no. 16 (“Requisition 16”) contained in a letter dated 17 August 2011 from the Plaintiff’s solicitors (Messrs. Wong & Co., “W&C”) to the Defendant’s solicitors (Messrs. Edmund W.H. Chow & Co., (“EC”). The other one was said to be contained in another letter of 6 December 2011 (“the LLT Requisition”) from W&C. The Plaintiff says further that due to the existence of those unauthorized building works, the Defendant has in any event failed to give title. When opening her case before me, Ms Wong stated that her primary case was that the Defendant had failed to give title. The Plaintiff seeks a number of declarations, primarily that the Defendant has failed to show and/or give title to the Property, and that the Plaintiff has lawfully rescinded the Agreement. The Plaintiff seeks consequentially return of the deposit that it has paid in the amount of HK$1.2 million, and damages. 4.The Defendant’s position was summarised by Mr Li in his written submission as follows, that (1) in respect of Requisition 16, it was not a proper requisition or that it had been sufficiently dealt with; (2) in respect of the LLT Requisition, no requisition was in fact contained in the letter of 6 December 2011 from W&C. Instead, the Plaintiff had by that same letter already repudiated the Agreement which the Defendant had reserved the right to accept and which it had subsequently accepted; and (3) if the letter of 6 December 2011 contained any valid requisition, it was late and/or the Defendant should have given reasonable time to deal with it and/or the Defendant had sufficiently dealt with it by an offer (to remove the unauthorized building works and to complete at a reduced price) which the Plaintiff did not accept. The Defendant thus counterclaims for a Declaration that the Defendant was entitled to forfeit the deposit. It also claims certain wasted conveyancing expenses. THE FACTS 5.By an assignment dated 16 December 2010, the Defendant was assigned the Property. 6.The Plaintiff was incorporated on 4January 2011. The amount of its paid up capital was HK$10. Mr Tsang Ming Lun (“Mr Tsang”) was its director. 7.On 23 June 2011, the parties entered into a preliminary agreement for the sale and purchase of the Property. It was the Agreement mentioned in paragraph 1 above. No plan defining the boundary of the Property was attached. The Property was agreed to be sold subject to the existing tenancy and on “as is” basis. The purchase price was HK$12 million. The Plaintiff was required to pay deposit in the total sum of HK$1.2 million (“the Deposit”), which it did. The Agreement provided for the execution of a formal sale and purchase agreement on or before 14 July 2011. None has however been signed. Completion was set to take place on 14 December 2011. The Agreement contained no provision regulating the making or answering of requisitions. 8.Prior to the execution of the Agreement, Mr. Tsang had inspected the Property. 9.On 5 August 2011, title documents of the Property were delivered by EC to W&C. Amongst them was Assignment Memorial No. 3027195 which contained a plan of the Property. 10.By a letter dated 17 August 2011 to EC, W&C on behalf of the Plaintiff raised a number of requisitions. Requisition 16 was the one in dispute, and was in the following terms:-
W&C further said in the letter that “We reserve all our client’s right to raise further requisitions on title of the Property.” 11.The reply from EC was contained in their letter of 8 November 2011, in the following terms:-
12.By letter of 8 November 2011 from W&C to EC, the Plaintiff requested an extension of time for completion for 3 months. The Defendant did not agree. 13.According to paragraph 10 of Mr Tsang’s first affirmation,
14.The nature of the alleged unauthorised building works (collectively called “the Unauthorized Building Works”) is important. I reproduce in full the letter of 5 December 2011 issued by LLT (“the LLT Report”):-
15.Attached to the LLT Report were a Ground Floor Part Plan (“Ground Floor Part Plan”) and four photographs. Marked on the Ground Floor Part Plan were amongst other things two elongated rectangles which extended and protruded from the building boundary line. They were described as “Unauthorized shop area encroached on public foot path” and “Unauthorised steel deck and shop area encroached on existing scavenging lane”. Also marked on the Plan were two other rectangles drawn in dotted lines which were described as “Unauthorized projected wall signage above” and “Unauthorized projected signage above”. The Unauthorized Building Works were also shown on the photographs. 16.Also attached to the LLT report was a copy of the approved Ground Floor Plan showing the Property. According to that floor plan, the building boundary line immediately outside the Property was smooth. 17.The LLT Report was written on the letterhead of LLT, which described them as “Engineers & Architects” and “Chartered Structural Engineers & Authorized Persons”. 18.By a letter of 6 December 2011, W&C notified EC of LLT’s findings. W&C said:-
19.EC replied by their letter dated 9 December 2011. Its effects may be summarised as follows:-
20.W&C replied on the same day of 9 December 2011. The Plaintiff counter-offered to postpone the completion date to 30March 2012 at a reduced price (of HK$10.7 million) on payment of further deposit of HK$1.2 million, and with the Defendant’s consent to split up the Property by assignments, sub Deed of Mutual Covenants and Deed Poll. No condition was attached to the removal of the Unauthorized Building Works. The counter-offer was said to be without prejudice to the Plaintiff’s right in raising further requisitions, its right to the outstanding requisitions and its right to rescind the Agreement. It was further said that “[The Plaintiff’s] counter-offer is open for acceptance until the close of business hours on 12 December 2011. If [the Plaintiff’s] counter-offer is not accepted, please return the deposit to us in amount of HK$1,200,000.00 within 3 working days.” 21.EC replied on 12 December 2011. It was said that the Defendant’s earlier offer had been rejected by the Plaintiff’s counter-offer, and that as the Plaintiff had already by W&C’s letter of 6 December 2011 unilaterally repudiated the Agreement, the Defendant reserved the right to accept the Plaintiff’s repudiation. But without prejudice to that stance, the Defendant made an alternative proposal of either having completion at the reduced price of HK$10.7 million on the original completion date or at the original price of HK$12 million on an extended completion date. The Plaintiff was requested to revert before the close of business on 13 December 2011. 22.By a letter to EC of 14 December 2011 (which was the scheduled completion date), W&C said that the follows:-
The Plaintiff then asked for refund of the Deposit within three working days. 23.By a letter of 22 December 2011 from EC to W&C, the Defendant claimed to accept the repudiation of the Agreement by the Plaintiff and to forfeit the Deposit. THE ISSUES 24.A large number of issues have been raised, a lot of them in the alternative. Wide ranging submissions have been made, a lot of them also in the alternative. I may be excused for not reciting all of them. In my view, the relevant issues are those analyzed below. Whether Requisition 16 a properly formulated requisition 25.Mr. Li submitted on behalf of the Defendant that Requisition 16 was not a proper requisition as it was too general. In support, he referred me to Hong Kong Conveyancing and Practice Vol. 1A paragraphs VI[332.2] to VI[332.5]. 26.The observations made by Deputy Judge To (as he then was) at paragraph 47 of Goldmex Ltd v. Edward Wong Finance Co Ltd [2006] 2 HKLRD 795 are relevant, that:-
27.In Essence Star Ltd v Mai Jianbo (1998) HCMP No. 299/98, Recorder Kwok had before him a requisition as to an alleged unauthorised structure. His reasons for not satisfying that it was sufficiently precise were as follows:-
28.I refer to the wording of Requisition 16. It made no reference to any plan, approved or otherwise. It was not supported by any expert report. It in fact did not even refer to any particular structure. In effect, it simply requested the Defendant to make a confession as to the existence of any illegal structure. In my view, it lacked the specificity and precision to qualify as a proper requisition. The Defendant was not obliged to answer it. 29.The main thrust of Ms Wong’s submission in this regard was this, that whether Requisition 16 was properly formulated had become irrelevant, because by answering it in unqualified terms on 8 November 2011, the Defendant had waived its right to challenge the propriety of that requisition. It was further submitted that had any objection been raised, the Plaintiff could have rectified the alleged defect. 30.I enquired with Ms Wong as to whether she had any authority in support of this submission of hers. She told me that she could not find any. She however sought to rely upon Goldmex in support of the proposition that lateness in raising requisitions can be waived, and that, in her submission, if lateness can be waived, other defects should also be capable of being waived. 31.In the absence of any authority in support, I do not accept Ms Wong’s submissions on this issue. A late but otherwise proper requisition is fundamentally different from a purported requisition which lacks the specificity and precision to be a proper requisition. While lateness can be waived, no waiver can change the nature of a purported requisition or to provide specificity and precision to a purported requisition which it otherwise lacks. 32.The fact that the Defendant had answered Requisition 16, while in my view could not cure the defects it had, may however be relevant to the following matters:-
33.The consideration of these other matters requires me to decide first of all whether W&C’s letter of 6 December 2011 (said by the Plaintiff to contain the LLT Requisition) in fact contained any properly formulated requisition. If it did not, those other matters fall away. It is to this issue I now turn. W&C’s letter of 6 December 2011 – whether contained any requisition, and whether repudiation 34.I turn to the contents of E&C’s letter of 6 December 2011. Two issues are involved: (1) whether W&C’s letter of 6 December 2011 contained any requisition, and (2) if not, whether the Plaintiff had in fact thereby rescinded the Agreement by evincing an intention no longer to be bound by the same. 35.Mr Li submitted that the Plaintiff did not raise any requisition in W&C’s letter of 6 December 2011, and the Plaintiff had in fact thereby repudiated the Agreement. 36.Ms Wong submitted that the letter in fact contained a requisition which was raised “in furtherance of” Requisition 16. She further, with reference to the opening words of that letter, namely “Without prejudice to our right in raising further requisitions and our right to the outstanding requisitions…”, submitted that the Plaintiff had not ‘unequivocally evinced an intention to treat the Agreement as at an end”. 37.I have considered the contents of that letter objectively and carefully. I note that immediately after the opening words reproduced above, W&C proceeded to refer to the contents of the LLT Report and said that “We found that your client had failed to answer our Requisition 16 and failed to prove a good title to the property. As such, your client cannot give a good title of the property to our client which constitutes a breach of the [Agreement].” W&C did not ask EC or the Defendant to address or clarify any title issues which the LLT Report might have raised. They simply stated their conclusions that the Defendant had failed to answer Requisition 16, failed to prove a good title, and could not give a good title. They then concluded by demanding return of the deposit paid within 3 days. That demand is in my view particularly important. It was not a warning. It was an immediate demand. The only legal basis upon which that demand could have been made was that the Agreement had come to an end. Otherwise, the Plaintiff simply had no entitlement to the return of any deposit. 38.Thus, having considered the contents of the letter as a whole, and despite the opening words, I form the view that no requisition was contained in W&C’s letter of 6 December 2011. Rather, the Plaintiff had thereby rescinded the Agreement by unequivocally evincing an intention to treat the Agreement as at an end or no longer to be bound by the same. However, at this stage, I have not reached any conclusion as to whether that rescission was wrongful. Whether Defendant failed to give title 39.I now consider Ms Wong’s primary case, which was that the Defendant had failed to give title. She elaborated it as follows: The Defendant’s duties as vendor included the duties to show and give title. The two duties were distinct. The issues as to whether Requisition 16 was a proper requisition, and as to whether W&C’s letter of 6 December 2011 contained any requisition, go only to the Defendant’s duty to show title. Even if both of those issues were to be answered in the negative, the Defendant remained under the duty to give title on the contractual completion date. The Defendant’s duty to give title survived any rescission on the part of the Plaintiff by W&C’s letter of 6 December 2011, because either the Plaintiff was entitled to rescind on 6 December 2011 as the title defects associated with the Unauthorized Building Works were irremovable (at least by the contractual completion date), or because the Agreement had been kept alive by the Defendant’s conduct subsequent to the rescission. On the contractual completion date, the Agreement remained binding upon both parties, and the Unauthorized Building Works had not been removed. It was therefore the Defendant who had breached the Agreement. 40.I consider each of the sub-issues in turn. The Defendant’s duty to give title 41.In the course of her submissions, Ms Wong helpfully took me through a number of authorities on the nature of the Defendant’s duties to show and give titles. A lot of them are not in dispute. But of particular relevance is Strong & Associates v Flywin Co. Ltd. [2002] 1 HKC 54, wherein Le Pichon JA observed, at p.60 F-G, that:-
42.In Profit World Trading Ltd v Ho So Yung [2011] 2 HKLRD 773, Le Pichon JA at p.779-780 made similar observations at paragraphs 21 and 23, that:-
43.The law in my view is clear. The Defendant’s duty to give title is independent of its duty to show and prove title. Even though, as I have found, Requisition 16 was not a proper requisition, and even though W&C’s letter of 6 December 2011 did not contain any requisition, and even if the Plaintiff had not raised the purported requisition at all, the Defendant, subject to what are to be considered below, remained obliged to give title to the Property on the contractual completion date. Whether Defendant’s duty to give title survived the rescission by the Plaintiff 44.If the rescission by the Plaintiff on 6 December 2011 had been wrongful and had been accepted by the Defendant, the Defendant would have been from the time of the acceptance relieved from further performance of its duties under the Agreement. In other words, the Defendant would have been discharged from the duty to give title. 45.Ms Wong countered that by submitting that the Defendant was not so discharged. The reasons, in her submission, were either that the Plaintiff was entitled to rescind on 6 December 2011 as the title defects associated with the Unauthorized Building Works were irremovable (at least irremovable by the contractual completion date), or because the Agreement had been kept alive by the Defendant’s conduct subsequent to the rescission. 46.I consider the first reason given by Ms Wong first. In Peyman v Lanjani [1985] Ch. 457, Slade L.J. stated, at pages 496-497, that:-
47.Peyman v Lanjani was followed, albeit obiter, by Barnett J in Lucky Health International Enterprise Ltd v. Chi Kit Co Ltd [1998] 4 HKC 656. At page 671, his Lordship observed that:-
48.The first reason put forward by Ms Wong is in my view correct in law. Whether it is in fact valid is however facts sensitive, and is dependent upon whether the title problems associated with the Unauthorized Building Works were irremovable. I will come back to this issue at the latter part of this judgment after I have considered the question of “substantial performance”. 49.In respect of the second reason put forward by Ms Wong, I am of the view that it is a valid one. EC had never expressly accepted the Plaintiff’s rescission until its letter of 22 December 2011. In EC’s letter of 9 December 2011 (in reply to W&C’s letter of 6 December 2011), no acceptance was communicated. Rather, the Defendant made an offer to remove the Unauthorized Building Works and to complete at a reduced price. It was indeed Mr Li’s own case that the Defendant had only reserved its right to accept the Plaintiff’s rescission, and had not actually accepted it until 22 December 2011. 50.As held by Yuen J (as she then was) in First Shanghai Enterprises Ltd. V Dahlia Properties Pte Ltd [2001] 3 HKC 443 at 455I:-
51.Thus, as the Agreement had been kept alive, the Defendant, subject to what are to be discussed below, remained under the duty to give title. 52.I have considered Ip Cho Sau v Leung Kai Cheong HCMP 1288 of 1998 which Mr Li referred me to. In that case, the plaintiffs/purchasers complained to the vendors about the existence of certain illegal structures. But instead of raising a requisition, they announced that they did not intend to perform the agreement and repudiated it. They further failed to pay certain further deposits which they were contractually bound to do. At paragraph 20 of the judgment, Deputy Judge Woolley observed that:-
That conclusion however has to be considered in the context of the facts of that case. After the purchasers’ repudiation, and after some negotiations between the parties, the vendors ultimately expressly accepted the repudiation, and they did so nearly a month before the contractual completion date. That having been the case, the venders were no doubt relieved of any further duties to rectify the problem or to give title on the completion date. That was however not what had happened in our present case. Whether failure to give title – The parties’ submissions 53.As it turned out, the Unauthorized Building Works were not removed by the contractual completion date. Has the Defendant therefore failed to give title? 54.Ms Wong on behalf of the Plaintiff submitted yes. 55.The submissions made by Mr Li in reply were quite complicated. He relied upon the doctrine of “substantial performance”. His basis premise was that good title can be given by substantial performance. Whilst the Unauthorized Building Works had not been removed by the contractual completion date, he relied upon the offer contained in EC’s letter of 9 December 2011. He submitted that as “substantial performance” is an equitable remedy, the conduct of the parties would therefore have to be looked at. He submitted further that the offer made by the Defendant was a reasonable one, which the Plaintiff had failed to accept. By not accepting the offer, it became not a pre-requisite for the Defendant to remove the Unauthorized Building Works before the Defendant could invoke “substantial performance” as the basis to justify the Defendant’s stance that it was the Plaintiff which had been in breach. In particular, it was said that by failing to accept the offer, and by maintaining the position first evinced in W&C’s letter of 6 December 2011, the Plaintiff had evinced an intention not to perform the Agreement, and that that was sufficient to support the proposition that it was the Plaintiff who was in breach of the Agreement. Substantial performance – the law 56.Two legal issues are involved, being (1) whether the doctrine of substantial performance is applicable to a claim for forfeiture of deposit when the underlying agreement has been terminated, and (2) what the test is in deciding whether substantial performance has been tendered. 57.In relation to the first issue, Ms Wong submitted that the doctrine of substantial performance was not applicable to the present case because the Defendant had by its letter of 22 December 2011 sought to terminate the Agreement and that it is now seeking forfeiture of deposit. She referred me to G.C. Kirby & Sons (a firm) v Sharman (1990) unrep., 19.11.1990 CA (LexisNexis Transcript) and Chitty on Contract (31st edition) paragraphs [27-054] to [27-055]. She relied heavily upon the obiter observations made by Lam J (as he then was) in Cashew Holdings Ltd v Pacific Success Enterprise Ltd [2004] 2 HKC 594, that:-
58.I find it difficult conceptually to divorce the concept of substantial performance from the nature of the title which a vendor has to give, or to make the applicability of the doctrine of substantial performance conditional upon the forms of relief sought. As held by Yuen J (as she then was) in Goldful Way Development Ltd v. Wellstable Development Ltd [1998] 4 HKC (686A-E):-
59.In Goldful Way, the unauthorised structure concerned was a greenhouse covering about 3.93% of the total floor area of the property in question. The issue was whether its existence would lead to the vendor being unable to complete the sale for want of good title. The parties by consent kept the agreement alive and extended the completion date until 5 days after the delivery of the judgment. Yuen J, having applied the test of whether the vendor was able to convey substantially what he had contracted to sell (thus in effect invoking the doctrine of substantial performance), and on the facts, held that the vendor could demolish the greenhouse prior to completion and still be in the position to complete by substantially performing the agreement. Good title could be given. There was no breach on the part of the vendor. But suppose the facts were slightly different in the following ways: the vendor had decided to demolish the greenhouse which he in fact did before the original completion date. The purchaser however found that objectionable on the basis that he did not get what he thought he bargained for and refused to complete. The vendor then forfeited the deposit. The purchaser took him to court. When before the Court on this slightly different set of facts, the issue would still be the same (whether the vendor had given or would have been able to good title), the test to be applied would be the same (whether the vendor was able to convey substantially (albeit not all of) what he has contracted to sell), and the answer should be the same (namely he was able to give good title). The vendor committed no breach. It was the purchaser who did. Why should the vendor then not be able to keep the forfeited deposit merely because the purchaser had taken what turned out to be a wrongful move which led to the termination of the agreement? I see no legal or logical reason for that. 60.In my view, the concern that Lam J (as he then was) expressed in Cashew Holdings may better be addressed by the application rather than the applicability of the doctrine of substantial performance. That was indeed what Yuen J has alluded to in Goldful Way at p.686 E-H when she warned that every case will have to depend on its own fact:-
61.Further, Ms Wong has not referred me to any cases since Cashew (decided in 2004) which has made the applicability of the doctrine of substantial performance conditional upon the types of relief sought or whether the underlying agreement is still on foot. On the contrary, I note that as recent as 2011, the Court of Appeal in Profit World Trading Ltd v. Ho So Yung [2011] 2 HKLRD 774 proceeded on the basis that the doctrine of substantial performance was applicable even though the underlying contract in that case had been terminated. 62.I am therefore of the view that the doctrine of substantial performance is applicable to the present proceedings even though the Agreement has been terminated, and even though the Defendant is seeking forfeiture of the deposit paid. 63.I turn next to the test to be applied in deciding whether substantial performance has been tendered. The test has both subjective and objective elements. In Goldful Way, Yuen J (as she then was) held at 686I to 687C that:-
64.In Chan Man Choi v Poon Fook Wah [2001] 3 HKC 493, Woo JA at 511E to 512B accepted as correct the approach submitted by counsel:-
65.In Leung Wing Fai v. Onlink Investments Ltd [2000] 1 HKLRD 725, Yuen J (as she then was) summarised the relevant considerations at 731 as follows:-
66.When approaching the issue of substantial performance, I will adopt the approach as discussed above. Substantial performance – whether substantial performance by the Defendant 67.In respect of the objective elements of the test, I have referred to the contents of the LLT Report. I have also summarised the effects of the Ground Floor Part Plan attached thereto. I have also compared that plan with the assignment plan produced by Mr Tsang (page 87 of the Bundle). I note that on the assignment plan, the building boundary line of the Property was smooth. There were no extensions or protrusions as drawn on the Ground Floor Part Plan. 68.Mr Li has made some comments on the LLT Report. First, he commented that its author was apparently only a Chartered Structural Engineer. But as I have said above, the LLT Report was written on the letterhead of LLT, which described them as “Engineers & Architects” and “Chartered Structural Engineers & Authorized Persons”. They were also described by Mr Tsang as “a firm of engineers and architects.” The available evidence suggests that they were qualified to give the opinion in their report. 69.Mr Li further commented that although the words “encroached” was used in the LLT Report, there was no evidence as to the exact boundary line of the Property, and as a result one simply could not just take from the LLT Report that the extended shop fronts had trespassed onto common or public area. 70.I have considered those submissions. I have also considered the totality of the LLT Report, including in particular the Ground Floor Part Plan attached thereto. Their combined effects were clear. The Unauthorized Building Works were additions and alterations. They were different from what were shown on the approved plan. The extended shop fronts were described as having encroached onto public area. The projected signage was also described as unauthorised. No contrary evidence has been adduced by the Defendant. I in the circumstances accept and place weight upon the LLT Report. In particular, I accept LLT’s opinion that the extended shop fronts on the Boundary Street side and the scavenging lane side encroached upon the public footpath and the scavenging lane respectively. 71.The fact that the extended shop fronts encroached upon the public footpath and scavenging lane is an important one. On the evidence, the Defendant could have no title to give in respect of those parts. I refer to the analysis of Lam J (as he then was) in Cashew Holdings in respect of the distinction from a legal point of view between an illegal structure within the boundaries of the property and one encroached upon common area or land of the others. 72.According to Mr. Tsang’s evidence and a letter of 29 February 2012 from LLT, the net area of the Property was approximately 59.358m2. The total area of the extended shop fronts was 5.9318m2(4.0068 m2 on the Boundary Street front and 1.925m2 on the scavenging lane front), which represented about 10% of the net floor area. 73.Turning to the subjective matters, I have considered Mr Tsang’s evidence. He said that the Plaintiff entered into the Agreement knowingly with the benefit of sitting tenancies and would have been “happy to earn the yield by way of rental income.” He said he was impressed by the signage which would be an attraction to potential tenants and would enhance the rental value of the Property. He said further that “[a]part from the signage, the extended shop area which was found to have encroached upon the scavenging lane is also an important feature of the Property.” When he inspected the Property, it was partitioned into two portions, one bigger and one smaller. The extended shop front on the scavenging lane was enjoyed by the smaller portion. Without the extended shop fronts, and in particular, without the extended shop front on the scavenging lane side, the smaller portion would be even smaller. He said that “without the Unauthorized Building Works, there was not much point for the Plaintiff to purchase the Property since in that case not only the Property’s yield by way of rental income would be much lower, the Property would be less attractive to potential tenants.” 74.Although Mr Tsang’s evidence was not tested by cross-examination, I still have to consider whether his subjective views were reasonably held in the light of all the evidence. In respect of the signage, he might genuinely have been impressed by them. I have no basis to doubt that. But in my judgment, his view on the effect of the removal of the signage upon the marketability of the Property was exaggerated. As pointed out by EC in their letter of 9 December 2011, which I accept, the signage, even if removed, could always be re-erected upon application to the relevant authorities. At least similar ones could be re-erected. 75.I am however more concerned about the extended shop fronts. I find that they formed part of the Property agreed to be sold. That is the effect of Mr Tsang’s evidence. That is also consistent with the contemporaneous conduct of the parties. The extended shop fronts together represented about 10% of the net floor area. Without them, the Property, and in particular the smaller portion thereof, would be appreciably smaller. In the absence of any cross-examination and specific challenge, there is no basis for me not to accept Mr Tsang’s evidence that the extended shop fronts were important features of the Property. 76.It is against the above matters that I consider whether the Defendant did tender or could have tendered substantial performance. 77.Ms Wong submitted that the burden of proving substantial performance was on the Defendant. She cited Grandco (Holdings) Ltd v Harbour Wealth Co Ltd., HCA 3388/1998. I agree. 78.The Defendant had not actually removed the Unauthorized Building Works by the contractual completion date. It relied on its offer to do so. I repeat Mr Li’s submissions made to me which I have summarised in paragraph 55 above. I have considered them. 79.In my judgment, even if the Defendant had removed the Unauthorized Building Works by the contractual completion date, and even taking into account the reduced price, it still would not have been able to give good title. The Property would have been a substantially different one both objectively and from Mr. Tsang’s subjective perspective. The Defendant could not have substantially performed the Agreement. I repeat my findings and considerations set out in paragraph 75 above. 80.Having so found, and on the basis of my findings, I cannot accept that the refusal on the Plaintiff’s part to accept the Defendant’s offer amounted to any repudiation, as Mr Li submitted to me. 81.Mr Li relied on Victory Star Ltd v. Ng Fung Ying [2003] 4 HKC 677 and submitted that the Plaintiff’s counter-offer gave rise to some sort of estoppel so that it should not be allowed to rely on the Unauthorised Building Works to rescind the Agreement. 82.Victory Star involved a very different set of facts. There, the vendors, having received a requisition concerning certain unauthorised structures on the property which they had agreed to sell, informed the purchaser that they were going to demolish them before completion. The purchaser did not respond. The vendor then informed the purchaser that the demolition work would be carried out unless the purchaser stated otherwise within the next seven days. The purchaser again did not respond and the work was completed. Subsequently, the purchaser purported to rescind the agreement on the basis that it was an implied term of the sale and purchase agreement that the property was to be sold on an “as is” basis, and there had been a substantial variation of the property agreed to be sold. On the purchaser’s application for summary judgment, the vendors were granted unconditional leave to defend on the ground that there was a highly arguable defence of estoppel by way of the purchaser’s silence. The purchaser appealed. On appeal, the Court of Appeal held that there was an arguable case that the purchaser had been under a legal duty to respond, and that:-
83.In the present case, the Defendant’s offer was first made on 9 December. The Plaintiff made a counter-offer on the same day. The Defendant’s original offer was rejected thereby. The Defendant itself said so in its letter of 12 December. In that letter, the Defendant in turn made its counter-proposal (of either having completion at the reduced price of HK$10.7 million on the original completion date or at the original price of HK$12 million on an extended completion date), thus rejecting the Plaintiff’s counter-offer. The Defendant imposed a deadline of 13 December for the Plaintiff to answer. It is true that the Plaintiff did not expressly respond to that letter. But on the day immediately after the deadline imposed, the Plaintiff issued the letter of 14 December terminating the Agreement. Given such facts, I do not find any conduct on the Plaintiff’s part which could be construed as any estoppel so that it should not be allowed to rely on the Unauthorised Building Works to rescind the Agreement. 84.In Victory Star, Cheung JA observed that:-
85.Mr Li has repeatedly commented that the Plaintiff was a speculator and that it raised the issue of the Unauthorized Building Works as an excuse to get out of the Agreement. He pointed to the Plaintiff’s request for extension, and the fact that the counter-offer it made on 9 December 2011 contained no term about the removal of the Unauthorized Building Works. 86.I have considered those submissions and the related evidence. Mr Tsang in his affirmations has denied that the Plaintiff raised the issue of the Unauthorized Building Works to get out of the Agreement (paragraph 13 of his first affirmation). I refer further to his evidence recited in paragraph 13 above in relation to the circumstances leading to the preparation of the LLT Report. I have no reason not to accept his evidence. I note in this regard also the Defendant’s case (as is apparent from its answer to Requisition 16) that even the Defendant was not aware of the Unauthorized Building Works until the LLT Report. 87.In the end, and having analysed the facts and evidence as above, my views are:-
88.I also rule that the Agreement had been brought to an end by the Plaintiff’s letter of 14 December 2011. The third paragraph thereof made the Plaintiff’s position clear, that “Our client is neither ready nor willing nor able to purchase a property with substantial Unauthorized Building Works while you have not been able to give good title of the Property to our client.” The breach by the Defendant was thereby accepted. 89.I now come back (though strictly speaking not necessary in the light of my reasoning above) to the issue left open in paragraph 48 above as to whether the title problems associated with the Unauthorized Building Works were irremovable. If necessary I would rule that the title problems were irremovable. I repeat my views set out immediately above. With the Unauthorised Building Works as they were on the completion date, the Defendant had no title to give in respect of those parts of the Property. Even if they had been removed, the Defendant still would not have been able to substantially perform the Agreement. CONCLUSIONS ON THE CLAIM AND COUNTERCLAIM 90.By reason of the above, I allow the Plaintiff’s claim on the basis that the Defendant has failed to give title to the Property. I accordingly dismiss the Defendant’s counterclaim. LOSS AND DAMAGE 91.In the light of my judgment, the Plaintiff is entitled to have its deposit in the total sum of HK$1,200,000 back. 92.The issue of loss of bargain does not arise as the joint surveyor’s evidence shows a drop in price. 93.In his first affirmation, Mr Tsang sought various costs and expenses, in the total sum of HK$170,000. In the affirmation filed on behalf of the Defendant, those claims were criticised as mere assertions, as no documentary proof of those costs had been produced. Despite such specific challenge, Mr. Tsang in his second affirmation was only able to produce a bill from W&C for HK$20,000 and a debit note from LLT for HK$15,000. That is the extent of the Plaintiff’s claim for expenses which I am prepared to allow. ORDER 94.I make the following Orders:-
Ms Emma Wong, instructed by Wong & Co, for the plaintiff Mr C Y Li SC, instructed by Edmund W H Chow & Co, for the defendant | |||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case