Accurate Contractors & Renovators Co v. The Incorporated Owners of Beverley Heights
|
CACV 280/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO 280 OF 2012 (ON APPEAL FROM HCA 2482/2006) ____________
____________
___________________________________ REASONS FOR JUDGMENT ___________________________________ Hon Cheung JA: 1.I agree with the Reasons for Judgment of Au-Yeung J. Hon Yuen JA: 2.I agree with the Reasons for Judgment of Au-Yeung J. Hon Au-Yeung J: 3.This is an appeal by the plaintiff against To J’s judgment dismissing its claim in part for a sum outstanding for building renovation works under what was known as “Item 17” of the renovation contract. At the conclusion of this hearing, we dismissed the appeal with costs. Here are the reasons. The background 4.The facts as found by trial judge that are relevant to this appeal are as follows. The plaintiff was a registered general building contractor who had done renovation works for the defendant (“the Incorporated Owners”) in respect of a building known as Beverley Heights. There are 48 units in that building. The appellant has done common works under Item 17 of the contract which it said amounted to $722,800. It applied to the Architect for payment of $417,580 under Item 17 (“the appellant’s application”) and the Incorporated Owners had paid the same. In the Statement of Claim, the appellant claimed for, amongst others, the balance amount of $355,220[1] for Item 17 works. 5.To J found that the final quotation accepted by the Incorporated Owners for Item 17 (“the final quotation”) consisted of 3 tables which clearly identified the common works items and the private works items. The parts concerning common works were as follows:
6.Subsequently, the parties agreed that the unit owners were only allowed to opt for Item 17.3 plus either Item 17.1 or 17.2. Thus the total price for Item 17 was $772,800. These were common works items to be paid by the Incorporated Owners. The private works items were to be paid by individual unit owners who were free to engage the plaintiff or their own contractors (paragraph 14 of To J’s judgment). 7.The cost of sanitary fittings, such as bath tubs and basins, would be provided by the individual unit owners. 8.To J then found as follows:
9.Upon that ruling, To J held that the appellant was entitled to be paid $417,580, the amount which it applied for from the Architect and was fully paid. The appellant has failed to show that it has executed works in other units apart from those stated in the appellant’s application. Accordingly, its claim under this head was dismissed (paragraphs 28 and 30 of the judgment). Issues on appeal 10.The appellant does not seek to overturn the factual findings. The only issue on appeal is whether, on a proper interpretation of paragraphs 22, 26 and 30 of the judgment, the plaintiff was entitled to be paid more than $417,580 for Item 17 works. 11.In the Amended Grounds of Appeal, the appellant contends that it was entitled to $16,100 for each unit if it had actually executed some works, however minimal, in one unit. 12.The appellant further relies on the finding that it was entitled to be paid $417,580 to contend that that sum was not based on lump sum rate per unit basis but the re-measurement concept, ie actual work done (“the alternative contention”). It was arrived at by:
The appellant contends that in accepting the plaintiff’s application for the sum of $417,580, To J must have accepted that the various sub-items adding up to that sum formed part of the Item 17 works. 13.In the course of the arguments, Mr Chung, counsel for the appellant, withdrew that part of his case based on execution of sub-items (v) to (viii). That withdrawal was rightly made as those sub-items simply did not form part of Item 17. Upon that withdrawal, Mr Chung rests his case on having done works for 33 instead of all 48 units. The appellant therefore claims a sum of $531,300, ie $16,100 x 33 units. After deduction of the $417,580 already received, the appellant seeks $113,720. Analyses 14.In coming to his decision that Item 17 was not a lump sum item, To J had analyzed the background which gave rise to the final quotation, the complications which had developed among the owners, the contract terms, a letter of the IO’s representative and minutes of a meeting on 3 May 2005. 15.The initial quotation was in the form of a figure for $75,500 per unit, subsequently reduced to $53,000 (paragraph 12 of the judgment). It was at the invitation of the Architect and the Incorporated Owners that the appellant came up with a breakdown of Item 17 in the 3 tables. That breakdown was clearly not on the basis of $16,100 per unit but was further broken down. 16.Complications arose when some unit owners wished to engage their own contractors to execute the private works and even part of the common works in their units at their own costs. In fact a substantial number of owners declined to allow the appellant to execute Item 17 works inside their units at all (paragraphs 16 and 18 of the judgment). 17.To J also referred to clause 1 of the Contract which stipulated that the Incorporated Owners may by notice issued before specified dates to the appellant require it to execute the optional works. The unit rate and/or the total price for those works shall be in accordance with those stated in the quotation (paragraph 17 of the judgment). 18.To J then referred to a letter dated 23 November 2004 from the Incorporated Owners to the appellant. He considered that when Mr Cheng (the secretary and representative of the Incorporated Owners) used the caption “lump sum per unit”, Mr Cheng could not have meant anything but the total price for that item of works for one unit. There, in referring to the rates, Mr Cheng put in parenthesis, “ie lump sum for each of the units concerned”. To J took the view that Mr Cheng was not talking about a lump sum contract, but the total price of the various sub‑items under Item 17 for one unit. The term “unit rate” 單價 meant the price of works for each unit (paragraph 22 of the judgment). To J said:
19.At a weekly meeting among the representatives of the appellant, the Incorporated Owners, the Architect and the building manager held on 3 March 2005 the parties agreed to adopt the “buffet” concept in calculating payment. It was minuted (paragraph 24 of the judgment). To J explained the proper understanding of the minutes in paragraph 26 of his judgment. He gave the example of the appellant removing an old sanitary fitting but the individual unit owner waiving his right to have the new fitting installed by the appellant. The Incorporated Owners would pay for the whole item. It was on the basis of the minutes that he accepted Mr Cheng’s evidence. 20.At this hearing, Mr Lin, counsel for the Incorporated Owners, draws our attention to the evidence of Mr Cheng in this respect in paragraph 15 of his witness statement [B271-272]. There Mr Cheng explained the computation of the $417,580 which (i) was based on the number of units for which work was done and the unit price under items 17.1A0, 17.1B0, 17.3A0 and 17.3B0 respectively; (ii) included an additional sum allowed to the appellant for what were known as preliminaries; and (iii) included an additional sum in settlement. 21.Further, in paragraph 11 of Mr Cheng’s 2nd witness statement [B305], it was stated that:
22.Considering all these findings and on a proper interpretation of the judgment, an individual owner was at liberty to select the item of common works which he wanted the appellant to do. If the appellant had done part (however minimal) of one item of common works, the full price per unit for that item (eg 17.1A0 or 17.2A0 or 17.3A0 as the case may be) would be paid to it. Mr Chung’s contention that the plaintiff should be entitled to $16,100 per unit must be rejected. 23.The alternative contention can be disposed of easily. Firstly, it has never been pleaded as the appellant’s pleaded case all along was that Item 17 was for a lump sum. It is not permissible for unpleaded issues to be raised out of the evidence: Kwok Chin Wing v 21 Holdings Ltd, FACV No. 9 of 2012, 30 September 2013, at paragraph 21. 24.Secondly, the appellant’s computation of the sum of $417,580 was based on unit rates (eg of $1,400 for demolition of sanitary unit, $800 for re-installing the same) not found in the final quotation. Mr Chung concedes that there was no contractual basis for the unit rates claimed for sub-items (i) to (iv). 25.Thirdly, when seeking payment from the Architect, the appellant has not reserved its position to claim for more than $417,580 in the appellant’s application. 26.On a proper interpretation of To J’s judgment and based on paragraph 28 of his findings as to the extent of work done, the correct amount which the appellant could recover from the Incorporated Owners should be:
27.The appellant has in fact been paid more than it was entitled to under To J’s judgment. Conclusion and costs 28.This appeal was dismissed. 29.Although the Incorporated Owners sought costs on an indemnity basis, this appeal did involve the proper interpretation of To J’s judgment. An order for costs on party-and-party basis was considered appropriate. 30.I thank counsel for their assistance.
Mr Jerry Chung, instructed by Wong & Lawyers, for the plaintiff/appellant Mr Kenny CP Lin, instructed by Y.C. Lee, Pang, Kwok & Ip, for the defendant/respondent | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||