Dawn Jade Ltd and Another v. Himanshu Girdhar Dua
Read the full judgment text of HCA 581/2012 on BabelCite. This High Court CFI judgment was delivered on 10 December 2013.
1. This is the defendant’s appeal against the master’s order dated 29 August 2013. The order dismissed the defendant’s application to set aside the final judgment entered on 10 July 2012 in default of notice of intention to defend.
Cited by 2 cases
|
HCA 581/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE HIGH COURT ACTION NO 581 OF 2012 ____________
____________
______________ D E C I S I O N ______________ INTRODUCTION 1.This is the defendant’s appeal against the master’s order dated 29 August 2013. The order dismissed the defendant’s application to set aside the final judgment entered on 10 July 2012 in default of notice of intention to defend. 2.This action was commenced in April 2012. The plaintiffs, investment companies incorporated in BVI but having a place of business here, sued the defendant for the refund of deposits earlier paid pursuant to two company share sale and purchase agreements (both in January 2011) (collectively “the Jan 2011 agreements”); the two companies were:
BACKGROUND 3.The background below appears to be undisputed. 4.The plaintiff are companies related to The Maxdo Group Ltd which has offices in Hong Kong and the Mainland (“Maxdo”). Maxdo’s business is financial and/or industrial and/or agricultural and/or forestry investments, resources development, in China and Asia. 5.Through Maxdo’s business dealings with a Phoenix Lumber SA (of which the defendant is a director and shareholder), the defendant became known to the plaintiffs since late 2009 (those dealings were related to investment in land and forestry rights in Nicaragua). 6.In around end of 2010, the defendant offered to sell to Maxdo his (and other shareholders’) interests (described as “exclusive rights” in the defendant’s skeleton argument) in Greenair and Dua Forestal. The former was said to operate a “reduced emissions from deforestation and degradation project” (or REDD project) and the latter was said to be holding interests in a forestry logging project. Both projects were in Bolivia. 7.The total monetary consideration payable by the plaintiff pursuant to the Jan 2011 agreements was US$16 million (US$7 million + 9 million). Deposits which totaled US$1 million were paid to the defendant by early February 2011 (these become the subject-matter of this action). THIS APPEAL (a) Service of process and time of setting aside application 8.As stated above:
9.The defendant contended before the master the default judgment was irregularly entered. This is sensibly (and correctly) no longer pursued in this appeal (para 3, defendant’s skeleton argument). 10.Arguments have, however, been put forth by the defence regarding the reasonableness of its conduct in relation to this action. These will be discussed below. (b) Merits of proposed defence 11.In gist, the proposed defence is:
12.Before embarking on a discussion of the proposed defence (summarized above), it should be noted:
13.The relevant part of condition 3.1 of the Jan 2011 agreements provided:
14.Thus, on the defendant’s admission, but for the proposed defence summarized in para 11 above, clause 3.4(i) has already become operative. 15.I agree with the plaintiffs that neither of the matters set out in para 11(a) and (b) above can be a defence with reasonable prospect of success. 16.In relation to the matter set out in para 11(a) above (plaintiffs’ alleged breach of contract), the defendant’s complaint is:
17.It would appear such conduct would amount to the “economic torts” of:
18.But, as the plaintiffs correctly argue, it cannot be put forth as the repudiation of some unspecified term(s) of the Jan 2011 agreements. Less still can it ground a right to forfeit the deposits pursuant to clause 3.4(ii) thereof (which, as has expressly been stated therein, was only exercisable upon the breach of condition 3.1(b)). In this connection, condition 3.1(b), Jan 2011 agreements was concerned with the plaintiffs being satisfied with the defendant’s land and property titles (Greenair agreement) or forestry inventory count (Dua Forestal agreement). 19.Insofar as it may be necessary to observe (in relation to para 17 above, for example), there is no general principle of “good faith and fair dealing” in contract law in the performance of a contract: Chitty on Contracts (2012) 31st Ed, Vol 1, para 1-039 to 1-041. 20.Similar considerations are applicable to the defendant’s allegation that the plaintiffs have breached the confidentiality provision of the Jan 2011 agreements (clause 11.1 thereof). 21.The defendant also relies on the following authorities for the proposition that deposits paid pursuant to contracts can be forfeited upon breach without the need for a contractual provision for forfeiture:
22.The plaintiffs disagree, and point out that none of the above authorities supports the defendant’s above legal proposition. In Soper:
The Samarenko case was about the purchaser’s failure to pay the deposit (where there was an express term requiring such deposit), despite the lapse of a reasonable time period after the demand for its payment, being held as an act of repudiation of the contract (forfeiture of the deposit was not an issue therein). 23.In relation to the defendant’s complaint that the plaintiffs have breached condition 3.1(b), Jan 2011 agreements, and therefore the right to forfeit by the defendant (pursuant to clause 3.4(ii) thereof) should take precedent over the plaintiff’s right to a refund (pursuant to clause 3.4(i) thereof), I also agree with the plaintiffs’ contentions set out below. 24.To construe clause 3.4(ii), Jan 2011 agreements to take precedence over clause 3.4(i) would lead to a commercially absurd and unreasonable result. It would mean that the defendant could retain the deposits when various conditions had been breached, provided one of them fell within condition 3.1(b) (as the defendant has in effect asserted in this appeal). 25.The language of clause 3.4(i) also militates against such a construction (see para 13 above). The part of that clause which reads:
26.The defendant also mentioned, in his verbal reply submissions, an anticipatory breach which was repudiatory in nature. It is noted, however, the defendant’s case is that the alleged breach only came to his attention in late-2011: para 9 and 28 to 29, defendant’s skeleton argument. 27.In relation to the matter set out in para 11(b) above (estoppel/variation of contract), as the plaintiffs argue:
CONCLUSION 28.By reason of the above matters, this appeal is dismissed. OTHER MATTERS 29.I also disagree with the defendant that its post-writ conduct was reasonable. 30.His (and his solicitors’) view that the service of the writ has not been validly effected is unreasonable. It ignores the express language of clause 13.3(a), Jan 2011 agreements which states:
There is no dispute the relevant court documents have been delivered to the address stated in clause 13.3(a) (the address of a law firm where the process agent worked). 31.What makes the matter worse for the defendant is that, about 2 weeks or so after such service, the defendant’s solicitors informed the plaintiffs’ solicitors the writ had been brought to the defendant’s attention. It follows that the defendant’s subsequent conduct cannot be regarded as reasonable either. 32.It is unclear whether, and if so for what purpose, the defendant still relies on an alleged failure on the plaintiffs’ part to fully and frankly disclose his possible defence in the relevant court documents. Insofar as he may do so, I agree with the plaintiffs that the point is misconceived (para 17 to 21, plaintiffs’ skeleton submissions will not be set out herein). 33.The parties’ closing submissions also mentioned various other points. These have not been expressly set out or dealt with in the above headings and sub-headings. This is so only because of the need to balance between the length of the decision and its comprehension. It does not mean those other points are thought to be irrelevant (or have been overlooked). To avoid doubt, those other points have also been considered. COSTS ORDER 34.The usual rule that costs should follow the event is accepted by the parties. There will accordingly be a costs order that the costs of this appeal be paid by the defendant to the plaintiffs. 35.The parties do not dispute, and I agree, that the hearing of this appeal was suitable for attendance by two counsel. It is thus so certified. 36.I consider summary assessment of costs to be appropriate. The above costs shall thus be so assessed. For this purpose:
Mr Anderson Chow, SC leading Mr Jonathan Wong, instructed by Reed Smith Richards Butler, for the 1st and 2nd plaintiffs Mr Ashley Burns, SC leading Ms Bianca Yu, instructed by Baker & McKenzie, for the defendant Please refer to CACV4/2014 for the relevant appeal(s) to the Court of Appeal. | ||||||||||||||||||||||