Crestdream Ltd v. Potter Interior Design Ltd
Read the full judgment text of HCCT 32/2013 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 24 July 2014 before Master S Lo.
Construction contract dispute — plaintiff CRESTDREAM LIMITED retained defendant POTTER INTERIOR DESIGN LIMITED to carry out fitting-out works for a fixed sum HK$3.3 million with specified completion dates; delay and repudiation arose when defendant abandoned works; plaintiff instructed quantity surveyor and third-party contractors to assess works and complete reinstatement ordered by Buildings Department due to unauthorized structural alterations. Core legal issues addressed included: (1) recoverability of damages for cost of reinstatement commissioned by plaintiff after defendant's abandonment, which was allowed based on established principles and expert report; (2) entitlement to liquidated damages accruing post-contract termination, decided in favour of plaintiff relying on construction contract authorities and reasoning against absolving defendant of delay liability upon termination; (3) validity of liquidated damages clause as genuine pre-estimate rather than penalty, accepted following authorities and contract formula analysis. The court assessed damages totaling HK$2,904,588 inclusive of cost of reinstatement, overpaid amount, and liquidated damages for delay; interest was awarded; and costs were summarily assessed at HK$230,000 to plaintiff subject to order nisi. Defendant did not appear at assessment hearing.
Legal issues: Recoverability of damages for cost of reinstatement work by a third party · Claim for liquidated damages after termination of contract · Validity of liquidated damages clause as genuine pre-estimate of loss
Outcome: Damages awarded to plaintiff totalling HK$2,904,588 with interest; costs awarded to plaintiff summarily assessed at HK$230,000 subject to order nisi.
Cites 1 case
|
HCCT 32/2013 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 32 OF 2013 _________________________ BETWEEN
_________________________
__________________________ ASSESSMENT OF DAMAGES __________________________ INTRODUCTION 1.This is an assessment of damages hearing pursuant to the interlocutory judgment dated 17 October 2013 entered in favour of the plaintiff. 2.By the Order dated 7 March 2014, Master K Lo ordered inter alia that: -
3.The Notice of Appointment of Assessment of Damages was filed and served on the defendant on 21 March 2014. The Assessment of Damages hearing was fixed before me on 14 July 2014. 4.By the letter dated 21 March 2014 by post, the plaintiff’s solicitors wrote to the defendant to inform them of the hearing. But the defendant failed to file any documents or turn up at the hearing on 14 July 2014. BACKGROUND 5.At all material times, the plaintiff was and is the registered owner of a residential flat at 15th Floor, No 24 Fontana Gardens, Hong Kong (also known as 15th Floor, Block A, No 24 Fontana Gardens, Hong Kong) (“Premises”). 6.At all material times, the defendant was and is a limited company incorporated in Hong Kong and carrying on the business as an interior design contractor. 7.By a written contract in simplified Chinese dated 7 September 2012 made between the plaintiff and the defendant, the defendant agreed to carry out and complete the fitting-out and building works of the Premises (“Works”) and the Plaintiff agreed to pay a fixed contract sum of HK$3,300,000 in accordance with the said written contract (“Contract”). 8.The Contract contains inter alia the following express terms: -
9.On or about 7 September 2012, the parties orally agreed to vary the project commencement date to 17 September 2012 (“Revised Project Commencement Date”) and project completion date to 19 July 2013 (“Revised Project Completion Date”). 10.On 17 September 2012, the defendant took possession of the Premises and commenced the Works. 11.Pursuant to Clause 5(2) of the Contract, between 12September 2012 and 1 February 2013, the plaintiff made various payments to the defendant in the total sum of HK$2,701,305. 12.On or about 5 March 2013, without the plaintiff’s approval, the defendant abandoned the Works and left the Premises. Reinstatement Work ordered by BD 13.In about early January 2013, the defendant drilled certain holes in the structural beam and wall in the Premises without advising the plaintiff that prior approval of the Buildings Department (“BD”) was required. 14.On or about 8 March 2013, representatives from the BD inspected the Premises. 15.In about mid-March 2013, the plaintiff received a letter dated 5 March 2013 from the defendant who indicated that they would suspend the Works at the Premises until the plaintiff obtained the BD’s approval of certain building works. 16.On or about 27 March 2013, the plaintiff received a letter dated 26 March 2013 issued by the BD (“BD Notice”) stating that unauthorised building works were found inside the Premises. According to the BD Notice, the plaintiff was required to reinstate the unauthorised building works namely (1) holes formed in the structural beam and (2) one hole formed in the structural and external wall of bathroom in the Premises (“unauthorised building works”). 17.By the letter dated 26 March 2013 from Messrs Cham & Co. Solicitors, the defendant’s solicitors (“Cham & Co”) to Messrs Li, Wong, Lam & WI Cheung, the plaintiff’s solicitors (“LWLC”), the defendant notified the plaintiff that they would treat the Contract as having been repudiated. 18.By letter dated 12 April 2013 issued by LWLC to Cham & Co, the plaintiff instructed the defendant to carry out the reinstatement of the unauthorised building works as required by the BD. 19.By letter dated 8 April 2013 from Cham & Co to the plaintiff, the defendant notified the plaintiff that they would not continue with the project. 20.By the Building Order dated 2 May 2013 issued by the BD to the plaintiff, the plaintiff was ordered to reinstate the unauthorised building works and to appoint an authorised person to supervise the reinstatement of the unauthorised building works (“the Reinstatement Work”). 21.In about June 2013, the plaintiff appointed Prudential Surveyors International Limited (“Prudential Surveyors”) to handle the Reinstatement Work which would cost a total sum of HK$90,000. Valuation of Works by Quantity Surveyor 22.On or about 24 June 2013, pursuant to Clause 6(5) of the Contract, the plaintiff appointed Mr Steve Au-Yeung, a qualified quantity surveyor of A1 Surveyors Limited (“the Quantity Surveyor”), to assess the works done by the defendant on the Premises and to prepare a valuation report on inter alia the works done and outstanding works left by the defendant. 23.On 9 July 2013, the Quantity Surveyor together with his assistant and the representatives of the plaintiff conducted a site inspection at the Premises. Before the joint site inspection, LWLC had notified the defendant by letter to send its representative to attend the said site inspection. However, the defendant or its representative did not show up on the date of site inspection. 24.The main purpose of the site inspection by the Quantity Surveyor was to assess the works done and outstanding works left by the defendant and then prepare the valuation report. 25.The Quantity Surveyor submitted the valuation report entitled “Valuation Report On Fit-Out Work at 15th Floor, 24 Fontana Gardens, Hong Kong” dated 29 August 2013 (“Valuation Report”) to the plaintiff. 26.The Valuation Report addresses inter alia the following issues:
Replacement Contractor 27.In order to mitigate the loss of the plaintiff, since about May 2013, the plaintiff had been searching for a replacement contractor to complete the outstanding works left by the defendant. 28.On 10 October 2013, the plaintiff entered into a written contract in simplified Chinese with Ever Green Decoration Works Company Limited, a fitting-out contractor (“Replacement Contractor”), for the completion of the outstanding works left by the defendant (“Replacement Contract”). The Replacement Contract contains inter alia express terms that the project commencement date be 15 October 2013 and the project completion date be 21 March 2014, ie a total of 100 working days (excluding Saturdays, Sundays and public holidays), and the contract price was agreed at HK$1,813,393.73. 29.On 15 October 2013, the Replacement Contractor took possession of the Premises and commenced the works in accordance with the Replacement Contract. MY ASSESSMENT 30.The plaintiff claims in the statement of claim for a total sum of HK$2,267,255 which comprises 4 sums of money namely:-
31.Mr Suen, Counsel for the plaintiff, rightly conceded that costs of the Valuation Report for HK$88,000 shall only form part of the plaintiff’s legal costs in these proceedings rather than damages. Cost of the Reinstatement Work 32.It is well established that damages for the cost of completion or reinstatement of work undertaken by a third party is recoverable[1]. 33.After the defendant’s abandonment of the Works and refusal to return to the Premises, by the agreement dated 7 June 2013, the plaintiff appointed Prudential Surveyors International Limited (“Prudential Ltd”) to carry out the Reinstatement Work as ordered by the BD. The terms of the agreement include inter alia that Prudential Ltd would-
34.It was agreed between the plaintiff and Prudential Ltd that the service fees for the Consultancy Work to carry out and supervise the Reinstatement Work be HK$90,000. 35.On 23 October 2013, Mr Cheung formally agreed to succeed the Consultancy Work under the same terms and condition of the agreement between Prudential Ltd and the plaintiff dated 7 June 2013. 36.The Reinstatement Work was completed by the contractor under the supervision of Mr Cheung and Mr Chan Hei Leung, a Registered Structural Engineer, of Petros Consulting Engineers Limited (“Mr Chan”) on 8 May 2014. 37.Mr Chan has already submitted the Certificate of Completion of the Remedial Work to the Buildings Department. 38.Mr Suen, Counsel for the plaintiff, referred me to para 4.3 (3) of the Valuation Report which reads:
39.On the basis that (1) the principle that damages for the cost of reinstatement of work undertaken by a third party is recoverable, (2) the Quantity Surveyor’s view that the relevant fees charged by Prudential Ltd for the Reinstatement Work was reasonable and (3) the Reinstatement Work has been completed, I conclude that the plaintiff’s claim for the cost of the Reinstatement Work at HK$90,000 should be allowed. Over-Paid Amount 40.Upon the termination of the Contract and pursuant to Clause 6(5) of the Contract, the plaintiff appointed A1 Surveyors Limited (the Quantity Surveyor) to finalise the project account by valuating the works done by the defendant and the amount of payments already paid by the plaintiff to the defendant. 41.According to the Valuation Report (in para 4.1), the valuation of works completed by the defendant including the 3 No. variation orders and 1 No. quotation work is HK$612,050. 42.Mr Suen, Counsel for the plaintiff, referred me to para 6.2 of the Valuation Report which reads:
43.On or about 29 August 2013, the plaintiff received a refund of deposit of HK$83,167 from a material supplier for the defendant (“the Refund”) namely Man Chong Engineering Co. Ltd. (“Man Chong”). The deposit was previously paid by the defendant to Man Chong for the order of window frames and glasses, etc. According to Man Chong, the said order was regarded cancelled due to the defendant’s abandonment of the Works. Taking into account of the Refund, I accept and assess that the over-paid amount by the plaintiff should be HK$2,006,088 (being HK$2,089,255 minus HK$83,167). Cost of the Replacement Contract 44.Originally, Mr Suen, counsel for the plaintiff, made the claim for costs of the Replacement Contract in the opening submission but after discussion with me, he rightly conceded to withdraw this submission on the reason that such claim is never pleaded in the statement of claim. Liquidated Damages for Project Delay 45.As to the question of whether a contractor is liable for any liquidated damages accruing after termination of contract (provided that the contract itself does not specify otherwise), Mr Suen, Counsel for the plaintiff, is very helpful to draw my attention to the conflicting authorities. Keating on Construction Contracts has this to say:-
46.However, some do not agree with Keating’s view. Construction Briefings on Liquidated Damages (p27), which deals with the issue of whether a claim for liquidated damages after termination of a contract can be made, reads:-
47.Mr Suen, counsel for the plaintiff, further cited the case of Hall & Shivers v Jan Van Der Heiden [2010] EWHC 586 (TCC), in whichCoulson J adamantly rejected the principle that claim for liquidated damages after termination of the contract is not allowed, and allowed an employer to claim liquidated damages after termination of the contract. In his judgment, Coulson J awarded the employer liquidated damages beyond termination through to completion of the project several months later by a replacement contractor. To explain his reasoning, he gave this example (para76-77 of his Judgment):-
48.On the basis of Construction Briefings on Liquidated Damages and Hall & Shivers v Jan Van der Heiden, Mr Suen for the plaintiff submitted that the plaintiff’s claim for liquidated damages should be allowed for the following reasons:-
49.As I do not have the benefit of argument by the defendant, I accept the above submissions by Mr Suen that the plaintiff is entitled to claim for liquidated damages under Clause 6(2) of the Contract after termination of the Contract. Genuine Pre-estimate of Damage 50.Chitty on Contracts 31st ed Vol II Specific Contracts (Paragraph 37-121) provides a succinct summary of liquidated damages clause in construction contracts:
51.In the present case, Clause 6(2) of the Contract provides that liquidated damages be calculated at 0.1% of the contract sum per day, ie HK$3,300 per day for each day of delay caused by the defendant. Mr Suen for the plaintiff submitted that the calculation of the liquidated damages based on the formula “HK$3,300 x number of day of delay” is precise and simple to apply, hence damages can be easily assessed. 52.Mr Suen for the plaintiff also submitted that the sum of HK$3,300 per day of delay stipulated for the liquidated damages realistically reflects the level of damages the plaintiff would likely to suffer in the event of delay. 53.In the case of Tennyson Estate Limited[2], the court accepted that the agreed liquidated damages at HK$2,000 and HK$3,000 per day are more than reasonable and in no way can they be suggested to be extravagant or unconscionable or oppressive, and certainly does not go beyond a genuine pre-estimate of the likely loss to the plaintiff. 54.I accept the above submissions by Mr Suen that the liquidated damages clause of the Contract is a genuine pre-estimate of damage and therefore the plaintiff’s claim under this head should be allowed. Calculation of Liquidated Damages 55.According to the Contract, the Revised Project Completion Date was 19 July 2013. However, the contractual project completion by the Replacement Contractor was 21 March 2014. Therefore, the total number of days of delay is 245 days (inclusive of Saturdays, Sundays and Public Holidays, and both 20 July 2013 and 21 March 2014). 56.Concerning the issue of duty to mitigate, the “Reasonable Steps” test is well established. The onus of proof is on the defendant to prove any failure on the part of the plaintiff to mitigate[3]. So I do not need to consider this issue. If I need to do so, I am of the view that the plaintiff has taken reasonable steps to mitigate the loss, in particular in selecting and engaging the Replacement Contractor within a reasonable time, ie the Replacement Contract commenced on 15 October 2013. 57.Para 4.4 of the Valuation Report reads inter alia that:
58.Therefore, for the reasons given above, I accept the submissions by Mr Suen that the plaintiff’s claim for Liquidated Damages for Project Delay at HK$808,500 (being $3,300 x 245 days) should be allowed. Conclusion 59.In the circumstances, I assess the damages suffered by the plaintiff as follows:
60.I also award interest on the damages assessed at the rate of 8% per annum from the date of the Writ to the date of judgment and thereafter at judgment rate until payment. 61.Regarding costs of this action and hearing for assessment of damages, Mr Suen for the plaintiff submitted a statement of costs for $337,000 and requested me to do the summary assessment under Order 62 rule 9A RHC. 62.By adopting the broad-brush approach, I consider that the costs claimed are unreasonable and excessive. I only allow $100,000 for the solicitors’ costs, $60,000 for Counsel’s fees and $70,000 for the Valuation Report totaling $230,000. 63.I now make an order nisi that costs of this action and this assessment of damages be to the plaintiff with certificate for counsel summarily assessed at $230,000 payable by the defendant. Such order nisi shall become absolute unless any of the parties apply to vary within 14 days.
Mr Suen Chee Hang Henry, instructed byLi, Wong, Lam & WI Cheung, for the plaintiff The defendant was not represented and did not appear | |||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment