Remedy Asia Ltd v. Yick Shing Contractors Ltd
Read the full judgment text of HCCT 4/2012 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 30 September 2014 before Hon Au J in Chambers.
Court of First Instance — construction and arbitration proceedings — leave to appeal — champerty and maintenance — access to justice exception — equitable assignment and locus standi — time bar of claims under Subcontracts A and B — relation-back doctrine under Limitation Ordinance (Cap 347) s 35(1) — amendment of claims with leave or consent — counterclaim to counterclaim under s 35(3) and s 35(4) — procedural law. The defendant sought leave to appeal a decision refusing to strike out the plaintiff's claim based on alleged unlawful champerty under the Assignment, the plaintiff's locus to sue without joinder of True Light, and time-bar defences. The court rejected the defendant's grounds on the access to justice exception, holding no reasonable prospect of success to overturn. It affirmed plaintiff's equitable interest and locus standi with joinder of True Light to avoid double liability. The court held that claims under Subcontract A are not time-barred and that the doctrine of relation-back applies to amendments consenting to include Subcontract B claims preventing strike out on limitation grounds. The defendant’s cited authorities were distinguished as involving different procedural contexts. Further, the counterclaim to counterclaim argument under s 35(3) LO was held academic given the finding on the amendments. The court refused leave to appeal and ordered costs to plaintiff to be taxed if not agreed.
Legal issues: Access to justice exception under champerty and maintenance law · Plaintiff’s locus to sue without joinder of True Light · Time-barred status of Subcontract A claims · Time bar under Subcontract B and relation-back doctrine · Counterclaim to counterclaim under s 35(3) LO
Outcome: Refusal to grant leave to appeal on all grounds
Cited by 1 case · Cites 4 cases
|
HCCT 4/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 4 OF 2012 ------------------------
Before: Hon Au J in Chambers Date of Hearing: 23 September 2014 Date of Decision: 30 September 2014 ------------------------ D E C I S I O N ------------------------ A. INTRODUCTION 1.On 26 June 2014, I handed down judgment (“the Judgment”) dismissing effectively the defendant’s summons to strike out the plaintiff’s claim. 2.This is the defendant’s application[1] for leave to appeal against the Judgment. 3.This decision should be read together with the Judgment. I would also adopt herein the abbreviations used in the Judgment. B. THIS LEAVE APPLICATION 4.In its Notice of Appeal, the defendant raises four principal grounds of appeal. 5.For leave to be granted, the defendant has to show that it has a reasonable prospect of success on any of those proposed grounds of appeal. I would look at each of them now. Ground 1: The court erred in finding that the arrangement under the Assignment falls under the “access of justice” exception and thus not prohibited under the law of champerty and maintenance (para 1 of the Notice of Appeal and paras 8-12 of the defendant’s skeleton) 6.I do not find this ground having a reasonable prospect of success:
7.I would not grant leave to appeal on this ground. Ground 2: The plaintiff lacks locus to bring the present action, without joining True Light as a party to the proceedings, but it cannot do so under the terms of the Assignment (Para 2 of Notice of Appeal and paras 13-16 of the defendant’s skeleton) 8.Under this ground, Mr Parker says the plaintiff is not even an equitable assignee under the terms of the Assignment, and thus it cannot seek to have True Light joined to complete the title to sue. This is so (as I understand the arguments) since:
9.I do not think these arguments bear any reasonable prospect of success:
10.I therefore would also refuse to grant leave to appeal on this ground. Ground 3 – Subcontract A was time-barred to the extent as pleaded in the Re-Amended Defence and Counterclaim (para 3 of the Notice of appeal and para 17 of the defendant’s skeleton) 11.Mr Parker’s contentions under this ground as set out at para 3 of the Notice of Appeal are effectively a re-run of the contentions on the construction of the various relevant clauses in Subcontract A. Suffice for me to say that I am not convinced that they have a reasonable prospect of success for the same reasons I have set out in the Judgment at paras 45-50 and 52. 12.I would refuse to grant leave on this ground. Ground 4 – Time bar under Subcontract B (para 4 of the Notice of Appeal and paras18-26 of the defendant’s skeleton) 13.The first contentions raised under this ground of appeal are principally premised on Mr Parker’s arguments that the court erred in relying (at para 53(1) of the Judgment) on the Court of Appeal’s decisions in Sun Focus v Tang Shing Bor [2012] 1 HKLRD 738 at paras 10-15 and Global Bridge Assets Ltd v Sun Hung Kai Financial Ltd [2012] 4 HKLRD 474 at paras 19-22, to say that, because of the relation back doctrine under s 35(1) of the Limitation Ordinance (Cap 347) (“LO”), it is no longer open to the defendant to seek to strike out the claim under Subcontract B for time-bar after it has consented to the amendments to include those claims. 14.This part of the Judgment is wrong, counsel submits, as the court has failed to deal with the authorities of Liff v Peasley [1980] 1 WLR 781 at 803C and Moulin Global Eyecare Holdings Ltd v Olivia Lee Sin Mei [2012] 4 HKLRD 263 at paras 66-69 per Barma J. Mr Parker says these authorities support the propositions that it is still open to the defendant to challenge a time-bar claim even after the amendments had been consented to and made notwithstanding the relation-back doctrine. 15.With respect, I am not convinced:
16.I similarly would not grant leave on this ground. 17.Lastly, the defendant submits that the court’s alternative observation at para 53(2) of the Judgment is also in error. In that paragraph the court says this:
18.Mr Parker’s submissions in support of this ground are set out at para 26 of his skeleton as follows:
19.In substance, Mr Parker says s 35(4) of the LO has the effect of disbarring the plaintiff from making a counterclaim (or set-off) under Subcontract B (which is time-barred) against the defendant’s own counterclaim brought under Subcontract B because the plaintiff had already made a claim in this action. As a result, the requirement that the plaintiff “has not previously made any claim in an action” is thus not satisfied. 20.I would not grant leave on this ground too as, given my above view that the defendant does not fair a reasonable prospect of success in challenging on appeal the court’s primary conclusion not to strike out the plaintiff’s claims under Subcontract B on the basis of time-bar as the amendments have been consented to, this ground is academic in the proposed appeal. C. CONCLUSION 21.For all the above reasons, I would refuse to grant leave to appeal. 22.I further order that costs of this application be to the plaintiff to be taxed if not agreed.
Mr Ian Pennicott SC, instructed by Messrs Cheung & Lee, for the plaintiff Mr Timothy Parker, instructed by Messrs Massie & Clement, for the defendant [1] By way of its summons dated 9 July 2014. [2] Especially when the defendant did not challenge at the original hearing that the liquidators could have obtained funds from elsewhere. Please refer to HCMP2543/2014 for the relevant appeal(s) to the Court of Appeal. | |||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCCT 4/2012