Capella Ltd v. Ability R&D Ltd
|
CACV 142/2014 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO 142 OF 2014 (ON APPEAL FROM DCCJ NO 4509 OF 2011) _______________
_______________ J U D G M E N T Hon Poon J (giving the Judgment of the Court) : INTRODUCTION 1.In September 2010, the defendant, Ability R&D Limited (“Ability”), engaged the plaintiff, Capella Limited (“Capella”), to carry out renovation works at its registered office. Disputes subsequently arose, which eventually resulted in litigation. 2.In the proceedings below, Capella sued Ability for outstanding balances for the works it performed under 4 quotations and an additional invoice in the total sum of HK$473,785.00. Ability denied the claims and counterclaimed for the costs for remedying and rectifying Capella’s defective works and liquidated damages for delay in completion of the works. 3.After trial[1], Deputy District Judge D Ho (“the Judge”) found for Capella on its claims in full. He allowed part of Ability’s counterclaim on the remedial costs for defective workmanship in the sum of HK$242,694.85 but dismissed its counterclaim for liquidated damages based on delay in completion. The final order that he made was :
4.Ability’s subsequent application for leave to appeal was dismissed by the learned Judge on 8 April 2014. Ability then sought leave from the Court of Appeal, which was granted by Yeung VP on 8 July 2014. BACKGROUND 5.The background has been helpfully summarized by the Judge in his judgment[2], which we would gratefully adopt without repeating it here. 4 ITEMS UNDER APPEAL 6.This appeal has a very limited scope. What Ability sought to challenge is confined to 4 specific items of its counterclaim which the Judge dismissed. Ability contended that the Judge ought to have entered judgment on them instead. The 4 items are :
7.Ability thus argued that the total sum awarded under its counterclaim should have been HK$468,968.85 ($242,694.85 + $40,250.00 + $51,750.00 + $143,750.00 + $464,309.00 – $473,785.00 (judgment sum awarded to Capella)) instead of HK$242,694.85. 8.On that basis, Ability further sought an order that its costs below be borne by Capella. 9.We will deal with the 4 items in turn. ITEM 1 10.The glass door was installed at the main entrance to the premises. It measured 6m (width) x 2.7m (height) with a thickness of 12mm. It was made of tampered glass. It was a frameless glass door hung up by an upper hinge facing a public road. The experts engaged by the parties agreed that the gap between the glass door and the wall finishes was too wide; that the gap at the bottom of the glass door was too large and that the gap between the fixed glass panel and the door was too wide. The experts also agreed that the glass door would vibrate when heavyweight vehicles passed by; and that it would easily move at the free edge with a minor finger push. 11.Ability complained that the workmanship of the glass door was defective and posed a safety problem to passers-by. 12.The Judge said :
13.In our view, in dismissing Ability’s complaint, the Judge had placed too much emphasis on the absence of structural problem with the glass sliding door. Ms Yang for Ability also made the same mistake by stressing that there was no structural problem. They were wrong in so doing because the absence of such structural problem does not necessarily mean that Capella’s workmanship was not defective. According to what the experts had agreed, and absent any evidence to contradict or diminish their evidence, an inescapable finding must be that Capella’s workmanship was in fact defective as Ability alleged. 14.The Judge also erred when he found that having adopted the frameless design with an unavoidable gap at the bottom, Ability would have to live with both the pros and cons of the same, including the associated safety concern of a large glass door facing a public road. It is because under the relevant quotation for the work[5], Capella was responsible for the design, supply and installation of the sliding glass door. Plainly, Ability was relying on Capella’s expertise in designing, supplying and installing a glass sliding door which would not pose a danger to the passers-by, a duty which Capella had breached. 15.The Judge therefore erred in dismissing Item 1. ITEM 2 16.There were 3 staircases in the premises. The Judge proceeded on the basis that all the staircases were not constructed by Capella. Mr Yau told us that in fact one of the staircases was constructed by Capella. This is however a new point not covered by the Notice of Appeal at all. That being the case, we will not allow Mr Yau to argue Item 2 on any factual basis other than the one adopted by the Judge. 17.The Judge dealt with Ability’s complaints about the staircase in these terms : “ 114. There is more than one staircase in the Premises on which Capella had laid timber coverings, the other two being items 185 and 187 in Section 7 of the 2nd joint report. In his witness statement, Mr Leung admitted that the structure of staircase (without specifying which) was not constructed by Capella but averred that since the Quotations included project management, Capella should have alerted Ability to the problems before laying the steps with timber treads and risers. He said one of his staff and he himself had tripped over the stairs.
18.Mr Yau argued, as did his predecessors before the Judge, that Capella had an implied duty to coordinate the renovation works and arising from that duty, a further implied duty to inform Ability of the existence of the uneven staircases. In support of his argument, Mr Yau relied on the terms of the contract : “ Our offer covers design, supply, project management, installation as listed on quotation in Hong Kong Dollars.” (Emphasis supplied) However, Mr Yau’s reliance on that term is completely misplaced. 19.Properly read, the term only applied to works listed in Capella’s quotation and no more. In other words, Capella was only responsible to project-manage the works that it had contracted to provide. It had no duty to project-manage the works provided by other contractors engaged by Ability or to coordinate their works. Without a proper basis, no implied duty to inform as alleged by Ability could possibly arise. 20.The Judge was correct in dismissing Item 2. ITEM 3 21.Item 3 concerned the grade of stainless steel used for the roller shutter to be supplied by Capella. It is not in dispute that the plates were not made of Grade 316 stainless steel. Ability complained that under the relevant quotation[6], the entire roller shutter including the plates were to be made of Grade 316 stainless steel. The veracity of Ability’s complaint depends on a proper construction of the relevant terms in the quotation. 22.Those terms read :
23.Mr Yau argued that on a proper reading of Remark 1, the entire roller shutter should be made of Grade 316 stainless steel. He said in effect that between “鋼閘” and “外框” there should be a comma so that “鋼閘外框”, one single item of the outer frame of the roller shutter should become two items, “鋼閘” and “外框”. Such a construction is plainly wrong and must be firmly rejected. 24.Mr Yau prayed in aid of the undisputed fact that when Capella supplied the first roller shutter in January 2011, it was made of Grade 316 stainless steel entirely. However, it is well-established that the parties’ post-contract conduct had no bearing on its construction. 25.Mr Yau also drew our attention to a letter sent by Mr Leung to Capella dated 30 March 2011 in which Mr Leung raised several questions about the roller shutter to be supplied by Capella. Mr Yau argued that according to what Mr Leung had raised, his understanding was that the entire roller shutter must be made of Grade 319 stainless steel. We doubt if Mr Leung’s own understanding of what the contract meant has any significant in construction. In any event, what Mr Leung had said was :
Mr Leung was only referring to the outer frame of the roller shutter, which is exactly what Remark 1 had provided for. What he said does not support Mr Yau’s argument. 26.The Judge was correct in dismissing Item 3. ITEM 4 27.3 of the 4 quotations had different completion dates. The 4th quotation did not state any completion date. The 4 quotations all provided that :
28.In the Amended Defence and Amended Counterclaim, the claim for delay in completion is pleaded in these terms :
29.Capella’s case was that completion took place on 20 January 2011 when Ability signed the document “Completion Key Delivery”. What Capella’s staff and sub-contractors did subsequently were mere touch-up or additional works. 30.The Judge dealt with Item 4 in §§24 to 52 of his judgment. After analyzing the evidence of Mr Leung and Mr Caleb Chan of Capella (“Mr Chan”), the Judge said :
31.Before us, Mr Yau accepted that irrespective of the different completion dates stipulated in the quotations, the parties had by conduct extended the completion date to 26 January 2011. However, he argued that completion did not take place on 20 January 2011 as found by the Judge. He placed reliance on the letter sent by Mr Leung to Capella on 19 January 2011 where he complained, among other things, about the roller shutter and the fact that the first roller shutter was only replaced in March 2011. He argued that the roller shutter was a blatant defect, far from being trivial. The replacement could not be regarded as touch–up work. 32.It is well-established that in the context of building work, completion means practical or substantial completion. It means that the work has reached a stage of readiness for use by the owner and free from any known omission or defects which are not merely trivial. Plainly, that was how the Judge approached Ability’s complaint in the present case. The Judge had taken into account all the relevant circumstances and carefully analyzed Mr Leung’s and Mr Chan’s evidence in making his finding that completion took place on 20 January 2011. We agree with his analysis. In our view, the Judge was entitled to make that finding on the evidence available to him. We are not persuaded that such a finding was plainly wrong. We see no basis to disturb it. DISPOSITIONS 33.For the above reasons, we allow Ability’s appeal to the limited extent that Ability’s counterclaim on Item 1 be allowed. We therefore revise (a) the total sum awarded under the counterclaim to HK$282,944.85 (HK$242,694.85 + HK$40,250.00 = HK$282,944.85) and (b) the net judgment sum awarded to Capella to HK$190,840.15 (HK$231,090.15 – HK$40,250.00 = HK$190,840.15). We dismiss the remainder of the appeal. 34.On the costs below, we do not think the decision that we made on Item 1 would have any substantial bearing on the apportionment of the costs made by Judge. Accordingly, we do not disturb his costs order. 35.On the costs of the appeal, since Capella has been substantially successful in resisting the appeal, it should have 75% of its costs of both the appeal and the leave application for leave against Ability. We so order.
Ms Eugenia Yang, instructed by Cham & Co, for the plaintiff (respondent) Mr Albert Yau, instructed by Simon Ho & Co, for the defendant (appellant) [1] At trial, Capella was represented by Ms Eugenia Yang of counsel; Ability, by Mr George Chu and Miss Ivy Leung of counsel. [2] At §§3 to 22 of the judgment. [3] Mr Leung in full name is Mr Leung Hin Ting. He is a director of Ability. [4] Mr Ho is Ability’s expert. [5] Quotation No 2010021b dated 27 September 2010. [6] Quotation No 2010021b3 dated 20 October 2010. | ||||||||||||||||||||||||