Kharma Greater China Ltd v. Kharma International B.V.
Read the full judgment text of HCA 545/2013 on BabelCite. This High Court CFI judgment was delivered on 17 March 2017.
1. By Summons dated 7 December 2016, Kharma International B.V. (“D”) makes this application to:
Cites 7 cases
|
HCA 545/2013 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE HIGH COURT ACTION NO 545 OF 2013 ________________________
________________________
_______________ D E C I S I O N _______________ The applications 1.By Summons dated 7 December 2016, Kharma International B.V. (“D”) makes this application to:
2.The applications are contested by Kharma Greater China Limited (“P”). The parties are legally represented.[1] 3.P’s primary position is that both applications should be dismissed. Alternatively, the counterclaim should only be restored with the following conditions imposed:
The background 4.The factual background below is not disputed. 5.Pursuant to an Exclusive Distributorship Agreement (the “Agreement”), D appointed P as the exclusive distributor for the sale of Kharma Products[2] in the PRC, Hong Kong, Macau, Cambodia, Vietnam and Laos for a period of 5 years from 1 January 2010[3]. 6.P commenced this action against D for a breach of the Agreement by: -
7.D, on the other hand, alleges that P was in breach of the Agreement by: -
8.D contends that it was entitled to terminate the Agreement and counterclaims against P for:
The relevant legal principles 9.Both parties refer to the then Registrar Q. Au‑Yeung’s decision on this issue: World Chinese Business Investment Foundation & Ors v Shine Rainbow Marketing Ltd & Ors [2010] 2 HKC 294:
10.D further relies upon the following Decisions:
Discussion – the Reinstatement Application 11.It is quite clear from the Decisions of the above cases that the courts are abiding by Order 1A of the Rule of the High Court. Order 1A, rule 2 provides:
12.P does not dispute that D’s Counterclaim raises the same issues as for his Defence in respect of liability, which has to be dealt with even if the Counterclaim were struck out. The Counterclaim should not be struck out unless it is clear that the Counterclaim has no merit. 13.The Court of Appeal in The Real Estate Developers Association of Hong Kong v Building Authority (unrep., HCMP 1746/2014, Lam VP, 14 May 2015) adopted the decision of Lord Neuburger of the Supreme Court in HRH Prince Abdulaziz Bin Mishal Bin Abdulaziz Al Saud v Apex Global Management Ltd [2014] UKSC 64 that in the application for relief from any sanction for failure to comply with the Order, the court should not hear the merits on the matter unless it is so clear that there is no real answer to it. [18] 14.From P’s written submissions, I do not find that this is a case where D plainly has no real answer to P’s claims. The factual disputes as to whether the parties were in breach of the contract and the issue of passing off D’s goods must be resolved by the trial judge. Discussion – condition of security for costs 15.As to whether this Court should accept P’s proposition on imposing the condition of ordering D to pay $589,125, being the half amount for security for costs of the entire action, P submits that this is proper to do so, referring to: Hong Kong Civil Court Practice Issue 79 (February 2017) at [8880] pp.557-558. I shall quote the relevant passage:
16.Order 25, r. 1C(4) RHC is the provision for imposing condition as the court thinks fit for restoring the Counterclaim. The question is: what is the condition that the court should think fit to impose as condition for restoring the Counterclaim in this case? 17.Here, P proposes half the amount for the security for costs, relying upon the following factors:
18.D opposes this proposal by saying that it is clear that the main issues within the Counterclaim would in any event have to be dealt with by P in establishing its Claim. As such, this is not an appropriate case for ordering security for costs, and at the very least not 50% of total costs. Allowing the Counterclaim to be run will not materially prejudice P from a costs perspective. In any event, D says that the quantum is excessive. 19.In Bank of America National Trusts and Savings Association v Chai Yen [1980] 1 WLR 350 at p.353D, Lord Lane, delivering the advice of the Privy Council, said that “the essence of any rule of procedure must be fairness”. The same is true of any rule of practice. 20.Of all the above authorities cited by the parties, in my view, the court does not impose condition on the defaulting party as penalty or as hindrance to a fair trial of the issues in dispute between the parties. According to World Chinese Business Investment Foundation & Ors, the court has to consider the merit of the Counterclaim. If the merits of it is plainly so flimsy that only conditional leave should be given to it to pursue the Defence on condition that money should be paid into court, this is a good case where the court should consider making an order for payment into court for the restoration of the Counterclaim. Of course, there should be other circumstances that may merit a condition of payment in. However, we shall focus on this case now. 21.This morning, P has referred me to the authority of Lei Tao, in which the learned Deputy High Court Judge had ordered security for costs as a condition for allowing the plaintiff in that case to restore the claim. P submits that this Court should be guided by that decision. I should point out here that the discretion of a higher court on the special facts of the case should not be binding upon me. I should be bound by the rationales and the legal principles decided by the higher court. However, I have to bear in mind consistency in the exercise of the discretion. I shall distinguish that case from this case for the reasons that first, the court in that case had found that the plaintiff’s non-attendance at the hearing was intentional and contumelious. Second, the defendant had applied for security for costs before a Master, who had rejected the application. Such application can be considered by the learned Deputy High Court Judge. When he considered all the circumstances of the matter, including the plaintiff’s conduct, which he was entitled to do, he had made the order as he did. 22.Here in this case, P had not made any application for security for costs before. Also, D’s conduct, though there being some delay, should not be classified as intentional and contumelious. 23.P’s proposal of ordering D to pay half the amount for security for costs is not acceptable to me for the reasons as follows:
24.For the reasons above, I reject P’s proposal. 25.P has not proposed other condition in the written submissions for my consideration. In the circumstances, I grant leave to D to restore the Counterclaim without any condition. Extension of Time Application 26.On the Extension of Time Application, P agrees to allow D to have 35 days, as requested, to exchange its provisional expert report subject to an unless order. The question is whether the Court should impose an unless order. Unless order should not be made without history of non-compliance of the court's orders: §23 of K M Cheung & Co Solicitors (a firm) v Kung Ching (unrep., HCA 831/2011 Le Pichon DHCJ, 26 October 2012). But "unless order" can be made at the Case Management Conference, without having regard to the history of non-compliance under Practice Direction 5.2 §29; §10 of GTC Industries Ltd & Others v Lee Man Hoi Ocean & Others (unrep., HCA 600/2012, 4 January 2013). 27.D has no dispute over the procedural chronology as set out in P’s written submissions. As such, this matter should receive more robust case management to ensure that the proceedings should progress the way they should. D is obviously the cause for the delay in these proceedings. With the history of delays in the proceedings, I agree that an unless order is warranted. D has no strong objection to this proposal. So I order. Costs and order 28.As to the costs of this application, including the summons and the hearing today, P asks for costs for this application including the costs for today’s hearing, relying upon the authorities of World Chinese Business Investment Foundation [27], Wishing Star Ltd. [70] and Lei Tao [43(6)]. D asks this Court to consider the costs order made by Master Lo in Wong Kar Gee Mimi where she ordered the requesting party to pay all the costs up to the final preparation for the application and thereafter, the costs were awarded to the requesting party as she had succeeded her application for reinstating her claim. D submits that this is akin to the application for amendment of the pleadings where the requesting party should bear the costs for the application, but the opposing party should bear the costs for losing the argument. 29.Costs are very much at the discretion of the court, taking into consideration of all the circumstances of the case. In the case of an application for amendment, which the law does not require any affidavit evidence in support except for allegations of fraud or defamation, which demonstrates that such application can be quite plain and easily seen from the amendments themselves. See 20/8/4 of the White Book 2017. For this application, it is clearly incumbent upon D to set out the reasons on affidavit to explain his reasons for his absence at the Case Management Conference in September 2016. P is quite entitled to hold D to give the reasons and argue its case before the court. Absence at the Case Management Conference is, under the relevant statutory provisions, a very serious matter indeed. The Court should not pass a wrong message that such a misconduct is equivalent to an application for amendment of the pleadings, which is, by the conduct of the applicant, neutral without any evidence of abuse. 30.For the reasons above, I adopt the majority decisions that the costs of this application, including the costs for today (with counsel’s certificate) be to P, to be assessed summarily under O.62, r.9A RHC to be $130,000 to be paid by D to P within 14 days from the date hereof. 31.I shall make an order in terms as follows:
32.For the case management, the next hearing should be a Case Management Summons hearing as the parties are not certain when to take out an application for expert evidence on quantum of damages and there would be an application for a split trial for passing-off claims. The next Case Management Summons hearing is at 10:00 a.m. on 16 October 2017.
Miss Connie Lee, instructed by Cheung & Liu, for the Plaintiff Mr. Alexander Tang, instructed by ONC Lawyers, for the Defendant [1] See at the end of this Decision [2] See: SOC at §2 [A/t1/2]. [3] See: SOC at§3 [A/t1/2]. [4] See: SOC at §§5-13[[A/t1/7-13] [5] See: SOC at §§14-21[A/t1/13-15] [6] See: SOC at §§22-28[A/t1/15-17] [7] See: D&CC at §§8.1-8.6[[A/t2/39-40]. [8] See: D&CC at §8.7 [A/t2/40]. [9] See: D&CC at §§8.8-8.10 [A/t2/40-42] [10] See: D&CC at §§51-55[A/t2/58-60]. [11] See: D&CC at §§56-59[A/t2/60-61]. [12] See: D&CC at §§60-68[A/t2/61-64]. |
Cases cited in this judgment
Further hearings and rulings under HCA 545/2013