Able Luck Development Ltd and Others v. Boly Metal Manufactory Ltd and Others

Read the full judgment text of LDCS 11000/2018 on BabelCite. This LDCS judgment was delivered on 19 March 2019.

1. This is the applicants’ application for review of my decision made on 20 February 2019, whereby I have given extension of time to the parties to file and exchange evidence including experts’ evidence.

Cites 2 cases

Case No.LDCS 11000/2018
Court
LDCS
Date19 Mar 2019
Judge
Case Document
100%Judiciary

LDCS 11000/2018

[2019] HKLdT 22

IN THE LANDS TRIBUNAL OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

LAND COMPULSORY SALE MAIN APPLICATION NO. 11000 OF 2018

_________________

BETWEEN
Able Luck Development Limited
(加福發展有限公司)
1st Applicant
Biel Crystal Manufactory Limited
(伯恩光學有限公司)
2nd Applicant
Manway Corporation Limited (文威有限公司) 3rd Applicant
Huge Wise Trading Limited (廣智貿易有限公司) 4th Applicant
Sky Huge Development Limited (廣天發展有限公司) 5th Applicant
Nice Express Development Limited
(益通發展有限公司)
6th Applicant
Able Wide Corporation Limited (廣能有限公司) 7th Applicant
Well Nice Corporation Limited (佳美有限公司) 8th Applicant
High Smart Industrial Limited (領駿實業有限公司) 9th Applicant
and
Boly Metal Manufactory Limited
(寶利金屬製品廠有限公司)
1st Respondent
Cheng Sing Kun (鄭誠根) 2nd Respondent
Yuen Pui Kiu (阮佩翹) 3rd Respondent
Pawling Limited 4th Respondent
Henson & Company Limited (漢信洋行有限公司) 5th Respondent
PSK Limited 6th Respondent
Le Son Wong 7th Respondent
Ng Cheung Fui (吳翔奎) 8th Respondent

_________________

Before: His Honour Judge M WONG, Presiding Officer of the Lands Tribunal
Date of Last Written Submission: 18 March 2019
Date of Decision on Review: 19 March 2019

______________________

DECISION ON REVIEW

______________________

1.This is the applicants’ application for review of my decision made on 20 February 2019, whereby I have given extension of time to the parties to file and exchange evidence including experts’ evidence.

2.The grounds raised by the applicants in this review application are as follows:-

(1)   The relevant respondents have scheduled with the applicants
to complete the inspection of all the remaining units and to conduct field tests around the end of March 2019, and hence the time for the parties to file and exchange evidence should be shortened to 2.5 months from the end of March 2019;

(2)   The tribunal should give adequate consideration to the delay caused by the respondents’ experts, who should have been aware of the express comments of Her Honour Judge Kot at the hearing on 16 July 2018 that 3 months should be the appropriate time allowed for preparation of expert reports and who should have acted swiftly all along without delay;

(3)   The estimated construction costs of the redevelopment of the Building is being inflated at a rate of 3% per month, and hence any unnecessarily lengthy time extension will cause delay to the proceedings and is detrimental to the applicants’ interests, in that the financial costs suffered by the applicants will not be compensated; and

(4)   One of the underlying objectives of the CJR is to ensure that cases are dealt with as expeditiously as is reasonably practicable. 

3.However, the fact that the parties have now scheduled to complete the inspection of all the remaining units and field tests to be conducted around the end of March 2019 is something that happened after my decision.  Whether the inspection and field tests could actually be done around the end of March 2019 are still yet to happen.  It is always possible that such work may still not be done around the end of

March 2019 because of unforeseen circumstances.  It is premature to say that the uncertainty and ground to justify the extension of time is now removed.

4.During the hearing, the applicants did not argue against the time frame of the respondents’ experts, but just asserted that the respondents’ experts should not inspect further units.  I do not accept that the respondents’ experts were wrong in insisting on inspection of further units or that they were delaying the matter.

5.The alleged inflation rate of the estimated construction costs was not mentioned at the hearing and is not substantiated with any evidence. There is no reason for the tribunal to accept such a bare assertion. In any event, even if there is such a loss to the applicants, it is always a litigation risk that the applicants have to bear, and it cannot outweigh the necessity for the respondents’ experts to have adequate time to inspect the units, conduct field tests and prepare reports.

6.No doubt the underlying objective of the CJR is to ensure that cases are dealt with as expeditiously as is reasonably practicable. However, it should not be at the expense of giving adequate time for the respondents’ experts to do their jobs.

7.If the work could indeed be completed earlier than estimated, then the applicants should later on apply for variation of the order made, instead of reviewing the decision, which was made without knowing that the parties could have arranged the schedule so quickly.

8.The applicants submit that the approach for review adopted in the case of Triumphal Fountain Limited and Another v Chan Chui Lun and Others [2002] HKEC 47 is not applicable to the present review because it is not a review after trial.  There is no basis to make such a submission at all. The approach for review should be the same whether it is before or after trial.

9.Thus, I do not find that there is any valid ground to review my decision made on 20 February 2019, and I decide not to review my decision.

10.The applicants’ application for review is therefore dismissed with costs order nisi that the applicants do forthwith pay the 1st to 7th respondents costs of the review application to be summarily assessed on papers at High Court scale.

11.The 1st to 7th respondents are to submit and serve their respective Statement of Costs on or before 1 April 2019.

12.The applicants are to submit and serve their Statement of Objection on Costs on or before 15 April 2019.

13.If there is no application to vary the costs order nisi on or before 1 April 2019, it shall become absolute thereafter.

 
 

  M WONG
  Presiding Officer
Lands Tribunal

Mr YC Mok, instructed by Sit, Fung, Kwong & Shum, for the 1st to 9th applicants

Mr HC Man and Ms WN Lau, of Ho Tse Wai & Partners, for the 1st to 3rd and 5th to 7th respondents

Ms CM Seto, of Woo Kwan Lee & Lo, for the 4th respondent

The 8th respondent, unrepresented, was absent