West Kowloon Cultural District Authority v. Aig Insurance Hong Kong Ltd
Read the full judgment text of HCA 2039/2018 on BabelCite. This High Court CFI judgment was delivered on 2 April 2020.
1. There are 2 summonses before this court.
Cited by 2 cases · Cites 2 cases
|
HCA 2039/2018 [2020] HKCFI 569 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 2039 OF 2018 _________________
_________________ Before: Hon Ng J in Chambers Date of Hearing: 10 April 2019 Date of Judgment: 2 April 2020 ________________ J U D G M E N T ________________ Introduction 1.There are 2 summonses before this court. 2.First, the Defendant’s application by summons dated 11 September 2018 for the Writ and Statement of Claim herein to be struck out and the Action to be dismissed on the grounds that none of the 3 demand letters relied upon by the Plaintiff constitute valid demands upon the Bond No H.7478 (“Bond”) issued by the Defendant since
3.At paragraph 2 of the Defendant’s summons, it seeks in the alternative that this Court determines as a preliminary matter the following questions of law and/or construction of the following documents –
4.Second, the Plaintiff’s application by summons dated 14 September 2018 for summary judgment against the Defendant on the basis that it had made a valid demand on the Bond. In the prayer of the Statement of Claim, the Plaintiff’s claim is for the sum of HK$297,198,000 together with interest. 5.By a consent order of Master Ho dated 14 September 2018, and for reasons unknown to this court, the Plaintiff’s application for summary judgment and the Defendant’s application to strike out the Writ and Statement of Claim only were ordered to be heard together. This is meant to be the hearing of the said 2 applications. However, since the issues raised by the Defendant in resisting summary judgment are the same as the basis for the striking out application as well as the preliminary issues raised in the Defendant’s summons, it is inevitable that this court’s decision on the said 2 applications will also effectively determine the preliminary issues one way or another. Material Facts 6.The basic material facts are uncontroversial and can be briefly summarized as follows. 7.The Plaintiff is the body corporate established under the West Kowloon Cultural District Authority Ordinance, Cap 601, engaging in the development of the West Kowloon Cultural District. 8.By General Conditions of Contract for Building and Civil Engineering Works dated 26 September 2015 (“Contract”), the Plaintiff engaged Hsin Chong Construction Company Limited (“Hsin Chong” or “Contractor”) as contractor for the construction of a project known as “M+” project. 9.By Clause 14(1) of the Contract, Hsin Chong was obliged to obtain and provide to the Plaintiff a bond in its favour from a bank or other financial institution, valid until completion of the works. Pursuant to the clause, Hsin Chong procured the Defendant to issue to the Plaintiff a Form of Contractor’s Bond No H.7478 and dated 8 October 2015 ie the Bond in the sum of HK$297,198,000 (“Bonded Sum”). 10.The Bond expressly provided that the Defendant is irrevocably and unconditionally bound to the Plaintiff in the sum of HK$297,198,000 for payment of which sum the Defendant binds itself in accordance with the provisions of the Bond. 11.The clause of the Bond which is of special relevance to the present case is Clause 2:
12.Further, Clause 3(b) of the Bond expressly provides that the liability of the Defendant under the Bond shall remain in full force and effect and shall not be affected or discharged in any way by, and the Defendant hereby waives notice of inter alia the termination of the Contract or the employment of the Contractor under the Contract. 13.On 17 August 2018, the Plaintiff issued a formal notice to Hsin Chong under Clause 74.1 of the Contract advising that the Plaintiff was terminating Hsin Chong’s employment under the Contract on the basis that a default had occurred under Clause 73.1(a) viz “You have become insolvent.” (“Termination Letter”). The Plaintiff also required Hsin Chong to leave “the Site and the Project Site forthwith”. In the same notice, the Plaintiff announced its intention to employ others to execute the remaining works. 14.The relevant parts of Clauses 73.1(a) and 74.1 of the Contract provided:
15.Also on 17 August 2018, the Plaintiff delivered to the Defendant a letter demanding payment of the Bonded Sum (“1st Demand”). 16.The relevant parts of the 1st Demand stated that:
17.On 21 and 24 August 2018, the Plaintiff delivered to the Defendant 2 letters again demanding payment of the Bonded Sum (“2nd Demand” and “Final Demand” respectively). These 2 demands are effectively chasers and add little, if at all, to the 1st Demand. 18.The Defendant failed to comply with the Demands and on 29 August 2018, the Plaintiff commenced the present Action. Deliberation 19.The legal principles in relation to applications for summary judgment and striking out are trite and no doubt familiar to experienced senior counsel on both sides. They will not be rehearsed here. 20.In Kono Insurance Ltd v Tins’ Industrial Co Ltd [1987] 3 HKC 71, Hunter JA stated that the first issue in a case of this kind is the true construction of the bond in question and his Lordship identified 2 different types of bonds ie a single or on demand bond and a double conditional bond. At 74E and 75B of the report, the learned Judge observed:
21.In Trafalgar House Construction (Regions) Ltd v General Surety & Guarantee Co Ltd [1995] 3 All ER 737 at 742j–743a, Lord Jauncey observed:
22.In his skeleton submissions, Mr Westbrook SC correctly and very properly accepted that the wording of the Bond points to it being an on demand bond. 23.In relation to the nature of on demand bond, Deputy Judge Lok (as he then was) set out his understanding in Hyundai Engineering & Construction Co Ltd v UBAF (Hong Kong) Ltd [2012] 5 HKLRD 620 at 624-5, which this court gratefully adopts:
24.In the skeleton submissions of Mr Maurellet SC and Mr Westbrook SC, the parties are ad idem that there are 2 issues which fall for determination by this court:
Formality Issue 25.On this issue, both parties accept that it is a question of construction of the terms of the Bond and whether the Demands (or more precisely the 1st Demand) complied with Clause 2 of the Bond. 26.In Nishimatsu Construction Co Ltd v AHA Co unrep, HCA 10416 of 1999, 20 September 1999, the plaintiff applied for summary judgment on a bond entered into by the defendant the terms of which were substantially identical to the present one. The most relevant parts of the Judgment are:
27.On the basis that the demand in that case was a conforming one, Recorder Kotewall SC granted summary judgment in favour of the plaintiff. 28.Similarly, in Esal (Commodities) v OCL [1985] 2 Lloyd’s LR 546 at 550, Ackner LJ (as he then was) set out the twin requirements of a valid demand on the bond in that case:
29.The question is therefore: did the 1st Demand comply with the requirements of Clause 2 of the Bond? 30.One thing is very clear: proof of the Contractor’s default or the amount demanded is not necessary. Paraphrasing Recorder Kotewall SC in Nishimatsu Construction Co Ltd v AHA Co, and as a matter of construction, all that is required under Clause 2 are:
31.In this court’s view, 1st Demand satisfied all 3 requirements and is therefore a valid demand on the Bond. 32.First, the 1st Demand was in writing. 33.Second, the Plaintiff did say in the 1st Demand that it was of the opinion that the Contractor was or had been in default in respect of various of its obligations under the Contract. 34.Third, the Plaintiff has set out the sum demanded ie HK$297,198,000 and that the sum was in respect of damages, losses etc sustained by reason of the Contractor’s default. 35.In his skeleton submissions, Mr Westbrook SC submits that the 1st Demand was defective in that it did not identify the amount of damages, losses etc sustained by the Plaintiff by reason of Hsin Chong’s unspecified default. Specifically, Mr Westbrook SC submits that in the 2nd paragraph, the Plaintiff merely demanded payment of the full Bonded Sum without stating the basis for the demand while in the next paragraph, it alleged defaults and consequential damages, losses etc but failed to identify the amount of any such damages, losses etc. 36.With respect, this court does not agree. 37.First, specifying a particular breach/ default by the Contractor or particularizing the amount of damages, losses etc sustained is not a requirement under Clause 2: see, for instance, the 3rd requirement laid down by Recorder Kotewall SC in Nishimatsu Construction Co Ltd v AHA Co at [18]. 38.Second, and importantly, the 1st Demand must be read as a whole and not in a truncated manner. If one reads the 2nd and 3rd paragraphs of the 1st Demand as a whole, and putting two and two together, it is reasonably clear that the Plaintiff was saying expressly, or at least in substance, the basis for the demand for the full Bonded Sum was that the Contractor’s default had caused the Plaintiff to suffer and sustain damages and losses etc to the tune of HK$297,198,000, the only figure which appeared in the1st Demand. 39.In IE Contractors Ltd v Lloyds Bank Plc and Rafidain Bank [1990] 2 Lloyd’s Rep 496, the bond provided that “We undertake to pay you unconditionally the said amount on demand, being your claim for damages brought about by the above named principal”. At p 502 of the reported Judgment, Sir Denys Buckley said this:
40.In this court’s view, IE Contractors Ltd v Lloyds Bank Plc and Rafidain Bank stands for the proposition, which this court fully endorses, that as long as the demand states in substance what is required in the bond, and is understood by its recipient as such, the demand will be treated as a valid one. This approach is wholly consistent with the importance of preserving the certainty and reliability of on demand bonds, which, as emphasized in the authorities, are their essential and defining characteristics. Being hypercritical of the wording of a demand and an overzealous insistence of strict compliance would only serve to undermine the certainty and reliability of on demand bonds. This should be rigorously resisted. 41.Mr Westbrook SC then complains that the 1st Demand purports to include a claim for future or prospective losses which are not within the terms of the Bond. 42.It is true that the 1st Demand also referred to damages, losses etc that the Plaintiff would continue to suffer and sustain by reason of the Contractor’s default. But the reference to future damages, losses etc does not vitiate or render nugatory that part of the 1st Demand which did refer to damages, losses etc sustained by reason of the Contractor’s default which are admittedly within the ambit of the Bond. Since Clause 2 does not require particularization or proof of the amount demanded as damages, losses etc sustained, the additional reference to future damages and losses is at most redundant and a surplusage and can be ignored. It might be different if the 1st Demand only referred to future damages and losses but omitted to mention damages, losses etc already sustained: cf AES-3C Maritza East 1 Eood v Credit Agricole [2011] EWHC 123 (TCC)[1]. If that were the case, the Defendant’s argument that the 1st Demand is thereby rendered defective would have more force. But that is not the case here. 43.To conclude, for the reasons stated above, this court holds that the 1st Demand does comply with the requirements of Clause 2 of the Bond and the Formality Issue should be decided in the Plaintiff’s favour. Fraud Issue 44.In Hyundai Engineering & Construction Co Ltd v UBAF (Hong Kong) Ltd, Deputy Judge Lok (as he then was) set out his approach when fraud is relied upon to resist payment in the context of a summary judgment application based on a performance bond.
45.In Enka Insaat Ve Sanayi A.S v Banca Popolare Dell’Alto Adige SPA [2009] EWHC 2410 (Comm) at [24] - [25], Teare J adopted the principle that “particularly cogent evidence” is required to establish the fraud exception by banks or other financial institutions seeking to resist summary judgment based on a performance bond:
46.This court respectfully agrees. 47.Hence, whether one applies a “low” test or a “heightened” test, there is a considerable degree of consensus in the authorities that there are special considerations for a summary judgment application based on a performance bond and that particularly cogent evidence is required to establish the fraud exception. 48.In the present case, the evidence of fraud relied upon by the Defendant is contained principally in the affidavit of Richard John Wilmot, a partner of the Defendant’s solicitors. The evidence supporting the assertion of a fraudulent demand by the Plaintiff consists of only a few paragraphs and for ease of reference will be set out in full below:
49.In this court’s view, such evidence is little more than a mere assertion, rather than cogent evidence, let alone particularly cogent evidence, of fraud. 50.First, regarding Hsin Chong’s breach of the Contract by virtue of its insolvency, the so-called lack of bona fide belief on the part of the Plaintiff is simply based on (i) the fact that there was no prior determination of insolvency in winding up proceedings or otherwise, and (ii) Hsin Chong’s denial of it. In this court’s view, (i) is a complete non sequitur - a company can be insolvent, on the cash flow test or the balance sheet test, whether or not there has been prior determination of insolvency; while (ii) is simply irrelevant. 51.In the ordinary course of things, the issuer of a bond ie the Defendant, would normally not have access to the financial records of the procurer of the bond ie Hsin Chong. Nor would it normally have knowledge of the dealings and interaction between the beneficiary and procurer of the bond ie the Plaintiff and Hsin Chong respectively who had dealt with each other since the Contract dated 26 September 2015, if not earlier. There is no evidence that this case is any different. In this court’s view, unless the Defendant had access to the accounting records of Hsin Chong prior to 17 August 2018, and there is no suggestion that it did, the Defendant simply cannot make good the assertion, even in a RHC O 14 context, that the Plaintiff did not genuinely believe that Hsin Chong was insolvent. The Defendant's assertion, in the words of Megarry V-C, is all surmise if not Micawberism. 52.In order to overcome this difficulty, the Defendant turns from defence to attacking the (in)sufficiency of the 2nd Affidavit of Ronald Michael Randall where he referred to 4 media reports about Hsin Chong. That seems to this court to be reversing the burden of proof by requiring the Plaintiff to present sufficient evidence to justify its belief in Hsin Chong’s insolvency. That is also totally contrary to what Clause 2 of the Bond expressly provides ie “without conditions or proof of the said default …”. 53.Second, concerning the loss and damage suffered and sustained by the Plaintiff as a result of Hsin Chong’s insolvency, the so-called lack of bona fide belief on the part of the Plaintiff is based on (i) the fact that the 1st Demand was made on the same day as the Termination Letter ie 17 August 2018 and again (ii) Hsin Chong’s dispute of it. 54.In this court’s view, (i) is a complete non sequitur while (ii) is irrelevant. 55.The fact that the Termination Letter was issued on 17 August 2018 does not mean Hsin Chong only became insolvent on that very day. Indeed, it is rare, if not utterly impossible, for a company to be solvent on 16 August and suddenly became insolvent on 17 August. At this stage, there is no evidence as to when Hsin Chong became insolvent. The fact that the 1st Demand was issued on the same day as the Termination Letter equally does not mean the Plaintiff had suffered no damages, losses etc prior to the termination of Hsin Chong as contractor. The relevant event for the present purpose is Hsin Chong’s insolvency, rather than its termination as contractor. 56.In its skeleton submissions, the Defendant assumes that the vast majority of the Plaintiff’s losses must relate to the possible future additional costs of executing the work by others after Hsin Chong’s eviction from the site. But on a proper construction of Clause 2, as long as the Plaintiff's damages, losses etc were resulted from Hsin Chong’s default under the Contract ie its insolvency (rather than its termination and eviction from the site), they would be within the ambit of Clause 2. Since the Defendant would have little or no knowledge of the dealings and interaction between the Plaintiff and Hsin Chong, and there is no evidence to the contrary, it cannot say what are the financial consequences to the Plaintiff as a result of and commencing from Hsin Chong’s insolvency. 57.More importantly, it is the Plaintiff’s belief of the amount of its damages, losses etc which is relevant, not what a court or tribunal subsequently determines what that amount should be. The beneficiary under an on demand bond may genuinely believe it has suffered damages, losses etc within the meaning of the bond entitling it to make a demand for a certain amount before there is precise and detailed computation of the quantum. Otherwise, the express wording of Clause 2 ie “If, in the Plaintiff’s opinion…the Defendant shall upon demand…and without conditions or proof of the…amount demanded pay the amount identified in the demand” would be rendered meaningless. 58.The significance of a claimant's belief was emphasized by Knowles J in National Infrastructure Development Company Limited v Banco Santander S.A. [2016] EWHC 2990 (Comm) at [10]-[13]:
59.On the facts of that case, Knowles J was not prepared to conclude that it was seriously arguable that the claimant did not honestly believe in the validity of the demands or that it did not believe that sums were due and owing. The learned Judge granted summary judgment to the Claimant accordingly. 60.To conclude, for the reasons stated above, this court is not satisfied that the Demands made by the Plaintiff were mala fide - the Fraud Issue should also be decided in the Plaintiff’s favour. Disposition and cost order nisi 61.Given this court’s view that the 2 issues[2] raised be decided in favour of the Plaintiff, it naturally follows the Plaintiff’s application for summary judgment succeeds and the Defendant’s striking out application fails. This court hereby grants summary judgment in favour of the Plaintiff in the sum of HK$297,198,000 together with interest at the rate of Prime plus 1% from 17 August 2018 to Judgment and thereafter at the Judgment rate until payment, and dismisses paragraphs 1, 3 and 4 of the Defendant’s summons. 62.In light of the fact that this court has entered summary judgment in favour of the Plaintiff so that the entire Action is disposed of and that the 2 preliminary issues have in substance been decided against the Defendant, this court will make an order nisi that paragraph 2 of the Defendant’s summons is also dismissed. 63.There shall be an Order nisi that costs of the Action, including costs of the Plaintiff’s summons and the Defendant’s summons, be to the Plaintiff, to be taxed if not agreed and paid forthwith, certificate for senior counsel. 64.Lastly, this court thanks counsel on both sides for their helpful assistance.
Mr Jose Antonio Maurellet, SC and Mr James Niehorster, instructed by Bryan Cave Leighton Paisner LLP, for the Plaintiff Mr Simon Westbrook, SC, instructed by Stephenson Harwood, for the Defendant [1] In that case, Ramsey J ruled at [39] and [41] that the claim on the on-demand bond in that case had to be based on an assertion by the Claimant that the sum was due and payable by the contractors for the breach of their obligations since as a matter of construction of the bond, sums not yet due and payable by the contractors were not to be the subject of demands under the bond, even if those sums might inevitably be due and payable at some future date. [2] Which, as stated earlier in this Judgment, are the 2 preliminary issues raised in para 2 of the Defendant’s summons. In his skeleton submissions at para 2, Mr Westbrook SC describes the Plaintiff’s summons for summary judgment under RHC O 14 and the Defendant’s summons for the determination of the preliminary issues under RHC O 14A are effectively opposite side of the coin. | ||||||||||||||
Cases cited in this judgment
Other judgments that cite this case