Milestone Builder Engineering Ltd v. Yau Kwong Contracting Ltd
Read the full judgment text of HCMP 143/2020 on BabelCite. This High Court CFI judgment was delivered on 23 October 2020.
1. This is the substantive hearing of the Originating Summons (" OS ") dated 24 January 2020 concerning the application by the plaintiff (“ Milestone ”) for an injunction order restraining the defendant (“ YK ”), whether by itself, or its servants or agents or otherwise howsoever, from presenting any petition to this Honourable Court for the winding up of Milestone based on a statutory demand served upon Milestone on 14 January 2020 (the " SD ") claiming the sum of HK$4,987,048.68 plus further i
Cites 8 cases
|
HCMP 143/2020 [2020] HKCFI 2669 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE MISCELLANEOUS PROCEEDINGS NO 143 OF 2020 ____________
____________
____________ Before: Mr Recorder Pow, SC in Chambers Date of Hearing: 8 October 2020 Date of Judgement: 23 October 2020 _______________________ J U D G M E N T _______________________ 1.This is the substantive hearing of the Originating Summons ("OS") dated 24 January 2020 concerning the application by the plaintiff (“Milestone”) for an injunction order restraining the defendant (“YK”), whether by itself, or its servants or agents or otherwise howsoever, from presenting any petition to this Honourable Court for the winding up of Milestone based on a statutory demand served upon Milestone on 14 January 2020 (the "SD") claiming the sum of HK$4,987,048.68 plus further interest. 2.By a contract entered into between Spring Moon Investments Ltd (the “Employer”) and Milestone dated 4 August 2017 (the “Main Contract”), Milestone undertook to be the main contractor for alteration and addition works at 22 Wang Yip Street, Yuen Long, Y.L.T.L. No 374 (the “Site”). 3.Pursuant to the “MVAC and Electrical Installation Nominated Sub-Contract” entered into between Milestone and YK on 23 June 2017 (the “NSC”), YK became a nominated sub-contractor in respect of MVAC (mechanical ventilation & air conditioning) and electrical installation works at the Site (the “Project”). There were 3 other nominated sub-contractors in the Project responsible for different types of construction works. 4.The relevant debts stated in the SD (“Alleged Debts”) concern four interim payments (“NSC IP-18, IP-19, IP-20 and IP-21”) plus interests owed by Milestone to YK pursuant to the NSC. There is no dispute that Milestone has not made all or any part of these payments. Particulars of NSC IP-18 to 21 are as follows:-
5.Under the NSC Clause 33.1[1], payment for work done by YK is to be made in accordance with the following mechanism:-
6.On 5 March 2019, the Architect issued a notice of default to Milestone pursuant to the Main Contract (the “Notice of Default”)[2], stating that it had committed the following defaults (collectively, “Milestone’s Defaults”):
7.Upon certification from the Architect, on 23 March 2019, the Employer served on Milestone a written notice to determine its employment under the Main Contract (the “Notice of Determination”)[3]. By the operation of NSC Clause 38.1, upon the determination of the Main Contract, the NSC was also terminated at the same time. 8.YK has repeatedly demanded Milestone to make payments[4]. However, almost 5 months after the Notice of Determination was served, Milestone alleged that no outstanding payment was due to YK. Instead, it alleged that because YK had caused delay and was in default, a balance of HK$11,121,000 was owed from YK. In particular, it was alleged that YK was “provisional liable” for 224 days of delay (between 11 August 2018 – 23 March 2019) and hence liquidated damages in the sum of HK$15,680,000 (the “Alleged YK LD”)[5]. This was the first time since the Notice of Determination some 5 months earlier, that Milestone claimed that YK had caused delay and was in default. It is relevant to note Clauses 24.3 and 28.5(1) of the NSC:-
9.Between 10 September 2019 and 9 October 2019, YK repeatedly denied that it had caused or contributed to Milestone’s Defaults, and stressed that Milestone had not given any notice of default to YK pursuant to NSC Clause 36[6]. 10.Milestone’s next responses on 30 September 2019[7] were that:
11.On the issue of whether the Employer had paid Milestone for NSC IP 18-21, YK relies on an email from the Employer dated 9 October 2019 to YK (“Employer’s Email”)[8] stating they had paid the following amounts to Milestone under the Main Contract:-
12.Upon YK’s inquiry and YK’s request for direct payment by the Employer, the Architect wrote to Milestone[9] stating that:-
13.In a letter dated 9 October 2019 from YK to Milestone, YK stated that they were not responsible for the LD deducted by the Employer against Milestones and that the Employer had already paid for MC IP-20 to MC IP-23. YK also pointed out that Milestone’s application for EOT was irrelevant to Milestone’s payment obligation under the NSC. Plaintiff’s case 14.Milestone argues that there are bona fide disputes between them and YK for the following reasons:-
Defendant’s responses 15.YK argues that there was no bona fide dispute on substantial grounds for the following reasons:-
Applicable legal principles 16.The principles which govern an application for an injunction to restrain the presentation of a winding-up petition were recently restated by DHCJ Maurellet SC in Quest Investments Ltd v Lee Wai Tung [2020] HKCFI 1516, §14:
Discussion 17.Applying the above principles which are not in dispute between the parties, it is my judgment that Milestone has failed to discharge its burden of demonstrating a bona fide dispute on the Alleged Debts for reasons set out hereunder. 18.On Milestone’s first argument that it had not received payment from the Employer and hence is not liable to pay NSC IP-18 to IP-21, the Court is referred to NSC Clause 33.1(7) which reads:-
19.Mr. Li, counsel for Milestone referred me to Hong Kong Teakwood Works Ltd. v. Shui On Construction Co. Ltd. [1984] HKLR 235. He argued that in that case, the phrase “receipt of payment” in a clause similar to NSC Clause 33.1(7) was interpreted to mean receipt of money and thus the exercise of a set off by the building employer did not amount to receipt of payment by the main contractor under that clause. In that case, the relevant clause was clause 11(b) of that subcontract which read:-
The matter before Hunter J was an Order 14 application taken out by the sub-contractor against the main contractor. It was common ground that the main contractor received 2 certificates from the architect certifying the value of works completed by the sub-contractor. The main contractor argued that it was not obliged to pay the sub-contractor because the building owner set up against those two certificates an alleged set off arising from a claim for liquidated damages clause under the main contract. The main contractor argued that “receipt of payment” means cash or cheque, money and nothing else. The sub-contractor argued that “receipt of payment” means cash or a mutual discharge of the obligation arising under the certificate, and that discharge can arise from the exercise of a set off. In reply, the main contractor further argued that there could only be a discharge or payment if that set off is valid which they challenged. Thus in order to show that payment is due to the sub-contractor under this clause, the sub-contractor has to satisfy the court that the set off is not only claimed, but validly claimed. Hunter J held that the words “receipt of payment” should be given their normal meaning, which means receipt of actual payment, ie receipt of money. Hunter J held that whilst the word “payment” can be given an extended meaning, he could not give an extended meaning to the phrase “receipt of payment” to cover set off. However, Hunter J expressly stated that he was not willing to make a final construction of clause 11(b) in that Order 14 proceedings. It was unnecessary for his Lordship to do so. Hunter J said:-
20.In my judgment, although the Teakwood case is relevant and helpful, it is not determinative nor can it be of direct application. First of all, Hunter J did not make a final construction of clause 11(b) in that case at all. His Lordship was aware that for a final construction, more in-depth consideration of other interconnected clauses in the contract would have to be undertaken. His Lordship had not done so as it would not be necessary at an Order 14 stage. His dictum was thus mere statements of his prima facie assessment. Secondly, each contract has to be interpreted in its own terms and context. The wordings of clause 11(b) in Teakwood case are different from that of NSC Clause 33.1(7). Clause 11(b) in Teakwood case referred to “receipt by the main contractor of payment from the employer against any certificate from the architect”. Whereas in NSC Clause 33.1(7), the operative words are: “[Milestone] is required to pay [YK] the amount included for him in each interim certificate…within 14 days…of [Milestone] receiving payment from the Employer”. In my judgment, words “receiving payment from the Employer” must refer back to the particular interim certificate issued by Milestone to the Employer which included an amount for the sub-contractor’s work done. This is distinctly different from clause 11(b) in Teakwood case in which the receipt of payment clearly referred to “payment against the architect certificate” which in Teakwood case was a reference to the architect certificate certifying the value of the works undertaken by the sub-contractor. Thus, in Teakwood case, the fact that the employer imposed liquidated damages on the main contractor under terms of the main contract could not be taken to mean that the employer had made payment to the main contract against the architect certificate certifying the work done by the sub-contractor. In the present case, in relation to NSC Clause 33.1(7), I am of the view that the words “receiving payment” refer to payment of the relevant MC IPs in which amounts under the respective NSC IPs had been included. The crucial question is thus whether Milestone had received payment for the MC IP-20 to MC IP-23 which had included the sums claimed by YK under NSC IP-18 to NSC IP-21. In my view, on the evidence presented, MC IP-20 to MC IP-23 had indeed been paid by the Employer albeit after exercising its right of using the LD. As further explained below, it is clearly anticipated by NSC Clause 33.1(10) that the Employer can exercise a right of deduction “from monies due to [Milestone]”. In other words, whilst an amount is due to Milestone under a certain MC IP, the Employer can make deduction either in partial or in total extinction of such amount due under the MC IP. In that case, it cannot be said that the said MC IP had not been paid by the Employer, albeit through the exercise of a set off. 21.Be that as it may, Mr Lui, counsel for YK submitted that I need not base my decision on the above construction. He submitted that on the evidence presented, Milestone had in fact received payment for MC IP-20 to MC IP-23. Firstly, as pointed out in paragraph 15 above, both the Employer and the Architect considered that MC IP-20 to MC IP-23 had been paid. Mr Lui further referred me to Milestone’s own documentary evidence showing that it had actually received payment for MC IP-20 to MC IP-23 as follows:-
22.I accept the submissions of Mr Lui and conclude that Milestone has raised no bona fide dispute on the basis of its first argument. Pursuant to NSC Clause 33.1(7), the amounts due under NSC IP-18 to NSC IP-21 had become due and payable by Milestone to YK unless Milestone rightfully exercised any right of deduction within 14 days of payment of each of MC IP-20 to MC IP-23. Milestone clearly had not exercised that right of deduction within each respective 14 days period. The first time Milestone purportedly justified its non-payment as “rightful deduction” was on 22 August 2019[32]. 23.In respect of Milestone’s second argument that it was entitled to make deductions, I again reject Milestone’s submissions and accept those of YK. In my view, as seen from paragraph 15(5) above, Milestone has failed to put forward “credible evidence” or “sufficiently precise factual evidence” to substantiate its alleged entitlement to make deductions. As mentioned above, Milestone did not attempt to make deduction within each respective 14 days period when MC IP-20 to MC IP-23 became paid. Milestone’s attempt to shift full responsibility of the delay onto YK by making a “provisional deduction of 224 days of LD” was baseless. It also reflects that Milestone did not even have a clear case as to whether YK would eventually be held responsible for delay, and if so for how many days. The same is reflected in the stance shown in Milestone’s affidavit evidence. It has consciously chosen not to carry out a detailed programme analysis to examine how the net delay may be attributed and apportioned between Milestone and its nominated sub-contractors (including YK). Milestone’s alleged entitlement to make deduction is no more than a bare allegation. 24.Furthermore, it is also relevant to look at NSC Clause 31.1(10) which reads:-
In my view, the interplay of NSC Clauses 33.1(7) and (10) is as follows:-
25.In the present case, Milestone had not exercised any right to make deduction within 14 days from the respective payments made by the Employer for the MC IPs (albeit by way of set off using the LD). The full amounts claimed under NSC IP-18 to NSC IP-21 became due and payable. Furthermore, up to now, Milestone has produced no credible or sufficiently precise factual evidence to identify and establish the extent of the Employer’s LD deduction which were due to YK’s breach of contract or default. Milestone’s Reliance on the Lasmos Case 26.In Re Southwest Pacific Bauxite (HK) Ltd, [2018] 2 HKLRD 449 ("the Lasmos case"), Harris J dismissed a petition to wind up a company on the grounds of insolvency by relying on a statutory demand for payment of a debt said to arise under a management service agreement which contained an arbitration clause. He held that (in paragraph 31 on p 468 of the judgement) a petition for winding up should generally be dismissed:
27.Milestone submits that applying the above principles, the intended petition by YK based on the SD is bound to fail and an injunction should be granted because:-
28.The Lasmos case had subsequently been explained by the Court of Appeal in But Ka Chon v Interactive Brokers LLC [2019] 4 HKLRD 85 and Sit Kwong Lam v Petrolimex Singapore Pte Ltd [2019] 5 HKLRD 646 [DA#6]. It should now be clear that the Court retains a discretion under the insolvency legislation which should not be exercised only in one way by reason of the factor of arbitration although considerable weight should be given to this factor in the exercise of the Court’s discretion. In But Ka Chon at §53, Kwan VP stated that an insolvency petition would not be dismissed or stayed on the mere existence of an arbitration agreement, when the debtor has no genuine intention to arbitrate. In Sit Kwong Lam, at §37, Kwan VP said that to show a genuine intention to arbitrate, the debtor must have taken the steps required under the arbitration clause to commence the process of arbitration, and file an affirmation demonstrating this. In But Ka Chon, a letter stating that the debtor’s solicitors were instructed to initiate arbitration between the parties, without indication of when any “Notice of Arbitration” is to be sent, was not regarded as proper notice of an intention to arbitrate (see §52 per Kwan VP). A formal notice of arbitration must leave the recipient in no doubt of the applicant’s intention to resort to arbitration, and that some action is required of the recipient: Re Asia Master Logistics Ltd [2020] 2 HKLRD 423, §45 (per DHCJ W Wong SC). In Re Asia Master Logistics, the debtor company’s inaction for 6 months, after its solicitors sent a letter proposing arbitration, negated any real intention to resolve the dispute by arbitration (see §§41-43, 50). 29.Mr Lui submitted that on the evidence, Milestone had evinced no genuine intention to arbitrate. Milestone places reliance on its current arbitration with the Employer over Milestone’s consolidated EOT claims. However, this dispute simply has no connection with YK’s entitlement to NSC IP 18 – 21 owed by Milestone. Further, if Milestone really thought that YK’s debts are “hotly disputed”, it could have applied to join YK to the arbitration with the Employer (which is permissible under NSC Clause 49.9(1)), seeking a declaration of non-liability in respect of YK’s debts, and then applied for a stay pending that arbitration: see Sit Kwong Lam, §39 (per Kwan VP). The excuse proffered by Milestone that it was awaiting the results of its dispute resolution with the Employer, is plainly unacceptable. Although the SD was served almost 9 months ago (on 14 January 2020), Milestone has not taken any steps to initiate any of the dispute settlement procedures under NSC GC Clause 42 (whether to appoint “Designated Representatives”, or to refer the dispute to mediation or arbitration). Clearly, Milestone has failed to demonstrate any genuine intention to arbitrate vis-à-vis YK. In the premises, the mere existence of an arbitration clause in the NSC cannot prevent YK from exercising its statutory right to petition for winding up Milestone on the ground of insolvency (following But Ka Chon). 30.Mr Li effectively accepted that the 3rd requirement set out by Harris J in Lasmos case has not been satisfied. He submitted that the 3rd requirement is not a necessary requirement. He submitted that Milestone wants to first proceed with EOT claim and that is why no step has been taken towards arbitration between Milestone and YK. Mr Li submitted that it does not mean Milestone has no genuine intention to arbitrate. 31.I do not agree with Mr Li. The evidence adduced by Milestone indicates that it has no present intention of instituting arbitration with YK. At most, Milestone’s conduct amounts to reserving its position pending the resolution of its EOT claim under the arbitration between itself and the Employer. I accept the submission of Mr Lui that Milestone’s attitude is not materially different from the mere existence of an arbitration agreement between Milestone and YK and I would exercise my discretion accordingly. 32.Ultimately, the most potent factor affecting my exercise of discretion is the fact that I have earlier concluded Milestone has failed to discharge its burden of establishing bona fide dispute on the Alleged Debts for reasons set out in paragraphs 17 to 25 above. Coupled with what I have stated in paragraph 31 above, I have concluded that I shall exercise my discretion to refuse the grant of injunction sought by Milestone. 33.Accordingly, the OS is dismissed with costs against Milestone, to be taxed (if not agreed) on party-and-party basis with certificate for counsel.
Mr Vincent M K Li instructed by Lui & Law for the Plaintiff Mr Victor Lui instructed by William W L Fan & Co. for the Defendant [1] B2/219-220 [2] B2/381 [3] B2/383 [4] See YK’s letter 18/3/2019 at B2/385-387 [5] B2/317 at 319 [6] See B1/227 [7] B2/450 [8] B2/452 [9] B2/493-504 [10] See B2/297 [11] B2/302-376 [12] B2/317-320 [13] B2/493 [14] Tang 1st, §10-12 at A/12; see also [15] B2/298 [16] B2/299 [17] B2/295 [18] B2/324 [19] B2/327 [20] B2/333-350 [21] B2/353 [22] B2/355 [23] B2/493 [24] B1/234 [25] B2/302-316 [26] They concern a total of 299 days’ delay due to (a) revision of interior design, (b) hoisting of Tropical Cyclone Warning Signal No. 8 or above, (c) additional phasing of the works, (d) revised design of LED light fittings and external wall tiles, (e) final drainage amendment works, (f) additional wall partitioning and finishing, (g) provision of sales office and show flat, (h) additional steel posts at 1/F carpark, and (i) approval of General Building Plans and Drainage Amendment. See also Tang 1st, §13 [A/4/13-14]; Tang 2nd, §20 [A/6/43-44]; Milestone’s Skeleton §14. [27] B2/317 especially at 319 [28] Tang 2nd, §§24-25, 36 [A/6/44, 46] ; Milestone’s Skeleton §§2(2), 13-16, 23. [29] B2/332 [30] B2/299 [31] B2/295 [32] B2/317 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment