Malayan Banking Berhad v. China Insurance Co Ltd
Read the full judgment text of CACV 424/2002 on BabelCite. This 高等法院上訴法庭 judgment was delivered on 10 June 2003 before Hon Woo JA, Cheung JA.
Civil Procedure — Appeal — Striking out summons — Claim for wasted expenditure damages — Causation and pleading requirements — Order 18 rule 19 — Order 14A application for determination of contractual construction — Whether suitable for summary determination — Joinder of parties — Order 15 rule 12 representative proceedings — Discovery implications — Costs orders. The plaintiff, acting as agent for a syndicate of banks, claimed wasted expenditure damages against defendant pursuant to a performance bond following breach and termination of a development agreement by a contractor. Defendant applied to strike out the wasted expenditure claim on pleading grounds and absence of causation allegation, and sought determination under Order 14A on the construction of termination clause 24. Defendant also applied to join the other two banks as co-plaintiffs. The Court of Appeal held the claim for wasted expenditure was not uncontestably bad and required trial to determine causation and abandonment issues, rejecting striking out. The Order 14A question was held unsuitable for summary determination given the need for factual findings about abandonment and contract context. The joinder summons was wrongly dismissed: representative procedure for three banks was inappropriate, and refusal deprived defendant of discovery rights, justifying order to stay the action until joinder. Costs orders were largely affirmed except as to joinder summons costs. Appeal allowed in part to require joinder and stay. Key legal principles clarified include the necessity of causation in contract damages claims, the limited use of Order 14A procedure for mixed questions of fact and law, and the court's discretion in joinder where discovery and fairness issues arise.
Legal issues: Whether claim for wasted expenditure should be struck out · Whether question as to construction of clause 24 is suitable for determination under Order 14A · Whether the action requires joinder of OUB and OCBC as co-plaintiffs · Whether the judge erred in costs order relating to striking out summons
Outcome: Appeal allowed on joinder summons; order dismissing joinder summons set aside; action stayed until OUB and OCBC joined; rest of appeal dismissed
Cited by 1 case · Cites 2 cases
|
CACV000424/2002 CACV 424/2002 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 424 OF 2002 (ON APPEAL FROM HCCT NO. 48 OF 1999) ---------------------------
--------------------------- Coram: Hon Woo and Cheung JJA in Court Date of Hearing: 3 June 2003 Date of Judgment: 10 June 2003 ----------------------- J U D G M E N T ----------------------- Hon Woo JA (giving the judgment of the Court): Introduction 1.This is an appeal from the decision of Burrell J on 10 September 2002 when he dealt with two summonses taken out by the defendant dated respectively 28 March 2002 and 4 April 2002. 2.The summons of 28 March 2002 sought the striking out of certain paragraphs of the re-amended statement of claim and also sought, under Order 14A of the Rules of the High Court, the court's determination of questions of law and construction ("the striking out summons"). The summons of 4 April 2002 sought an order to stay all proceedings in the action until the plaintiff amends the writs of summons and the pleadings by adding Overseas Union Bank Limited ("OUB") and Overseas-Chinese Banking Corporation Limited ("OCBC") as co-plaintiffs ("the joinder summons"). 3.The striking out summons broadly sought to strike out the plaintiff's claim in respect of two matters, namely, the delay damages claim and the wasted expenditure claim. Prior to the hearing before the judge, the plaintiff abandoned the delay damages claim, and as a result, the parties and the judge focused on the wasted expenditure claim. The judge gave his decision on 10 September 2002 and made orders which, after correction under the slip rule, are as follows:
4.The question of costs on the two summonses was left to be agreed between the parties. However, no agreement was reached and the parties returned before the judge who made the following orders:
5.Against the orders in (1) to (4) above, the defendant now appeals. Broad issues 6.Apart from appealing against costs, the appeal raises three broad issues:
Background facts as pleaded 7.The dispute between the parties arose out of a project to develop a site in Tong Mi Road, Kowloon ("the Site"). United Trump International Limited ("UTIL") purchased the Site with financial assistance from the plaintiff, OUB and OCBC. The loan amount was agreed at $332,500,000 for the Site and the construction cost for building a hotel on it. By an agreement dated 8 April 1997 ("the Development Agreement") made between UTIL and Molitoko Limited ("Molitoko"), Molitoko agreed to redevelop the Site and to construct a hotel on the Site for sum of $150,000,000. The defendant executed a Performance Bond dated 29 April 1997 ("the Bond") in favour of UTIL guaranteeing the due performance by Molitoko of the Development Agreement. The loan granted to UTIL by the plaintiff and the two other banks was secured, inter alia, by an assignment dated 8 April 1997 made between UTIL and the plaintiff whereby UTIL assigned and agreed to assign to the plaintiff all of the rights, title and interest in and all of the benefits and claims to them under the Development Agreement and the Bond. The defendant acknowledged the assignment in writing. 8.By its statement of claim, the current version being the re-re-amended statement of claim dated 31 October 2002 amended pursuant to the order of the judge dated 23 October 2002, the plaintiff alleges that because of breaches of the Development Agreement by Molitoko, it had exercised its right to terminate the Development Agreement pursuant to clause 24 thereof. It is also pleaded that the notice of termination was served on 20 March 1998 and that as Molitoko had at the expiry of 7 business days from the date of the notice still failed or wrongfully refused to attend to and rectify, remedy or mitigate the matters set out in the notice, the Development Agreement was automatically terminated. It is also pleaded (in paragraph 13) that
9.It is also pleaded that despite the termination, Molitoko wrongly and in breach of clause 24.4 of the Development Agreement refused to handover possession of the Site to UTIL. The plaintiff commenced proceedings against Molitoko and obtained an order for possession of the Site in High Court Proceedings HCMP 3774 of 1998. However the plaintiff was only able to obtain possession of the Site on 30 April 1999. 10.By a letter dated 19 May 1999, UTIL served on the defendant a notice of call on the Bond. By a letter dated 12 May 1999, the plaintiff served on the defendant a final written notification and demand under the Bond demanding payment of $30,000,000 (the limit of the Bond) to the plaintiff. It is pleaded in paragraph 15 of the re-re-amended statement of claim that the losses suffered by UTIL are wasted expenditure in the sum of $89,353,863.43. 11.The relevant provision of the Bond is as follows:
The wasted expenditure 12.Mr Yu SC, on behalf of the defendant, stresses that the statement of claim is defective regarding the plea of wasted expenditure. He argues that a material averment of the plea, namely, the causation of the wasted expenditure, which is the only item of damages that remains pleaded in the statement of claim after the abandonment of the delay damages claim, is missing. The wasted expenditure as pleaded includes the interest on the loan that UTIL had to pay to the banks and the interest on the capital outlay of UTIL, together with the money wasted on the construction of the hotel before the Development Agreement was terminated and shortly after. 13.Mr Yu refers us to Chitty on Contracts, 28th Edition, para 27-024 for the proposition that causation is a necessary ingredient of a claim for damages for breach of contract. The paragraph states as follows:
14.Mr Yu complains that the standard form of pleading "by reason of the matters aforesaid" does not appear in the statement of claim to link the wasted expenditure plea to Molitoko's breaches complained of. He argues that as the plaintiff has had ample opportunity to remedy the defect, but failed to do so, it demonstrates clearly that the plaintiff is unwilling or unable to aver causation. The interest incurred for the loans from the banks had been incurred by UTIL because such loans were borrowed and they were borrowed for the purchase of the Site. Although there has been no plea that the project had been abandoned by reason of Molitoko's breaches, it is apparent from the statement of claim that the plaintiff has abandoned the project to build a hotel, because the plaintiff has abandoned its claim for damages arising from delay in the construction of the hotel or damages based on the liquidated damages provision in the Development Agreement, and because it claims wasted construction costs as part of the wasted expenditure. 15.On behalf of the plaintiff, Mr Tong SC submits that it is self-evident from the statement of claim that the project has been abandoned. However, he points out that the abandonment has not been pleaded because it is not what the plaintiff relies on in making the claim. What the plaintiff relies on is simply that there were breaches of the Development Agreement by Molitoko and the plaintiff has suffered loss and damage. He also submits that it is clear from the statement of claim that loss and damage flowed from Molitoko's breaches. Mr Tong draws our attention to the following matters to establish the causal connection between the wasted expenditure and the breaches of Molitoko:
16.Mr Tong also relies on Chitty on Contracts, para 27-059 to submit that the court assumes profitability in favour of the innocent party and it is for the wrongdoer to prove otherwise. 17.On the complaint that the words "by reason of the matters aforesaid, the plaintiff has suffered loss and damage" are not in the statement of claim, Mr Tong submits that these words were never there from Day 1 and the defendant pleaded to the statement of claim without objection from May 1999 to January 2002. Mr Tong submits that if necessary, these words can be added by way of an amendment, and this on its own does not justify a striking out. 18.In our view, the way in which the statement of claim is pleaded shows clearly that the plaintiff alleges that the loss and damage by way of wasted expenditure were caused by Molitoko's breaches of the Development Agreement, although the normal practice of using the words "by reason of the matters aforesaid" has not been adopted. We do not think that the absence of these words, if it is the crux of the complaint, justifies an application to strike out and, for that matter, an appeal against a refusal to strike out. 19.The crux is, however, not the form of the wording used in the statement of claim, but rather that there can be no causal link between Molitoko's alleged breaches and the alleged wasted expenditure. It will be noted that although it is not disputed by Mr Tong that that the hotel project has not been proceeded with, nonetheless in the statement of claim, no specific timing is mentioned regarding the intention on the part of UTIL to abandon the project. On the contrary, it is pleaded in paragraph 13 of the statement of claim that "it was the intention of UTIL to resume work on the project by appointment of another contractor." It is also pleaded in paragraph 11 of the re-re-re-amended reply that UTIL appointed the architect and Chun Wo (the foundation contractor) to continue with the hotel development on 4 June 1998. The intention to abandon the project, if at all, must have come later, but as to when, it is not pleaded by the plaintiff. Mr Tong emphasises that it is not the plaintiff's case that the abandonment has anything to do with its loss and damage. As far as the plaintiff is concerned, its position is simply that Molitoko breached the Development Agreement, resulting in loss and damage to the plaintiff. It is for the plaintiff to elect the basis as to how it claims and seeks to prove the damages. If the defendant states that it was the abandonment that caused the loss and damage, it is a matter for the defendant to prove and it cannot be a matter for striking out. 20.We agree. In Anglia Television Ltd v Reed [1972] 1 QB 60, where an actor who had contracted with the plaintiffs to play the leading man's part in a television play which they were producing later repudiated the contract, and the plaintiffs could not get a substitute for the part and abandoned the production of the film, the Court of Appeal held that the plaintiffs were entitled to recover against the actor for their wasted expenditure that had been incurred before and after the contract. At pp 63H-64F, Lord Denning MR said:
21.Taking into account the principle stated in Anglia Television, Mr Yu's main argument is reduced into this: It was because of the abandonment of the project by UTIL that the claimed loss and damage by way of wasted interest on the bank loan and its own capital outlay was caused by the abandonment and not by Molitoko's breaches. We are not persuaded that this must be an inevitable conclusion or that this can be decided without a proper trial for the court to hear the evidence from the parties. 22.We also attempt to look at the issue from another angle. Assuming that Molitoko was guilty of breaches of the Development Agreement, as pleaded by the plaintiff, there could be two courses open to the plaintiff. One was to complete the project and the other was to abandon it. Whether either course with consequential loss was within the contemplation of UTIL and Molitoko is a matter for evidence and for trial. It cannot be a ground for striking out. Similarly, whether one of the courses adopted by the plaintiff would amount to a failure to mitigate damage would also be a matter of evidence and trial. If the plaintiff chose to complete the project, Molitoko's breaches would have caused a delay in the completion of the hotel with consequential damages such as increased construction costs (if any), damages for the delay in having the hotel, if operated as such to produce an income, or alternatively to sell it as a hotel (as opposed to selling a plot of land). If UTIL chose to abandon the project, the interest on the loan and on its own capital outlay would all be wasted and the construction costs incurred before the abandonment also wasted. Mr Yu argues that UTIL would have incurred the interest on the loan and on the capital outlay in any event, which interest could therefore not have been caused by Molitoko's breaches. We do not agree. Had Molitoko fulfilled its obligations under the Development Agreement, the plaintiff would, as scheduled in the Development Agreement, have a hotel in June 1999. But as pleaded in the statement of claim, Molitoko breached its obligations under the Development Agreement that caused the termination of it by the plaintiff in March 1998 and the plaintiff was unable to repossess the Site until the end of April 1999. This gave rise to the two courses of action that UTIL might take, which would not have been opened to UTIL had there been no breach. 23.In paragraph 19 of his judgment, the judge said:
24.The judge also dealt with the argument that the claimed losses would have arisen by reason of the project being abandoned and not because of Molitoko's breaches. He said that it was a matter of fact for the defence to prove. 25.We agree. Whether it was the abandonment, independent of Molitoko's breaches, that caused UTIL's wasted expenditure or otherwise it is, in our judgment, a matter for trial, which in the present circumstances of this case does not justify a striking out. The Order 14A application 26.The issue that the defendant sought the court's determination, as set out in striking out summons, is:
27.The judge first identified the proper approach to an Order 14A application. He said:
28.The judge refused to exercise his discretion because he did not consider that he had all the material facts and matters before him required for determining the question and that he was not satisfied that it was a question that is suitable for determination under Order 14A. He elaborated:
29.Clause 24 of the Development Agreement provides as follows:
30.It is to be noted that the right of termination by UTIL is according to the first phrase of clause 24.1 to be "without prejudice to any of its rights or remedies". It is also repeated in the body of clause 24.1 that "the owner (without prejudice to any other rights or remedies it may have) may within 7 Business Days after such failure, refusal continuance or repetition by notice pursuant to Sub-clause 24.2 terminate this Agreement". Clause 24.6 also uses the word "including" (as highlighted above). 31.From the highlighted provisions of clause 24, it appears to us that at least it is arguable that the damages recoverable following a valid termination of the Development Agreement are not necessarily those exclusively provided for under that clause or limited to the recovery of additional costs (if any) of completing the works and loss caused by the delay in completion following such termination, as contested by the defendant. Where the issue posed by the defendant's Order 14A application is not definitely capable of being resolved in its favour, the determination of the question will not finally dispose of the plaintiff's entire cause of action or claim. This alone would have justified the judge's refusal to accede to the application. We agree with the judge that the proper determination of the issue might involve findings of fact in the context of the matrix of facts that are normally necessary for determining the proper construction of a contractual term, such as clause 24. 32.Mr Yu complains that if the damages claimed are not based on clause 24, then there is an absence of a plea, independent of clause 24, that Molitoko's breaches amounted to a repudiation which was accepted by UTIL. However, in our judgment, the underlying material facts have been pleaded by the plaintiff for making such a claim, and the absence of an express plea on repudiation does not, in the circumstances of this case, justify a contention that the judge was wrong in refusing to determine the issue sought to be determined pursuant to Order 14A. Joinder of plaintiffs 33.Mr Yu's refers us to the general rule that a party cannot appoint an agent to sue in the name of the agent. He submits that the judge was wrong to refuse the joinder summons since Order 15, rule 12 of the RHC should not be applied to the present case because the representative plaintiffs procedure is intended to apply where there are numerous parties who have the same interest in the action. In this action, there are only three banks who have an interest in suing the defendant on the Bond. There are not "great in number" and should not be allowed by the court to use the plaintiff as the agent for them to act as the sole plaintiff in this action. Mr Yu stresses that since the two lending banks apart from plaintiff are not parties, they cannot be ordered to make discovery of documents (see Ventouris v Mountain [1990] 1 WLR 1370), especially documents relevant to the defence under paragraphs 10-12 and 23A of the re-re-re-amended defence, which is that the termination of the Development Agreement was not caused by Molitoko's breaches but that UTIL had decided to abandon the project because it could not obtain further loans for the construction of the hotel from the banks. 34.The judge gave a number of reasons for dismissing the defendant's application for joinder of the two banks. He said:
35.We must say that while the judge has stated a number of reasons for his refusal to exercise his discretion under O 15, r 12(1) to order a joinder of the OUB and OCBC, there is merit in Mr Yu's point that the rule is generally applicable only where "numerous" persons having the same interest in suing are involved. There are only three banks here. It is hard to see why they should be allowed to be represented by only one of them, contrary to the normal rule that an agent cannot sue in his own name (see Jones v Gurney [1913] WN 72). 36.The fact that the assignment of the project and the Bond was in favour of the plaintiff alone and the defendant's acknowledgement of it should not be treated as a ground for justifying the two other lending banks being joined as plaintiffs, because the assignment was made to the plaintiff as an agent for itself and the two other banks as lenders, and the defendant's acknowledgment of the assignment does not mean that it had agreed that the plaintiff can sue as an agent. 37.Nor should the lateness of the application militate against granting it. It is apparent that it was when the defendant was not satisfied with the discovery only by the plaintiff and not by the two other banks that eventuated the application. 38.In Chinavest II-A, LP v Chan Leung UN Roy [1998] 4 HKC 453, the plaintiff and a number of companies claimed against the defendant for breach of contract to sell shares and obtained O 14 judgment against the defendant for his failure to pay the sums due. The defendant appealed. The Court of Appeal, while dismissing the appeal against the judgment, ordered all the sellers to be joined as plaintiffs in the action. Godfrey JA said at 459E-F:
39.While the judge in the present case apparently did not accept that the fact that OUB and OCBC are companies incorporated overseas being sufficient for him to order joinder, we consider that there is justification for Mr Yu's complain that without these two banks being actual plaintiffs, no discovery can be ordered against them (Ventouris v Mountain), and thus an unfair disadvantage towards the defendant has resulted. Mr Yu has drawn our attention to the defence that the termination of the Development Agreement by UTIL was unreasonable and vexatious, and that there are documents showing that these two banks were actively involved in decisions relating to the loan, and thus it is not unlikely that these two banks have documents that may assist the defendant in proving its defence. Mr Tong, on the other hand, refers us to a letter from the plaintiff's solicitors stating that there were no documents relevant to the issues in this action that were with the two banks. However, this statement is not in the form of an affidavit and one cannot be sure that the solicitors had the authorisation of the two banks to make the statement. The defendant is not bound to accept the statement as true. 40.We consider that although the defendant is not able to point to any specific documents that OUB and OCBC may disclose on discovery, yet discovery to be made by a party is a matter of course in the normal course of a litigation, and there is no sufficient reason or justification, because the plaintiff has chosen to represent itself and the two other banks, for the defendant to be deprived of such a benefit which should be available to contesting parties in normal civil litigation. 41.In the circumstances, we consider that the judge was wrong in refusing to grant the joinder summons. Costs 42.The appeal also attacks the judge's orders as to costs. On the costs orders, Mr Yu merely relies on the reasons set out in the notice of appeal which consists of two grounds against the costs order made by the judge. One is that the defendant's application under the striking out summons was substantially successful and had forced and/or would have forced the plaintiff to amend its pleadings further. The judge thus erred in not awarding the defendant all its costs in connection therewith. The second ground is that the judge erred in ordering that the defendant should only be permitted to recover its costs in relation to its striking out summons up to 9 August 2002. The basis of this ground is that the plaintiff by its Calderbank offer only offered to pay the costs of that summons up to 9 August 2002. It did not offer to pay costs thrown away arising out of the delay damages claim and/or abandonment thereof, and that it did not concede that its pleadings require further amendment above and beyond the deletion of the delay damages claim. The defendant was accordingly justified in proceeding with the striking out summons, and the judge erred in depriving the defendant of its costs and in ordering it to pay the plaintiff costs of so doing. 43.It is trite that costs are within the sole discretion of the judge. The judge had heard the parties for two days before he reached his decision on 10 September 2002. Counsel for the plaintiff had told the judge right at the beginning that the delay damages claim was abandoned. As is apparent from the judge's decision, he only dealt with the wasted expenditure claim. On that, the defendant had argued and lost. The judge did not award the entirety of the costs against the defendant for this failed summons. He has ordered costs in favour of the defendant up to 9 August 2002 and also the "additional costs thrown away arising out of the abandonment of the delay damages claim". We are not persuaded that the judge was plainly wrong in the exercise of his discretion. We are not disposed to interfere. Conclusion 44.For the above reasons, we allow the appeal relating to the joinder summons. We set aside the order made by the judge dismissing that summons, and make an order that until the OUB and OCBC are joined as plaintiffs in this action, the action be stayed. Apart from that, the rest of the appeal is dismissed. 45.Since the defendant is partially successful with the appeal, we make the following order nisi as to costs, having taken into account the amount of time employed by the parties in dealing with the various issues before us:
Representation: Mr Ronny Tong SC and Mr Anthony Chan SC, on the instructions of Messrs Simmons & Simmons, for the plaintiff Mr Benjamin Yu SC, on the instructions of Messrs Masons, for the defendant |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under CACV 424/2002