West Kowloon Cultural District Authority v. Aig Insurance Hong Kong Ltd
Read the full judgment text of CACV 82/2020 on BabelCite. This Court of Appeal judgment.
1. This is the defendant’s appeal against the summary judgment granted by Ng J (“the Judge”) in favour of the plaintiff on 2 April 2020 (“the Judgment”). By the Judgment, the Judge also dismissed the defendant’s summons dated 11 September 2018, which sought to, inter alia , strike out the plaintiff’s writ and statement of claim (“Defendant’s Summons”).
Cites 2 cases
|
CACV 82/2020 [2022] HKCA 975 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO 82 OF 2020 (ON APPEAL FROM HCA NO 2039 OF 2018) ________________________ BETWEEN
________________________ Before: Hon Yuen, Barma and Au JJA in Court Date of Hearing and Judgment: 10 September 2021 Date of Reasons for Judgment and Decision on Costs: 30 June 2022 ________________________ REASONS FOR JUDGMENT ________________________ Hon Au JA (giving the Reasons for Judgment and Decision on Costs of the Court): A. Introduction 1.This is the defendant’s appeal against the summary judgment granted by Ng J (“the Judge”) in favour of the plaintiff on 2 April 2020 (“the Judgment”). By the Judgment, the Judge also dismissed the defendant’s summons dated 11 September 2018, which sought to, inter alia, strike out the plaintiff’s writ and statement of claim (“Defendant’s Summons”). 2.By way of a Notice of Appeal dated 29 April 2020, the defendant advanced three grounds of appeal, which are categorized in its skeleton submissions as “the Demand Grounds” (Ground 1 and Ground 2 in the Notice of Appeal) and the “Fraud Ground” (Ground 3 in the Notice of Appeal). In light of the decision dated 18 September 2020 by this Court (Lam VP (as he then was) and Yuen JA) refusing the defendant leave to adduce new evidence for this appeal (“Leave Decision”), Mr Lam SC for the defendant indicated at the hearing that it would no longer pursue the Fraud Ground in this appeal. This appeal therefore is only concerned with the Demand Grounds. 3.The plaintiff also filed a Respondent’s Notice on 12 May 2020 seeking to affirm the Judgment on additional grounds. It has also asked for an alternative order that, in the event that the appeal is allowed, the defendant be given leave to defend on the condition that the defendant is to pay the plaintiff the Bonded Sum (as defined below) (with interest) by way of interim payment. 4.After the end of the hearing, we allowed the appeal and indicated that we would hand down our reasons for judgment and the decision on costs in due course. This is what we do now. B. Background 5.The material facts leading to this appeal were comprehensively summarized at [6] - [18] of the Judgment and [4] - [9] of the Leave Decision. We only need to set out the following which are relevant to this appeal. 6.By way of a General Conditions of Contract of Building and Civil Engineering Works dated 26 September 2015 (“the Contract”), the plaintiff engaged Hsin Chong Construction Company Limited (“the Contractor”) as contractor for its project known as “M+ project”. To secure the due performance of the Contractor, the defendant issued a bond No.H7478 (“the Bond”), up to the sum (“the Bonded Sum”) of HK$297,198,000 on 8 October 2015 in favour of the plaintiff. 7.Clause 2 of the Bond (“Clause 2”) provides as follows:
8.On 17 August 2018, pursuant to clauses 73.1(a) and 74.1 of the Contract, the plaintiff terminated the employment of the Contractor on the basis that it had been in breach of its obligations under the Contract. On the same date, the plaintiff issued and delivered a demand letter to the defendant, asking for payment of the entire Bonded Sum under the Bond (“1st Demand”). 9.The relevant parts of the 1st Demand stated as follows:
10.On 21 and 24 August 2018, the plaintiff delivered to the defendant two further chaser letters demanding the payment of the Bonded Sum. The contents of the chasers are in substance the same as that of the 1st Demand. For the purpose of this judgment, references to the demand made by the 1st Demand should be treated as also references to the demands made by the subsequent chasers. 11.In response, the defendant had by way of correspondence sought various clarifications from the plaintiff, including the proof of the Contractor’s default and whether the demanded Bonded Sum represented the amount of damages or losses said to have already been suffered by the plaintiff. The plaintiff did not provide the requested clarifications as it was of the view that it was unnecessary under Clause 2 for it to prove or particularize both the Contractor’s breach and the losses[1]. The defendant therefore had not paid the demanded sum. 12.In light of the non-compliance with the demands, on 29 August 2018, the plaintiff commenced the present action against the defendant seeking the payment of the Bonded Sum under the Bond. By way of the Defendant’s Summons, the defendant sought to strike out the claim, or alternatively a determination of preliminary issues. 13.On 14 September 2018, the plaintiff took out the summons (“the O14 Summons”) seeking summary judgment against the defendant. C. The Judgment 14.The Judge heard the Defendant’s Summons and the O14 Summons together. 15.The defendant’s principal case under the Defendant’s Summons was that the demand for the Bonded Sum made in the 1st Demand was invalid as it did not comply with the requirements under Clause 2. This was so as (a) the demand had failed to relate or identify the Bonded Sum with the damages said to have been sustained by reason of the Contractor’s default, and (b) in any event, the demanded sum also covered and included future damages, losses, charges, costs or expenses which were not within the ambit of Clause 2. For convenience, we will refer to these questions as the “Construction Issues”. 16.The defendant further alternatively contended that the demands were made fraudulently as the plaintiff could have formed no bona fide opinion that the Contractor was in default of its obligations under the Contract between the two of them, or that by reason of such alleged default the plaintiff had sustained damages etc of or exceeding the Bonded Sum. Again for convenience, we would refer to this issue as the “Fraud Issue”. 17.On these bases, the defendant also opposed the summary judgment application. 18.Under the Construction Issues, there was no dispute that to be valid, a demand made under the Bond must comply with the requirements as provided under Clause 2, and it was (a) a matter of construction of Clause 2 as to what those requirements were, and (b) a matter of construction of the 1st Demand as to whether it complied with those requirements: see [20] - [25] of the Judgment. 19.For the Construction Issues, the Judge concluded that on a proper construction, a demand would be in compliance with Clause 2 if[2]:
See [26] - [30] of the Judgment. 20.The Judge found that the 1st Demand complied with all three requirements. 21.First, he held it was clear that the 1st Demand complied with the 1st Requirement, as it was in writing. See [32] of the Judgment. 22.Second, the 1st Demand also complied with the 2nd Requirement as the plaintiff did say in it that it was of the opinion that the Contractor was or had been in default in respect of various obligations under the Contract. In this respect, it was clear from Clause 2 that the plaintiff in making a demand was not required to prove the Contractor’s default or the amount demanded. See [30] and [33] of the Judgment. 23.As to the 3rd Requirement, as mentioned above, counsel for the defendant[3] contended that it was not fulfilled since (a) the demand had failed to relate or identify the Bonded Sum with the damages said to have been sustained by reason of the Contractor’s default, and (b) in any event, the demanded sum also covered and included future damages, losses, charges, costs or expenses, as expressly stated at paragraph 3 of the 1st Demand, which were not within the ambit of Clause 2. 24.The Judge disagreed with the defendant. He held at [37] - [40] of the Judgment that:
25.The Judge further held that the additional reference to the future damages and losses in paragraph 3 of the 1st Demand, as heavily relied on by the defendant in support of its contentions, was at most redundant and mere surplusage that would not render the 1st Demand invalid. He explained his reasons at [42] as follows:
26.For the above reasons, the Judge concluded that the 1st Demand complied with all the requirements of Clause 2, and was thus valid. 27.The Judge then further rejected the defendant’s contentions made in support of the Fraud Issue for the detailed reasons given at [44] - [60] of the Judgment[4]. 28.Having decided against the defendant in relation to both the Construction Issues and the Fraud Issue, the Judge dismissed the Defendant’s Summons and granted summary judgment in favour of the plaintiff. D. This appeal 29.As stated earlier, the defendant in this appeal only pursues the Demand Grounds, which are as follows:
30.In relation to these, it is also important to note that in this appeal, the parties agree that:
31.Mr Lam SC (leading Mr Cheung) has in gist advanced the following submissions to say why the 1st Demand did not satisfy the 3rd Requirement. 32.First, he submits that paragraph 2 of the 1st Demand only set out the demanded sum being the Bonded Sum, while paragraph 3 independently and separately set out and made reference to the default of the Contractor. There is no reference or link between paragraphs 2 and 3 of the 1st Demand. In the premises, the 1st Demand does not show that the demanded Bonded Sum was related to or was in respect of the Contractor’s default as required in the 3rd Requirement. It is therefore an invalid demand. 33.We have no hesitation in rejecting this contention. 34.There is no dispute that, as a matter of construction, the 1st Demand (in particular paragraphs 2 and 3 thereof) should be read and construed together objectively and in proper context. Once so considered, it is surreal and unrealistic to read paragraphs 2 and 3 of the 1st Demand in the manner as submitted by Mr Lam. When reading the plain words of paragraphs 2 and 3 together and with common sense, the plaintiff was clearly stating in the 1st Demand that it was demanding the Bonded Sum under the Bond as it related to the Contractor’s default under the Contract. 35.Second, Mr Lam submits that given it was expressly stated at paragraph 3 of the 1st Demand that, by reason of the Contractor’s defaults, the plaintiff “have suffered and sustained and will continue to suffer and sustain damages, losses, charges, costs and expenses” (emphasis added), it is obvious that it is the plaintiff’s own position that the demanded Bonded Sum related to damages which the plaintiff regarded as something it would continue to suffer by reason of the Contractor’ default. The Bonded Sum thus included not only damages and losses the plaintiff had already suffered by the time of the demand (which are permitted under Clause 2) but also future damages and losses (which are not within the ambit of Clause 2). 36.We agree with Mr Lam. In our view, the plain and express words of the 3rd paragraph of the 1st Demand objectively and reasonably inform the reader that the Bonded Sum as demanded related to damages and losses that had already been suffered by the plaintiff as well as ones that are yet to be suffered by reason of the Contractor’s default under the Contract. 37.In this respect, it is important to note that Mr Maurellet SC (leading Mr Niehorster) for the plaintiff has fairly and rightly accepted at the hearing that:
38.However, Mr Maurellet has submitted that the court should adopt the Judge’s construction and find that the Bonded Sum as demanded under the 1st Demand related to only damages already suffered by the plaintiff at the time of demand, and that the words “will continue to suffer and sustain” in paragraph 3 are redundant and surplusage. This is so as paragraphs 2 and 3 should be read in the following proper contexts:
39.Once read in these contexts, says Mr Maurellet, it is clear that paragraphs 2 and 3 when considered together meant, as the Judge held at [42] of the Judgment, that the Bonded Sum as demanded reflected the plaintiff’s opinion that (a) this was the amount of damages they already suffered at the time of the demand by reason of the Contractor’s default, (b) the overall damages and losses the plaintiff would suffer as a whole must go beyond the Bonded Sum after final quantification, and hence the reference to the words “will continue to suffer and sustain”. These words are therefore, as held by the Judge, redundant and surplusage for the purpose of the demand. 40.With respect to Mr Maurellet, we are unable to accept his submissions. 41.First, the rather convoluted construction advanced by Mr Maurellet goes against the plain meaning of the words used in paragraph 3. In this respect, as a matter of construction, the court normally expects the drafter to use words chosen to express a meaning and would not lightly find that he intended to add or use redundant and surplusage words. 42.Second, as pointed out by Barma JA at the hearing, the operative words used in Clause 2 are “damages, losses, charges, costs or expenses”. These are words or terms referring to actual or quantified amounts. Hence, it is intended under Clause 2 that when the plaintiff makes a demand, it should be by reference to damages, losses etc which have already been suffered and quantified, but not unquantified sums arising from or by reason of the Contractor’s default. This intention is underlined by the fact, as confirmed by Mr Maurellet and Mr Lam, that under the Bond, the plaintiff can make multiple and subsequent separate demands[5]. 43.Third, there is nothing before the court which would show and support the position that at the time of the 1st Demand, there was an objective context or basis to say that the quantified damages were already well beyond the Bonded Sum. 44.In the premises, we reject Mr Maurellet’s construction as the preferred construction since that would go against the plain and obvious meaning of the words used in paragraph 3 and also the nature of the demand intended to be made under Clause 2. 45.For these reasons, with respect to the Judge, we find him to have erred in his construction and conclusion at [42] of the Judgment. We accept Mr Lam’s submissions that, on a proper construction, the Bonded Sum as demanded under the 1st Demand included future damages and losses which were outside the ambit of Clause 2. Therefore, the 1st Demand was not made in compliance with Clause 2 and was thus invalid. 46.We therefore allowed the appeal on this basis. 47.Given this basis, it is not necessary for us to deal with Mr Lam’s further submissions relating to whether the court should adopt a strict compliance[6] or in substance compliance[7] test or approach in an on-demand bond situation in determining whether the 1st Demand had complied with Clause 2[8]. This is so as both Mr Lam and Mr Maurellet have fairly accepted that the question of whether there was in substance compliance by the 1st Demand simply does not arise if this court concludes (as we have) that, as a matter of construction, the Bonded Sum as demanded included future damages and losses etc. E. Disposition 48.For the above reasons, we allowed the appeal at the hearing and set aside the Judgment. 49.In the Notice of Appeal, the defendant has also asked for the O14 Summons to be dismissed and that the sum already paid by the defendant to the plaintiff to be repaid together with interest at judgment rate from the date of the defendant’s payment to the plaintiff. 50.Mr Lam at the end of the hearing also asked for the Defendant’s Summons to be allowed and that the action be struck out. However, as pointed out by Yuen JA at the hearing, the defendant did not in its Notice of Appeal ask for these orders. Mr Lam therefore asked for leave to amend the Notice of Appeal to include this relief, which was not opposed by Mr Maurellet as he accepted that this should follow if the appeal was allowed. Mr Maurellet also confirmed at the hearing that the defendant would not pursue an alternative order that the defendant be given conditional leave to defend as sought in the Respondent’s Notice. 51.In light of the above, we would therefore also grant leave to the defendant to so amend the Notice of Appeal[9] and further order that (a) the O14 Summons be dismissed, (b) the Defendant’s Summons be allowed and the writ and the statement of claim be struck out, and (c) the sum already paid by the defendant to the plaintiff pursuant to the Judgment to be repaid together with interest at judgment rate from the date of the defendant’s payment to the plaintiff. 52.As to costs, Mr Maurellet accepts that costs of the appeal should follow the event. As to the costs below, he submits that, as reflected in the Judgment, up to 20 - 30% of the time had been spent at the hearing before the Judge on the Fraud Issue raised by the defendant, which the Judge had rejected and the defendant has abandoned on appeal. In the premises, counsel says the defendant should not be entitled to all the costs before the Judge. 53.We agree with Mr Maurellet. We therefore order that costs of this appeal (with certificate for two counsel) and 80% of the costs below be to the defendant, to be taxed if not agreed.
Mr Douglas Lam SC and Mr Tommy Cheung, instructed by Tanner De Witt, for the appellant (defendant) Mr Jose Maurellet SC and Mr James Niehorster, instructed by Bryan Cave Leighton Paisner LLP, for the respondent (plaintiff) [1] See Affidavit of Richard John Wilmot, paragraphs 13 - 21. [2] The Judge considered and applied Nishimatsu Construction Co Ltd v AHA Co (unreported, HCA 10416/1999, 20 September 1999) at [6], [7], [17] - [18] per Recorder Kotewall SC. [3] Mr Westbrook SC. [4] As mentioned above, as the defendant is no longer challenging in this appeal this part of the Judge’s reasons in dismissing the Defendant’s Summons and granting summary judgment, it is therefore not necessary for this court to look into this issue any more. [5] We were further informed by the parties at the hearing that, in any event, the plaintiff had indeed issued new demands. [6] As supported for example by Simic v New South Wales Land and Housing Corp [2016] HCA 47 at [97] - [100]. [7] As appears to be supported by IE Contractors Ltd v Lloyd’s Bank Plc and Rafidian Bank [1990] 2 Lloyd’s 496 at 500, lines (1) - (2), which authority is adopted by the Judge. [8] As mentioned above, the Judge appears to have accepted and adopted an in substance compliance test at [39] - [40] of the Judgment. [9] The defendant therefore should lodge with the court an Amended Notice of Appeal pursuant to the leave granted. |
Cases cited in this judgment
Further hearings and rulings under CACV 82/2020