Tdc Capital Solution Ltd v. Wong Sung King Dorothy and Others
Read the full judgment text of HCA 1598/2022 on BabelCite. This High Court CFI judgment was delivered on 19 March 2025.
1. This is a consequential hearing following my decision dated 22 May 2024 in this action (“ Decision ”). The abbreviations used in the Decision will continue to be used below.
Cites 3 cases
|
HCA 1598/2022 [2025] HKCFI 954 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO. 1598 OF 2022 ____________________
____________________
______________ D E C I S I O N ______________ INTRODUCTION 1.This is a consequential hearing following my decision dated 22 May 2024 in this action (“Decision”). The abbreviations used in the Decision will continue to be used below. 2.By the Decision, I struck out P’s SOC but gave it liberty to lodge and serve a Draft ASOC to address certain defects in its SOC. 3.P has subsequently lodged and served its Draft ASOC pursuant to my orders. However, Ds contend that P’s claims cannot be salvaged by the amendments proposed in the Draft ASOC. 4.The parties have therefore come before me for determination as to whether the proposed amendments ought to be allowed. BACKGROUND 5.The background to the underlying dispute has been set out in §§2 – 22 of the Decision and will not be repeated in full here. 6.In gist, the dispute arose out of the written Service Agreement between the Original Intermediaries and Ds pursuant to which the former agreed to assist D1 to D3 in selling the shares in D4, D5 and others to an external buyer in return for the Service Fee. The Service Agreement was later varied by the Supplemental Service Agreement whereby P assumed the rights and obligations of the Original Intermediaries. 7.For present purposes, the material terms in the Service Agreement are found in Clauses 1.1, 1.1.2 and 1.1.3. As mentioned in §8 of the Decision, these clauses provide as follows:
8.However, the SPAs that were eventually entered into between Ds and the buyers (ie the Tahoe Companies) do not contain some of the key terms specified in the Conditions. Despite having made a number of part payments for the Service Fee, Ds contend in the context of their strike out application that P is not entitled to payment of the balance of the Service Fee since there is a mismatch between the Conditions and performance under the Service Agreement and that the payment obligation had therefore not been triggered. As such, the SOC discloses no reasonable cause of action and ought to be struck out. THE DECISION 9.On 22 May 2024, I handed down my Decision on Ds’ strike out application. 10.As discussed in §§26 – 32 of the Decision, Ds submitted at the substantive strike out hearing on 8 January 2024, and I agreed, that on the basis of the claim as then pleaded in the SOC, there was a mismatch of the pleaded performance and the payment conditions. There was also no explanation as to why the terms eventually found in the SPAs (which are materially different from the Conditions) nevertheless can be construed as having the effect of the Conditions. 11.Importantly for present purposes, Mr Chang SC, Counsel for P who appeared before me at the last hearing on 8 January 2024, advanced the following construction argument (ie P’s Construction) in opposition to Ds’ strike out application (as recorded in §33 of the Decision):
12.Having considered P’s Construction carefully, I came to the view that I could not dismiss it as unarguable. However, since P’s Construction had not been pleaded in the SOC but only in the Reply filed on 22 November 2023, I struck out the SOC but gave P an opportunity to amend its SOC to rectify its pleading defect (see Decision §§34 – 35, 41 – 47). In particular, I specifically found in §§43 – 44 of the Decision that P’s Construction is not unarguable or bound to fail for the following reasons:
13.It should also be mentioned that at the substantive strike out hearing on 8 January 2024, P advanced the Waiver Contention and the Estoppel Contention as an alternative to P’s Construction in opposition to Ds’ strike out application. As recorded in §36 of the Decision, by those contentions, P submitted that even if the terms of the SPAs did not satisfy Clauses 1.1.2 – 1.1.3 of the Service Agreement:
14.I ruled that as the Waiver Contention and the Estoppel Contention had not been pleaded in the SOC but only in the Reply, they could not salvage a defective SOC where complete causes of action had not been pleaded. However, given that I found that P’s claims were not bound to fail on its contractual interpretation contention, I did not have to rule on whether the Waiver Contention and the Estoppel Contention were bound to fail (see Decision §§37 – 40, 45). THE DRAFT ASOC 15.In the Draft ASOC lodged and served after the Decision, P has introduced a number of new paragraphs to Section C of the pleading entitled “Performance of the Relevant Services” to further elaborate on how and why P has fully performed and discharged its obligations under the Service Agreement. 16.It is evident from the Draft ASOC that the pleas at the new §28A (“Construction Plea”), §29A (“Waiver Plea”) and §29B (“Estoppel Plea”) substantially mirror the pleas of P’s Construction, the Waiver Contention and the Estoppel Contention respectively as pleaded in P’s Reply. 17.Ds now oppose these amendments proposed by P on the basis that they are bound to fail and/or are time-barred by s35(3) of the Limitation Ordinance (Cap 347). In respect of the Construction Plea, Ds also contend that it is not sufficiently particularised. THE CONSTRUCTION PLEA 18.In relation to the Construction Plea, I do not agree that it lacks particulars. 19.Paragraph 28A of the Draft ASOC begins with a clear statement that on the true construction of the Service Agreement set in its proper context and background, the Original Intermediaries and P have fully discharged their obligations under the Service Agreement, and strict and legal compliance with the Conditions was not required for them to be “satisfied” under Clause 1.1 thereof. 20.Paragraph 28A.1 then goes on to plead the context and background relied upon, including, inter alia, that:
21.In relation to Ds’ criticism that P has not pleaded what amounted to the satisfaction of the Conditions, P has sufficiently pleaded in §28A.2 of the Draft ASOC that the Original Intermediaries and P procured and obtained for Ds the 18/11/16 SPA (whether by itself or subsequently varied) pursuant to which a contractual framework was set up with the intended purchaser to give effect to and satisfy the Conditions. 22.Indeed, in relation to the mismatch between P’s performance and the Conditions, P has provided particulars in §28A.2(a) and (b) of the Draft ASOC of the manner in which the various SPAs created a contractual framework to cater for the contingencies and to thereby give effect to and satisfy the Conditions. 23.I therefore agree with P’s submission that a party reading the Construction Plea would know the construction of Clause 1.1 of the Service Agreement which it contends, the factual basis of such construction and its case on how the Conditions were satisfied even though the Conditions were not strictly complied with. 24.Indeed, as I noted in §16 above, this Construction Plea in §28A of the Draft ASOC mirrors the plea of P’s Construction in the Reply. In other words, P has merely transposed the relevant plea in the Reply to the Draft ASOC. In coming to my Decision that P’s Construction could not be dismissed as unarguable, I necessarily had no difficulty in understanding the plea in the Reply which now forms the new §28A of the Draft ASOC. 25.As regards Ds’ contention that the Construction Plea is bound to fail, this ought to be rejected also on the basis that I had already ruled in the Decision that P’s Construction was not bound to fail. The Construction Plea in §28A of the Draft ASOC merely pleads out P’s Construction as found in the Reply. There are no new changes to the plea which will cause me to come to a different conclusion from the one I reached in the Decision. 26.As regards Ds’ time-bar contention, the relevant questions for present purposes are whether the proposed amendments seek to add or substitute a new cause of action and if so, whether the new cause of action arises out of the same or substantially the same facts as are already in issue in the existing claim (see Shenzhen Futaihong Precision Industry Co ltd v BYD Company Ltd [2019] 2 HKC 175 at §74). 27.In the context of a statement of claim that has been struck out because it is defectively pleaded and the plaintiff is given an opportunity to file a fresh statement of claim, P has drawn my attention to the decision of Burrell J in Li Tin Sang v Poon Bun Chak (unrep, HCA 9296/2000, 11 Apr 2003) and in particular §§8 – 9 as follows:
28.Burrell’s decision was upheld by the Court of Appeal (unrep, CACV 119/2003, 12 Nov 2003) where Rogers VP held at §13 that:
29.In the present case, it is clear that the new amendments in the Draft ASOC do not raise any new cause of action. The cause of action remains one of breach of contract. The Construction Plea is corrective and merely pleads further facts upon which P’s action is based. There is therefore no merit to Ds’ time-bar contention. 30.In the circumstances, I allow the amendments proposed by P in relation to the Construction Plea. THE WAIVER PLEA AND THE ESTOPPEL PLEA 31.In respect of the Waiver Plea and the Estoppel Plea, the primary position of P is that they are not causes of action and should properly be pleaded in the Reply. However, since I ruled in the Decision that P’s Construction had not been properly pleaded in the SOC and that the pleas of waiver/estoppel in the Reply could not be used to salvage a defectively pleaded SOC, Mr Dawes SC (Counsel for P) has helpfully informed me during the hearing that P has inserted the Waiver Plea and the Estoppel Plea in the Draft ASOC out of an abundance of caution even if P does not necessarily need them in the ASOC. 32.In view of my ruling above allowing P’s proposed amendments in respect of the Construction Plea and Mr Dawes’ indication, it is not necessary for me to specifically rule on Ds’ opposition to the Waiver Plea and the Estoppel Plea that they are bound to fail and/or are time-barred. DISPOSITION 33.For the above reasons, I allow all the amendments proposed by P in the Draft ASOC save and except the Waiver Plea at §29A and the Estoppel Plea at §29B. 34.I therefore make the following orders:
35.As for costs, I do not see any reason to depart from the usual order that the costs of and occasioned by the amendment of the SOC be to Ds, and I so order. 36.As for the costs of the hearing (including all preparation and incidental costs in dealing with Ds’ grounds of opposition), P has asked for such costs with certificate for 2 counsel. In this regard, P has submitted a statement of costs for summary assessment totalling HK$971,960. In reply, Ds have lodged written submissions contending that even if I were to allow P’s amendments, P should only be awarded costs to the tune of HK$477,320. Ds further submit that if P is successful only on part of its amendments, the costs of the hearing should be further apportioned. 37.In view of my ruling above that I have only allowed part of P’s amendments, I will only allow 50% of P’s costs of the hearing with certificate for 2 counsel. Having carefully considered Ds’ costs submissions and adopting a broad brush approach, I order Ds to pay P the costs of the hearing on 20 December 2024 summarily assessed at HK$390,000. 38.I thank all Counsel for their assistance.
Mr Victor Dawes SC and Mr Cedric Yeung, instructed by DLA Piper Hong Kong, for the Plaintiff. Mr Bernard Man SC and Mr Jonathan Fung, instructed by Gallant, for the 1st to 5th Defendants. |
Cases cited in this judgment
Further hearings and rulings under HCA 1598/2022