A v. B
Read the full judgment text of HCCT 125/2024 on BabelCite. This High Court CFI judgment was delivered on 23 December 2025 before Deputy High Court Judge Jonathan Wong.
Construction law — Arbitration — Stay of proceedings — Costs — Indemnity costs — Arbitration clause requiring completion or termination and consent before arbitration — Plaintiff prematurely commenced court proceedings — Defendant successfully obtained stay in favour of arbitration — Court orders indemnity costs against Plaintiff. The Plaintiff commenced proceedings against Defendant contrary to a clear arbitration agreement under subcontracts linked to a construction project at Hong Kong International Airport. The arbitration clause (GC 18) required arbitration only after completion or termination of the main works and written consent of the Defendant. The Defendant applied for a stay of court proceedings in favour of arbitration, which was granted shortly before the substantive hearing. The Plaintiff initially resisted the stay application and sought to litigate prematurely claiming the clause was null and void. The court held that the arbitration agreement was binding, found no unreasonable conduct by the Defendant, and rejected Plaintiff’s hardship argument as insufficient to rewrite the contract. The court relied on established authorities endorsing indemnity costs for unsuccessful challenges to arbitration agreements to further civil justice reform objectives. Consequently, costs of the stay summons were awarded on an indemnity basis against the Plaintiff, including reserved costs and costs of submissions.
Legal issues: Costs order on stay application in favour of arbitration
Outcome: Plaintiff ordered to pay costs of the Summons to Defendant on an indemnity basis.
Cites 3 cases
|
HCCT 125/2024 [2025] HKCFI 6367 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO 125 OF 2024 _____________
_____________
_______________ DECISION ON COSTS _______________ 1.Introduction 1.1The Plaintiff (“P”) commenced these proceedings against the Defendant (“D”) on 17 October 2024. By a summons dated 4 February 2025 (“Summons”), D applied to stay the present proceedings in favour of arbitration, which application was eventually acceded to by P and an order was made to that effect on 25 August 2025 shortly before the substantive hearing of the Summons on 1 September 2025. 1.2However, the parties were unable to agree on the issue of costs. Initially, the position advocated by P was that the costs of the action (including the costs of the Summons) be in the cause of the intended arbitration proceedings. The foregoing position is no longer maintained by P. Whilst P no longer disputes that it should pay costs to D, it says that the costs should not be taxed on an indemnity basis but should be taxed instead on a party-and-party basis. 1.3Conversely, D seeks costs of the Summons (but does not seek any costs in relation to the action) on an indemnity basis. 1.4The outstanding issue of costs was ordered to be dealt with on the papers. I have since received helpful submissions from Mr Vincent Li for P and Mr Clavin Cheuk for D. This is my decision on the issue of costs. 2.The contractual arrangement between P and D 2.1D was at all material times the main contractor for Contract X (“Contract X”) for the construction of the Third Runway Concourse at the Hong Kong International Airport (“Main Works”). 2.2D and P entered into 2 subcontracts (“Subcontracts”) on or about 25 January 2022 and a supplemental agreement on 27 June 2023 (“SA”). 2.3There is no dispute between the parties that Clause 18 of the General Conditions of the Subcontracts, as amended by the Special Conditions of the Subcontracts (“GC 18”), is a dispute resolution clause mandating the parties to refer any disputes in connection of the Subcontracts to arbitration. In particular, and relevant for present purposes, GC 18(4) provides as follows:
3.Commencement of the present proceedings 3.1By inter alia a letter dated 30 December 2023, D (on P’s case) wrongfully determined P’s employment. P says that it is entitled to claim for outstanding sums of over HK$107 million and damages for breach of the Subcontracts and the SA. 3.2Since the purported determination of P’s employment under the Subcontracts, P had been requesting for settlement of the Subcontracts’ final accounts. On 19 June 2024, P’s solicitors proposed mediation, which proposal was rejected by D’s solicitors on 3 July 2024. 3.3As the proposal to mediate was not accepted, by a letter dated 3 October 2024 (“3/10/24 Letter”), P’s solicitors wrote to D’s solicitors seeking D’s consent to commence arbitration. 3.4By a letter dated 10 October 2024 (“10/10/24 Letter”), D’s solicitors replied to the 3/10/24 Letter, in which the merits of Ps’ allegations were criticized. Although not stated expressly, it is plain that no consent to commence arbitration was forthcoming from D. 3.5Feeling that no further alternatives were available and in an attempt to ease its cashflow, P commenced the present proceedings on 17 October 2024. The Statement of Claim was only filed on 7 January 2025. 3.6In a letter from D’s solicitors dated 15 January 2025 to P’s solicitors (“15/1/25 Letter”), the grounds for staying these proceedings were set out in, inter alia, the following terms:
3.7As no agreement was forthcoming from P, D took out the Summons on 4 February 2025. P chose to contest the Summons and it was only on 31 July 2025 that P started to negotiate with D to dispose of the Summons by consent. 4.P’s Submissions 4.1P asks the court to take the following matters into account on the issue of costs. 4.2First, it is said that the terms of GC 18 gave rise to financial hardship on the part of P, and P’s claim had been “locked up” since December 2023 when D issued the purported notice of termination. 4.3Secondly, it was only when D took out the Summons on 4 February 2025 that an undertaking was proffered that D would give consent to commence arbitration after completion or termination of the Contract X. 4.4Thirdly, given the factual matrix, P (it is said) reasonably took the position that GC 18 was null and void, inoperative and incapable of being performed. In particular, P relies on D’s evidence that the Main Works would only reach completion in about mid-2027, which means that the disputes between P and D will not be adjudicated upon for some time still. 4.5Generally, Mr Li says that, under RHC Order 62, rule 5(1)(e), I should take D’s conduct into account on the issue of costs. He submits that D was unreasonable in refusing mediation in June 2024, and was also evasive, if not oppressive, in failing to respond to P’s request for consent to commence arbitration before these proceedings were instituted. 5.The applicable principles 5.1Chimbusco International Petroleum (Singapore) Pte Ltd v Fully best Trading Limited [2016] 1 HKLRD 582 is an authority for the proposition that the practice is to order indemnity costs in proceedings arising out of in connection with arbitral proceeding:
5.2In Chimbusco, indemnity costs were ordered against the plaintiff as the defendant was successful in obtaining a stay of the court proceedings in favour of arbitration. 5.3As regards the potential “harshness” of an arbitration clause on terms similar to those of GC 18 on a party’s financial situation, I refer to Kinli Civil Engineering Ltd v Geotech Engineering Ltd [2021] HKCFI 2503. The relevant arbitration clause considered in Kinli is as follows (Decision §3):
5.4G was the main contractor and K was G’s subcontractor. At Kinli §§30-31, Mimmie Chan J observed as follows:
6.Analysis 6.1I do not agree with Mr Li that the factors set out at section 4 above assist P, for the following reasons. 6.2First, although there are differences between GC 18 and the arbitration clause considered in Kinli, I am of the view that the observations made at Kinli §31 (the underlined passage above) remain apposite. It is not the function of the court to rewrite the parties’ bargain because of the professed harshness asserted by P. 6.3Secondly, and related to the above, P’s initial position that GC 18 was null and void, inoperative and incapable of being performed can only be regarded as overly-ambitious as an argument which, if pursued, would have defeated D’s application for stay. The foregoing is especially true when the onus of D is only to establish a prima facie case of the existence of an arbitration agreement (Kinli §§5-7 and 32). 6.4Thirdly, I do not regard there is any element of unreasonable in the D’s conduct. By virtue of the terms of GC 18, D was plainly entitled to regard P’s attempt to have its claim litigated as premature. It is pertinent to note that the conditions to be satisfied under GC 18 for arbitration to be commenced are cumulative (ie, relevantly (1) Completion or alleged completion of the Main Works or the termination of the Contract X and (2) written consent of D has been given therefor). Given that P accepts that the Main Works will not be completed until mid-2027, it seems to me clear that the first condition has not been satisfied. As such, I do not consider there is anything in P’s complaint that no undertaking to give consent was forthcoming from D until the Summons was taken out. Unless and until the first condition of GC 18 was satisfied, there was simply no utility for consent to be given. Conversely, were it suggested that D should give consent for arbitration to be commenced despite the first condition of GC 18 not having been satisfied, I do not see how it can be said that D should voluntarily depart from the contractual bargain reached between the parties. 6.5Fourthly, as pointed out by Mr Cheuk, D’s position was clearly set out in the 15/1/25 Letter but P decided to contest the Summons fully (including the filing of evidence in opposition) until shortly before the substantive hearing in September 2025. 6.6In my view, a proper exercise of the court’s discretion is to accede to the costs order pursued by D. 7.Conclusion 7.1For the above reasons, I accede to the order proposed at D’s submissions dated 8 September 2025 §2, namely the costs of and occasioned by the Summons, including all costs reserved and the costs of the submissions lodged for the purpose of the costs issue, be paid by P to D forthwith on an indemnity basis, to be taxed if not agreed.
Mr Vincent LI, instructed by Messrs. Zebra H Y Kwan & Partners, for the Plaintiff Mr Calvin CHEUK, instructed by Messrs. Johnson Stokes & Master, for the Defendant | ||||||||||||||||||||
Cases cited in this judgment