Read the full judgment text of HCA 2141/2020 on BabelCite. This High Court CFI judgment was delivered on 26 August 2021.
1. These proceedings were instituted by the Plaintiff (“ K ”) against the Defendant (“ G ”) for $4,055,696.83, as the sum claimed to be owing from G and due under a written contract dated 15 September 2016 (“ Contract ”). K is the subcontractor of G, for works to be carried out on a project for site formation, drainage and pile cap works (“ Works ”) in relation to a public housing development project at Shek Kip Mei Estate Phase 6 (“ Project ”). The Housing Authority is the employer, and Shui On
Cited by 9 cases · Cites 3 cases