Wenden Engineering Services Co. Ltd. v. Lee Shing Yue Construction Co. Ltd.
Read the full judgment text of HCCT 90/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 13 December 2000 before Hon Burrell J in Chambers.
Construction and Arbitration Proceedings — Enforcement of Tomlin Order — Interest on Sums Awarded — Whether claim for interest must be pleaded in amended motion — Discretionary power under High Court Ordinance Cap.4 s.48 to grant interest — Court's inherent power to vary orders — Whether court functus officio after approving draft order — Appropriate rate of interest — Costs. The plaintiff sought to enforce a Tomlin order and claimed approximately HK$4.4 million awarded, and further sought interest on these sums despite interest not being pleaded in the amended motion or mentioned at hearing. The court held that there was discretionary power under section 48 of the High Court Ordinance to grant interest and that failure to plead interest in the motion was not fatal. The court accepted that the claim for interest was always intended but inadvertently omitted at hearing. It found that the defendant had profited from retaining the money and that prime plus 1% per annum was the appropriate interest rate. The court rejected the defendant's submission that the court was functus officio after approving the draft order without reference to interest, holding that the order could properly be varied to include interest consistent with the court’s original intention. Costs of the summons were awarded to the plaintiff. The court thus granted the plaintiff’s application for interest from 5 April 2000 to 24 October 2000 at prime plus 1% per annum, with consequential costs orders.
Legal issues: Entitlement to interest on sums awarded under Tomlin order · Appropriate interest rate · Whether court is functus officio after approving draft order
Outcome: The plaintiff’s application for interest on sums awarded is granted; the rate applied is prime plus 1% per annum from 5 April 2000 to 24 October 2000; costs of the summons are awarded to the plaintiff.
Cites 1 case
|
HCCT000090A/1999 HCCT 90/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS -------------
------------- Coram: Hon Burrell J in Chambers Date of Hearing: 11 December 2000 Date of Addendum: 13 December 2000 ------------------------------------------------------- ADDENDUM TO DECISION ------------------------------------------------------- 1. On 20 November 2000, the court handed down a decision in relation to the plaintiff's application to enforce the terms of a Tomlin order. In that application, the plaintiff had claimed approximately $5.2 million under a settlement in which part of the litigation between the parties had been settled. By the court's decision, the plaintiff was awarded approximately $4.4 million. 2. The issue now before the court concerns the plaintiff's entitlement to interest on the sum awarded. The application for enforcement of the Tomlin order was brought by way of an amended motion. That amended motion made no reference to the question of interest. When the parties appeared in court, the question of interest was not canvassed. When the decision was handed down, interest was not dealt with and finally, when the order was drawn up and approved, there was no reference to interest. The order has not yet been sealed. On the same day that the draft order was submitted to the court, the plaintiff's solicitors wrote to the defendant's solicitors stating its entitlement to interest. Further exchanges of correspondence were unable to resolve the matter and so the plaintiff has taken out this summons which seeks an order that the sums ordered to be paid in the 20 November decision shall carry interest. 3. The cumulative effect of the following factors have persuaded me that I should grant the application sought by the plaintiff.
The appropriate rate 4. Mr Au submits that as the defendant's actual benefit by way of interest was only, in fact, about 6%, the usual rate of prime plus 1% should not be awarded. I do not agree. What the defendant did with the money is not a relevant consideration. The fact is that the plaintiff was deprived of its use. Prime plus 1% is the appropriate rate. 5. The dates from which interest shall run are those which appear in the draft order submitted to the court. Costs 6. The summons before the court today seeks an order in relation to the costs reserved order made on a previous occasion. Happily the parties have agreed that matter and it is also agreed that I need not deal with it in this decision, as a result of the agreement. 7. As to the costs of today, I make a final order that they be to the plaintiff. Order 8. There will be an order in the terms of the plaintiff's draft order as submitted, dated 11 December 2000. In paragraph 1, the appropriate dates are 5 April 2000 to 24 October 2000. In paragraph 4, the rate will be prime plus 1% per annum.
Representation: Mr Anthony K.K. Chan, instructed by Messrs Siao Wen & Leung, for the Plaintiff Mr Tony Au of Messrs Robin Bridge & John Liu, for the Defendant |
Cases cited in this judgment
Further hearings and rulings under HCCT 90/1999