Wenden Engineering Services Co. Ltd. v. Lee Shing Yue Construction Co. Ltd.
Read the full judgment text of HCCT 90/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 20 November 2000 before Hon Burrell J in Chambers.
Construction and Arbitration Proceedings — Enforcement of settlement under Tomlin order — Contract interpretation — Whether defendant may withhold payments under the settlement terms — Mandatory payment clauses — Security money release — Set-off and reimbursement provisions — Disputed deductions for insurance premiums — No statutory or case law cited — Plaintiff entitled to unpaid interim payments and release of security money — Disputed insurance deduction deferred to final account — Costs awarded to plaintiff. The plaintiff sought enforcement of a consent order dated 18 November 1999 concerning payments for ASD subcontract electrical works following settlement of protracted litigation. The defendant withheld payments citing alleged breaches and set-offs. The Court held the Tomlin order imposed clear, unconditional obligations to pay and release security money, rejecting the defendant’s withholding rights beyond agreed terms. The defendant’s claim for set-off for alleged overpayments and security non-compliance failed. Issues relating to insurance premium deductions, mostly pre-dating the order, were left for resolution at final accounting. The defendant was ordered to pay outstanding sums totalling approximately HK$4.4 million plus costs to the plaintiff. No ruling was made on disputed insurance premium deductions at this stage.
Legal issues: Interpretation of the Tomlin order regarding withholding payments · Entitlement to release of security money under clause 6(b) · Calculation and withholding of deductions for insurance premiums
Outcome: The defendant was ordered to pay the plaintiff outstanding interim payments and release security money, with no order made on disputed insurance deductions. Costs were awarded to the plaintiff.
Cites 1 case
|
HCCT000090/1999 HCCT 90/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO.90 OF 1999 -------------
------------- Coram: Hon Burrell J in Chambers Date of Hearing: 15 November 2000 Date of Decision: 20 November 2000 ------------------------ D E C I S I O N ------------------------ 1. This is an application by the plaintiff to enforce the terms of a settlement contained in a schedule to a consent order dated 18 November 1999 ("the Tomlin order"). By the Tomlin order, a significant part of on-going litigation between the parties, who are a contractor (defendant) and sub-contractor (plaintiff), for ASD maintenance works were settled. 2. The plaintiff claims it should have been paid the following under the settlement (none of which has been paid) :
3. The defendant concedes that it has received the ASD payments but argues that the Tomlin order does not preclude its right to set off monies which may be due to it and has accordingly withheld the monies to safeguard its position. In short, the defence submits that :
4. Whether or not these submissions are merited on the facts, the plaintiff submits that they fall outside the terms of the Tomlin order and the court should not and need not consider the factual merits. But further it submits that if the court does consider the facts upon which the defendant has based its entitlement to withhold money, the court should still find in the plaintiff's favour. There are therefore two issues, firstly, does the Tomlin order clearly preclude the withholding of money by the defendant and secondly, on the facts, has the defence shown it is entitled to withhold payments? 5. I have decided, for the reasons which follow, that for items (i) and (ii) above, one need look no further than the Tomlin order itself. I will nonetheless refer briefly to the evidence which I find also supports the plaintiff's case. Item (iii) is a separate issue with which I deal at the conclusion of this judgment. Interpretation of the Tomlin order 6. The Tomlin order constitutes a separate and binding contract of settlement between the parties. It is for the court to determine its meaning and effect. I find there to be no ambiguity in the words used. Its meaning is clear. It imposes obligations as to payment on the defendant which it has not discharged. The obligations are not conditional on other matters. I now deal briefly with each of the clauses referred to in argument. The defence rely primarily on clause 4, and to a lesser extent clause 12. The plaintiff relies on, effectively, the whole document. 1. Clause 4 :
7. This imposes an obligation on the plaintiff. The defendant argues that if the plaintiff is in default of this clause, or even if there is a mere allegation of default, then the defendant's obligations contained in the subsequent clauses need not be honoured. It may simply not pay the plaintiff to safeguard the possibility of future loss arising from the plaintiff's breach of clause 4. I reject this contention. If, as the work progresses, the plaintiff is in breach of clause 4, they are liable to be sued. 2. Clause 5 :
8. No conditions are attached to these terms. They are mandatory and unambiguous. The words "back to back" have been emphasized by quotation marks and it also imposes a burden on the defendant to provide evidence that the amount handed over is the same as the amount received. 3. Clauses 6 and 7 :
9. The amount of security (as per clause 6(b)) as at 31 July 2000 was still $2,000,000.00. There had been no cause to utilize any of it. The sum due to be released was therefore $1 million. Nothing was in fact released. 10. The defendant has advanced a technical argument. It says, correctly, that the $2 million security in fact came to the defendant by virtue of clause 7, not clause 6. That is, the plaintiff did not actually take out a $2 million bond, rather it relied on clause 7 and permitted the defendant to retain a sum of $2 million from an earlier interim payment. The defendant submits that as clause 6(a) was not followed, then clause 6(b) need not be complied with. I reject this submission. Regardless of whether the machinery for providing security used was clause 6 or clause 7, the result is the same. The defendant got its security, none was used. $1 million should have been released on 31 July 2000. 4. Clauses 8, 9 and 10 11. All these clauses provide for the "reimbursement" of monies to the defendant from the plaintiff in certain circumstances. They all commence with the words "In the event that ...." and conclude "the Plaintiff shall reimburse ....". The individual events catered for by each clause are not material. In clauses 8 and 9, there is no mention of any right to set off for alleged over-payments. The provision clearly states that if there are any over-payments, they shall be re-imbursed. That is the simple and straightforward machinery. Clause 10 does mention the right to set off. However the way in which it is mentioned supports the plaintiff's case. It specifically states that the right to set off is only triggered should the plaintiff fail to re-imburse :
5. Clause 12
12. This clause excludes the right of set-off in "any other dealings". The defendant's submission is that because this clause excludes the right to set off in other dealings, then by implication there is a right to set off in this dealing. I find there to be no merit in this submission. The facts 13. There are two main areas of contention. I do not propose to deal with them in any detail because I have already found the defendant liable to pay items (i) and (ii) in full because of the clear meaning and effect of the Tomlin order. The two issues are :
Item (iii) 14. This sum of $801,515.13 relates to a sum deducted by the defendant, being their calculation of the plaintiff's contribution towards insurance premiums. There is no doubt that the plaintiff is liable to pay part of the insurance premium. The issue is how much it should pay. There is a factual dispute as to how the sum should be calculated. Most of the deductions were made pre Tomlin order, one is post Tomlin. In spite of my rulings in relation to the interpretation of the Tomlin order, I think the preferable approach to this separate amount is to make no ruling in respect of it at this stage. As the timings of the deductions straddle the Tomlin order and the majority are beforehand, the issue as to methodology of calculation should be dealt with only once and is therefore best left until the final account. I need say no more than that the plaintiff's submission that the amount of the deduction has been somewhat inflated has some force. Order
Representation: Mr Anthony K.K. Chan, instructed by Messrs Siao Wen & Leung, for the Plaintiff Mr Richard Leung, instructed by Messrs Robin Bridge & John Liu, for the Defendant |
Cases cited in this judgment
Further hearings and rulings under HCCT 90/1999