Comtech Engineering & Consultant Co Ltd v. Thorn Security (Hong Kong) Ltd
Read the full judgment text of HCCT 53/1999 and HCA 7968/1999 on BabelCite. This 高等法院原訟法庭 judgment was delivered on 30 April 2003 before Hon Ma J in Court.
Construction dispute — fire services installation sub-sub-contract — termination of original sub-sub-contractor WEC by Thorn — engagement of Comtech to take over work — existence and terms of contract — contract formed on terms of PO 3164 — Comtech's breach by delay and defective work — Thorn took over wet work due to delays — claims for damages for additional materials, labour, and management costs — quantum assessed by court — Comtech's quantum meruit claim rejected due to contract existence — loss of profit claims by Thorn rejected for lack of evidence — judgment for Thorn for $8.7 million — procedural history of consolidation and trial before Hon Ma J. The court found contemporaneous documents, correspondence and conduct demonstrated a binding contract based on purchase order 3164. Comtech's arguments of absence of contract or cost-plus basis rejected. Thorn was not in breach by withholding payment, given Comtech's breaches. Delay and defective work by Comtech justified Thorn's counterclaim. Quantum was carefully assessed with expert evidence and adjusted conservatively. This case highlights principles in construction contract formation, breach, and damages assessment.
Legal issues: Existence and terms of contract between Comtech and Thorn · Thorn's breach of contract · Comtech's breach of contract · Quantum of damages due to Thorn
Outcome: Judgment for Thorn in the sum of $8,713,949.51; Comtech's claim reduced to $3,606,609.56 which is less than Thorn's counterclaim.
|
HCCT000053A/1999 HCCT 53/1999 and HCA 7968/1999 HCCT 53/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 53 OF 1999 ______________
______________ HCA 7968/1999 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FINAL INSTANCE ACTION NO. 7968 OF 1999 ______________
______________ Coram: Hon Ma J in Court Dates of Hearing: 15-18, 21-25 & 31 October 2002 Date of Judgment: 30 April 2003 _______________ J U D G M E N T _______________ Background 1.The relevant events in this action took place between 1997 and 1999, with the main events occurring in 1998. The Plaintiff's claims and the Defendant's Counterclaim are both concerned with the fire services installation work that was carried out in a Sandwich Class housing development at a site located at Lai Kong Street, Kwai Chung, New Territories ("the Site"). This development involved the construction of two 30-storey and four 32-storey residential blocks and a two-level car park. 2.The employer of the project was the Hong Kong Housing Society ("HKHS"). The main contractor was Hip Hing Construction Company Limited ("Hip Hing"). The Defendant in these consolidated proceedings, Thorn Security (HK) Limited ("Thorn") was the nominated sub-contractor for the fire services installation work. Such work encompassed, broadly, what are known as "wet" and "dry" work. Wet work included, for example, the installation of sprinklers and any plumbing work. Dry work included electrical installations (such as fire detection and alarm systems). 3.In turn, Thorn originally sub-sub-contracted on a back to back basis the whole of the fire services installation work to a company called Wise Engineering Company Limited ("WEC") under a purchase order numbered 2376 dated 15 August 1997. The purchase order before the court was not signed by WEC but one of the witnesses, Mr Yung Chor Hei ("C.H. Yung"), the sales director of Thorn, said in evidence that it was signed by WEC at some stage. Nothing turns on this because it is clear that Thorn did contract with WEC. The stated value of this purchase order was $7,785,122.00. 4.On its face, PO No. 2376 stated that WEC was to provide labour and materials to carry out the specified fire services installation work. Documents containing detailed terms were, however, annexed to this purchase order. Among the documents was one headed "Domestic Sub-Sub-Contract for Fire Services Installation of Residential Development KCTL 458 Lai Kong Street, N.T." ("the Domestic Sub-Sub-Contract"). This document stated the scope of works to be carried out by WEC as follows:-
5.It will thus be seen that one of the duties under its sub-sub-contract with Thorn was that WEC would be responsible for supervising the fire services installation work. I shall call this part of its task "contract administration" as this is the term that was used at trial. In this regard, it was further stated in clause 3.3 of the Domestic Sub-Sub-Contract that WEC was to provide sufficient full-time supervisors on site for the overall supervision of the works. 6.Problems developed over WEC's performance of the sub-sub-contract. This started about October or November 1997. Apparently, WEC was experiencing difficulties in getting the requisite labour to the Site, fell behind in the submission of drawings for the approval of materials and also had difficulties in maintaining adequate supervision. The fire services installation work fell behind schedule. 7.Another problem seemed to be that WEC was not paying its own sub-contractor, either on time or at all. WEC's sub-contractor was the Plaintiff, Comtech Engineering & Consultant Company Limited ("Comtech"), to whom WEC had sub-contracted a part of the works for the sum of $4,997,228.00. This sub-sub-sub-contract is evidenced by a Work/Variation Order dated 4 June 1997. The contract administration part of the work was, however, not subcontracted to Comtech. 8.Eventually, Thorn decided in February 1998 to terminate the sub-sub-contract with WEC (as well as two other projects on which WEC had been engaged also as sub-contractor, namely, the developments at KCTL 456, Hing Shing Street, Kwai Chung ("P 456") and at the MTRC Quarry Bay Station). The termination of WEC's employment in the Lai Kong Street project is evidenced by a fax dated 11 February 1998 from Thorn to WEC. Thorn decided to replace WEC with Comtech. Negotiations between Comtech and Thorn took place over February and March. During this time, Thorn was already behind schedule in the fire services installation work. For example, there is a record of a coordination meeting on 2 March 1998 in which it is recorded that Hip Hing found the fire services installation "slow and behind .... schedule". 9.We are in this action only concerned with the Lai Kong Street development (known also as Project 458). There is no dispute that Comtech was engaged to do fire services installation work by Thorn and that it did carry out such work. One of the principal disputes in this action between Comtech and Thorn, however, is the ambit and terms, if any, of Comtech's engagement. I will turn to this important issue in due course. 10.Comtech's engagement by Thorn started in about February 1998. At that time, WEC had done about 28.6% of the fire services installation work required of it. By a fax dated 11 February 1998, Thorn informed Comtech that WEC's involvement in the project was terminated and Comtech was asked to take over WEC's activities at the site. 11.I shall refer below in detail to the events from February to April 1998 when dealing with the important issue of the existence or otherwise of a binding contract between the parties. Suffice it to say for the present that as Comtech proceeded with the performance of the fire services installation work (both wet and dry), this work became increasingly behind schedule. There are many documents evidencing the concern and dissatisfaction of Hip Hing and HKHS on the lack of progress. 12.Eventually, on 1 July 1998, Thorn took over from Comtech the performance of the wet work for the fire services installation at the Site. It is quite clear that Comtech was unable or unwilling to complete this part of the work. Comtech made no objection to Thorn taking over the wet work. It appears that Comtech continued with the dry work until 24 September 1998. From that date, it carried out some rectification work although, as will presently be seen, Thorn had to carry out some of this. 13.Practical Completion was eventually certified by the architect, Ronald Lu & Partners ("RLP") to be on 31 December 1998. Thereafter, rectification work continued during the defects liability period. 14.In the course of early 1999, Comtech and Thorn had final accounts discussions. Allegations and counter-allegations were made as both Comtech and Thorn claimed against one another. Nothing was resolved. On 15 May 1999, Thorn commenced proceedings against Comtech (HCA 7968 of 1999) claiming the sum of $9,265,437.28 for breach of contract. For its part, on 1 June 1999, Comtech instituted proceedings against Thorn (HCCT 53 of 1999) claiming initially $6,179,974.41 as the amount due and owing to it from Thorn. Both claims of course arose out of the same project and the fire services installation work that had been carried out at the Site. The proceedings 15.On 23 May 2000, Burrell J consolidated the two actions and directed that Comtech be the Plaintiff in the consolidated action and Thorn, the Defendant. 16.Trial before me commenced on 15 October 2002 lasting some 10 days ending on 31 October 2002. At trial, Mr Nicholas Cooney represented Comtech and Mr Anthony Houghton represented Thorn. 17.The following persons gave evidence at trial for Comtech:-
18.For Thorn, the following persons gave evidence:-
19.All witnesses had provided witness statements which were treated as their evidence in chief. In making findings of fact in this judgment, I have based such findings on the testimony of the witnesses and the documents before me. The facts stated above in the Background (which are common ground or indisputable) are to be treated as findings of fact. The parties' claims 20.Both Comtech and Thorn have made claims against each other arising out of the performance of the fire services installation work carried out by Comtech at the Site. The nature, however, of the claims made by each party is quite different. 21.Comtech puts its case simply. Labour and materials were provided by it in relation to the fire services installation work carried out at the Site and Comtech's claim, less partial payments totalling $2,114,220.00, comes to $5,184,442.34 (as pleaded in the Amended Statement of Claim), although by the end of final submissions, the claim was put at $4,875,013.85. The claim is made on a quantum meruit basis. As pleaded, the various components of this claim comprise labour and materials supplied and various other expenses, together with office overheads and profit. It was, as Mr Cooney put it, a "cost plus" equation. In the course of the trial, it became clear that Comtech's primary position in support of its quantum meruit claim was that there was no contract between the parties. Alternatively, it was said that if there was an express contract, this was on the basis only of labour and materials to be supplied by Comtech at reasonable cost. I shall deal further below with this somewhat inconsistent approach. 22.Thorn puts its case equally simply but approaches it from a completely different direction. Thorn's case is that a contract did exist between the parties, not on the basis of a quantum meruit or for labour and materials at cost-plus, but on the basis of detailed terms contained in a sub-sub-contract as evidenced by a purchase order dated 9 April 1998 numbered 3164 ("PO 3164"). This purchase order, it is contended, reflected the parties' wish that Comtech would take the place of WEC as Thorn's sub-sub-contractor in respect of the fire services installation work. The contract sum stated in PO 3164 was $5,419,636.57. 23.It is important in the present case then first to resolve the question whether there existed a contract between the parties and if one did exist, its terms. This is critical to the following matters which have to be resolved:-
24.I propose dealing with the following issues in turn:-
Issue 1: Was there a contract between Comtech and Thorn and if so, what were its terms? 25.I have already summarised the parties' basic positions. 26.In my judgment, there is no doubt that a contract did exist between the parties and that the relevant terms were those as contained in or evidenced by PO 3164. I reject Comtech's contention that either there was no contract at all (its primary case) or if one did exist, it was on terms that Thorn would be charged on a cost plus basis for labour and materials supplied. 27.I reach this finding for the following reasons. 28.First, the relevant contemporaneous documentation compels this result:-
29.PO 3164 stated on its face the price ($5,419,636.57). The precision of this figure supports what C.H. Yung had said about the basis of the pricing (see paragraph 28(2) above). The purchase order also stated on its face "Job 9179" which was the same reference as that mentioned in the relevant purchase order given to WEC (PO 2376). This indicates quite clearly that it was intended that Comtech step into the shoes of WEC in taking over the fire services installation work. I have already referred to some of the contract administration obligations in the Thorn-WEC purchase order contained in the Domestic Sub-Sub-Contract. These same obligations were contained in PO 3164 in the equivalent document annexed thereto. I will refer further to this below as well as to the specific unit rates for materials contained in the Schedule of Rates also appended to that purchase order. 30.Secondly, I turn to the conduct of Comtech and Thorn subsequent to PO 3164 and this in my view reinforces the fact that there was a contract between the parties on the terms of the purchase order:-
31.Thirdly, Thorn's version makes commercial sense in the circumstances whereas Comtech's does not:-
32.Fourthly, I have already referred to the Amended Statement of Claim in which a contract is alleged to have existed between Comtech and Thorn. From that pleading, it is alleged to have been made on 11 February 1998. This is to be contrasted with the way Comtech approached this aspect at trial. Its case at trial was primarily that no contract existed. Alternatively, if a contract was made, this was made at the end of February 1998 (and not 11 February 1998) whereby Comtech agreed to perform the wet and dry work by providing labour and materials on a cost plus basis while Thorn would be responsible for contract administration. No explanation was given for the change and it is an aspect that I take into account in deciding this issue against Comtech. 33.Both Mr Cooney and Mr Houghton have referred me to a number of authorities dealing with the court's approach in finding the existence of a contract in building cases. Whether or not a contract exists may often be a difficult question on the facts, especially where there is no one document that is signed by the parties. The parties may often be in protracted negotiations, with offers and counter-offers being made to one another. In all such cases, the court needs to look at the whole of the communications between the parties and their conduct. I refer in particular to a passage in the judgment of Robert Goff J in British Steel Corporation v Cleveland Bridge & Engineering Co. Ltd. [1984] 1 All E R 504, at 509, in which he says, "Now the question whether in a case such as the present any contract has come into existence must depend on a true construction of the relevant communications which have passed between the parties and the effect (if any) of their actions pursuant to those communications". 34.With the finding I have made in Thorn's favour on Issue 1, I now turn to the other issues. Issue 2: Was Thorn in breach? 35.It follows from my finding (that the parties contracted on the terms stated in PO 3164) that Comtech fails in its claim for damages on a cost plus basis for labour and materials. However, there is no doubt that some monies are due to Comtech under PO 3164 itself. I find the amount of Comtech's entitlement comes to $3,606,609.56. This takes into account the contract sum of $5,419,636,57, with $701,193.08 to be added for variation work done by Comtech (in fact Mr Ngo for Comtech only allows $695,354.88 but I take the higher figure) but with $2,114,220.09 deducted being the amounts previously paid to Comtech as well as $400,000.00 (as the provisional sum). 36.However, in view of my conclusions on the next two issues, it would be wrong to say that Thorn was in breach by not paying Comtech this amount. The value of Thorn's counterclaim far exceeds the amount to which Comtech is entitled under PO 3164. Issue 3: Was Comtech in breach? 37.Under PO 3164, it was stipulated that the performance of Comtech's work was to be in accordance with the "sub-contract programme but not later than 31 July 1998". 38.At the time Comtech commenced to work on the Site replacing WEC, the fire services installation work was already behind schedule. I have earlier referred to the building services coordination meeting held on 2 March 1998 in which Hip Hing remarked that the fire services installation work was "slow and behind .... schedule", although Hip Hing had continually urged Thorn to take catch up action. The delay had no doubt been due, at least to a significant extent, to WEC's performance (or lack of it). 39.Thus, when Comtech was required to take over from WEC, there was a certain urgency to the performance of the fire services installation work that could not have been lost on Comtech. Comtech, it will be recalled, afterall had been the sub-sub-sub-contractor engaged by WEC at the Site. The quotation made by Comtech in the 1 March letter implicitly recognised this urgency in the price that was quoted. This price ($5,230,000.00) was in fact over $200,000.00 more than the price that Comtech got in its contract with WEC. It did not include contract administration, according to Comtech. Thus, since the work undertaken by Comtech for WEC also did not include contract administration (according to Otway Lee), it can be inferred that this increase in price contained in the 1 March 1998 quotation reflected (at least in part) the urgency of the situation. The letter also stated, "We [Comtech] are now to submit it herewith this proposal and advise that we must be sufficient and our resource for complete the installation works of Fire Services System". 40.It is Thorn's case that there were significant delays in the fire services installation work that Comtech was contracted to perform and this constituted a breach of contract on its part. It was this continual delay that led to Thorn taking over the wet part of the fire services installation work from 1 July 1998. Donnie Wong has given detailed evidence in support of this claim and I accept what he says. It is on the whole consistent with the contemporaneous documentation, with which I will deal presently. Donnie Wong's evidence was essentially that when Comtech initially took over, things progressed smoothly. However, during April 1998, Comtech began slowing down and fell behind the programme. In turn, Thorn became increasingly under pressure from Hip Hing, who was no doubt under pressure itself from the employer. Matters deteriorated in May and June 1998. Ultimatums were delivered to Thorn by Hip Hing and in turn passed down to Comtech. Comtech simply could not perform on time what was required. Eventually, without much if any protest, it allowed Thorn to take over the wet work as from 1 July 1998. The problem was probably lack of manpower to perform the necessary work. Eventually, owing to the predicament in which it found itself, Thorn had to engage labourers and obtain materials at great expense just to complete the requisite work. 41.Before I deal with the documentation, I should perhaps explain the significance of the fire services installation work in relation to the project as a whole. Hip Hing was particularly concerned over the fire services installation work being completed on time because unless the Fire Services Department certified this aspect to be safe, no certificate of completion would be issued and in turn the occupation permit for the buildings on the Site would not be issued. 42.I now deal with the relevant documentation. There is a lot over the relevant period but I will just deal with a few of the more important documents. 43.I have already referred to the coordination meeting held on 2 March 1998 (see paragraphs 8 and 38 above). By a letter dated 18 March 1998 from RLP to Thorn, Thorn was asked to take "immediate" action on a number of aspects including site installation progress being "still far behind programme" and what was perceived to be an insufficient labour force to catch up. 44.On 22 March 1998, following a site meeting between Comtech and Thorn, an "agreed" fire services catch up programme was sent to Comtech by Thorn. I have already referred to this letter in paragraph 28(6) above. 45.A site memorandum dated 17 April 1998 from Hip Hing to Thorn refers to the progress made by Thorn as a "terrible mess". This was a site memorandum amongst many. By a letter dated 24 April 1998 from Hip Hing to Thorn headed "Final Reminder on Termination of Sub-contract", Hip Hing informed Thorn that the sub-contract would be terminated on 30 April 1998 "if we consider your performance is still not satisfactory". The letter ended, "as the situation is extremely critical, taking into consideration on the submission of form 501 scheduled on 10/05/98, whereas most of your commitments still cannot be honored, please take special remedial action on almost urgent basis". 46.By a letter dated 27 April 1998 from Hip Hing to Thorn, completion dates for various fire services installation works were set out and the threat to terminate the sub-contract between them was repeated. This letter was copied to Comtech in Thorn's letter dated the same day in which the completion dates for various items set out in Hip Hing's letter were described as "critical dates for us to achieve in order not to be terminated by the Main Contractor". Comtech was also informed that it would be held liable for any costs incurred through its "slow and unacceptable programme". Significantly, there was no contradiction to the sentiments expressed in this letter when Comtech replied by its letter dated 30 April 1998. Otway Lee's explanation for this in cross-examination was that he basically ignored the letter because he took the view that no contract existed between Comtech and Thorn and therefore any problems that Thorn had as regards Hip Hing, were not Comtech's concern. I reject this attempt again to qualify the impact of the contemporaneous documentation. As I have found, a contract did exist and Otway Lee knew this. The contents of Thorn's letter to Comtech dated 27 April 1998 were not contradicted because they were true. 47.By a letter dated 12 May 1998 to Comtech, Thorn expressed its disappointment at Comtech's lack of progress. Reference was made to the continual complaints made by RLP, Mott MacDonald and Hip Hing. Comtech was further informed that if it could not complete the works on time, Thorn would be forced to allocate its own resources. Comtech responded to this letter the next day in which it referred to the working programme as being "impossible". Reference was also made to various factors, for which Thorn was responsible, that had contributed to the delay. I will deal with these counter allegations below when dealing with the excuses made by Comtech. It is sufficient to say for now that I reject them: they are insignificant compared with its own default. 48.Matters did not improve in June 1998. By a memorandum dated 11 June 1998 from Mott MacDonald to Hip Hing, the latter was urged to increase the work force to catch up with the fire services installation programme. It described the number of workers for the fire services installation work as being "totally unbelievable". By a letter dated 16 June 1998, Thorn informed Comtech that as it had repeatedly ignored Thorn's request to increase its workforce to cope with the fire services installation programme, Thorn had no choice but to mobilise its own workforce. Comtech responded the next day stating that it was not in a position to keep its workforce to perform the work and further alleged that Thorn had not provided sufficient information and drawings to perform the work on time. 49.On 22 June 1998, representatives of Comtech and Thorn met to discuss target dates and the number of electrical and plumbing workers that Comtech had to employ. The minute of that meeting was enclosed in a letter dated 22 June1998 from Comtech to Thorn. It is clear from that letter that Comtech was acutely aware of the need to achieve the target completion date. No mention was made in that letter, however, of any difficulties that Comtech might be having in relation to its not having been given sufficient information or drawings by Thorn. 50.By a letter dated 29 June 1998 from Mott MacDonald to Hip Hing (headed "Warning Letter"), Hip Hing was ordered to instruct Thorn to catch up with the fire services installation programme. A letter from Hip Hing to RLP referred to Thorn's performance as being "gradual further inferiority [sic]" (which I take to mean further deterioration). 51.Things came to a head on 30 June 1998. By a letter that day, Thorn instructed Comtech to mobilise at least 40 plumbers (making altogether 60 workers on the Site) to execute the fire services installation works without any further delay. This confirmed an oral request made by phone on C.H. Yung's part to Mr Parry Tang of Comtech. 52.By another letter that day from Thorn to Comtech, reference was made to the earlier letter as well as the 16 June 1998 letter. It continued:
53.These letters followed a fax dated 30 June 1998 from Hip Hing to Thorn in which concern was expressed by Hip Hing as to Thorn's "empty commitments" and it was further stated that the site supervision and labour resources provided by Thorn were "totally unacceptable". Thorn was given a final warning that the sub-contract would be terminated on 2 July 1998 unless Thorn committed 60 workers on the fire services installation work by 1 July 1998. 54.According to Donnie Wong, when he spoke to Otway Lee (as recorded in the second letter dated 30 June 1998), Comtech had only approximately 10 electricians at the Site with no plumbers. As he puts it in his witness statement, "We [Thorn] urgently needed plumbers to maintain progress on the fire services installation so we wrote confirming that we would be taking control of the works. .... Our intention was to provide additional labour so as to improve progress or even to mitigate the fact of the delay being progressively caused by Comtech. I knew that we had to do something quickly if the date for completion was to be achieved". 55.By a letter also dated 30 June 1998, Comtech referred to Thorn's request by phone for additional manpower and workforce. Reference was also made (again) to Thorn's failure to provide sufficient information and working drawings. However, no attempt was made by Comtech to link the question of sufficient workforce and manpower to that of the lack of information and drawings. Whatever Comtech now says, it was never really part of Comtech's position at that time that there was somehow no point increasing the workforce since there was insufficient information or lack of drawings. 56.On 7 July 1998, Comtech responded to Thorn's two letters dated 30 June 1998. Although it protested any attempt to charge Comtech for additional charges that Thorn said they would incur in completing the project, Comtech did not say that it could in fact perform the work itself. On the contrary, it stated in the letter that it would have no objection to Thorn mobilising its own workers. 57.Thorn did indeed take over the wet work as from 1 July 1998. According to Donnie Wong, Thorn immediately mobilised 60 plumbers on a day-work basis. Although he accepts this was not the most economical way of performing the work, it was a quicker way of securing performance of the fire services installation work rather than trying to get lump sum quotations. As was clear by that stage, Hip Hing had lost all patience. A fax dated 4 July 1998 from Hip Hing to Thorn stated Donnie Wong's acknowledgement at a meeting held on 3 July 1998 that no obvious progress had been made by Thorn. That fax referred to a meeting that was to be held on 6 July 1998 at which Thorn's continued role as fire services sub-contractor was to be further discussed. 58.Apart from organising extra workers, Thorn also had to order materials that Comtech should have done but did not. The additional labour and materials that Thorn had to organise and pay for are the subject of Thorn's Counterclaim. 59.In my judgment, it is clear that Comtech was in breach of contract in failing to perform the work timeously. This was on the whole the wet part of the fire services installation work. As I have earlier said, I accept Donnie Wong's evidence and this evidence is consistent with the contemporaneous documentation. 60.In the Defence and Counterclaim, reference is made to Comtech's breach as amounting to a repudiation which was accepted by Thorn either on 30 June 1998 (meaning presumably the two letters from Thorn to Comtech that day) or the issue of the writ in HCA 7968 of 1999 on 15 May 1999. In view of the fact that Comtech did remain on the Site after 1 July 1998 to perform some electrical and other work, it cannot really be said that the contract had been terminated by Thorn's acceptance of Comtech's repudiation. Obviously, as a matter of law, it is not possible for an innocent party to accept only partially the repudiation of a contract. Either the whole contract is affirmed or the whole contract is terminated by the acceptance of the repudiation. There is no halfway position. The correct legal analysis in the present case is that Comtech did breach the contract by failing to perform it either on time or at all. In the circumstances, the delay on Comtech's part to perform its obligations was equivalent to non-performance. Thorn did not accept this repudiation. Instead, the parties (at least implicitly) agreed that Thorn would mobilise its own workers and perform other parts of the contract itself while Comtech retained a more minor role. In a way, it was a variation of the original contract but this is not of great significance. What is, though, of importance is the conclusion that Comtech was in breach. 61.In arriving at this conclusion that Comtech was in breach of contract by its delay or non-performance, I have not ignored its contention that any delay was caused or contributed to by Thorn's own default. Though not pleaded (somewhat surprisingly), it was Comtech's case at trial that any delay was caused by:-
These allegations were contained in Otway Lee's evidence. 62.In my judgment, while I accept that these matters were not fictitious since there are documents making reference to them, I do not accept that they in any way caused or contributed significantly to the delay in this project, other than on a de minimis basis. I am of the this view for the following reasons:-
63.Apart from delay and inability to perform PO 3164, Thorn also alleges that Comtech was in breach of contract by performing defective work and failing to rectify such defective work. Donnie Wong has provided details in support of this claim and indeed the documents reinforce this. Comtech was pressed to rectify defective work but failed to do so. As Donnie Wong says in his first witness statement, from July to August 1998, Comtech maintained at the site about 7 plumbers and 3 electrical workers. After August, the electrical workers diminished to about 2 or 3 and there were no plumbers. He says, "Comtech effectively abandoned the site during this period". I have been referred to non-conformance reports from Hip Hing to Thorn providing details of defects and Otway Lee accepted in his testimony that Thorn would expect Comtech to rectify these matters. Letters from Thorn to Comtech referred to defect rectification (see for example the letters dated 12 May 1998 and 5 January 1999 from Thorn to Comtech). Hip Hing's complaints were copied to Comtech as well (see for example the fax dated 18 May 1998 from Thorn to Comtech). I accept Donnie Wong's evidence that Comtech failed to perform rectification work and was therefore in further breach of contract. In fact, he said that following Thorn's taking over of the wet work, about 40% of its resources was used for defects rectification work. 64.In summary, I am of the view for the reasons stated above that Comtech was in breach of contract as alleged by Thorn. What are the consequences of this? Issue 4: Quantum of damages 65.Thorn alleges that as a result of Comtech's breaches of contract, it had suffered loss and damage. The factual evidence in support of Thorn's claim is contained in the testimony of Terry Sy (which I accept as showing that Thorn suffered loss and damage), supported by the expert quantity surveying evidence of Mr Cierpicki. Comtech, for its part, relied on the evidence of Mr Ngo in relation to the assessment of Thorn's Counterclaim. Both experts have helpfully provided individual reports as well as a joint report agreeing on relevant figures in relation to certain items of claim. Thorn's Counterclaim can be broken down into the following parts:-
66.I deal with each of these claims in turn. 67.Additional materials
68.Extra labour
69.Additional management time
70.Overheads
71.Contra charges
72.Loss of profit and loss of business opportunity
Outcome 73.Taking into account the sums due to Comtech under PO 3164 (totalling, as stated in paragraph 35 above, $3,606,609.56), the amount of Thorn's counterclaim comes to $8,713,949.51. I therefore give judgment to Thorn in this sum. I will hear the parties in due course on interest, costs and any other outstanding matters. 74.The award of damages to Thorn in the above sum reflects the predicament that Thorn found itself in when faced at the end of June 1998 with a main contractor who was threatening to terminate the sub-contract (with the consequential claims that would inevitably have been made) and a sub-sub-contractor who was simply not performing. PO 3164 was, as Mr Cierpicki put it, underpriced, no doubt partially because Comtech wanted to establish itself as a fire services installation sub-contractor who could perform competitively. For Thorn, getting labour and materials at short notice was inevitably going to cost more. 75.It only remains for me to thank counsel and solicitors for their assistance in this case.
Representation: Mr Nicholas Cooney, instructed by Messrs K.H. Lam & Co, for the Plaintiff. Mr Anthony Houghton, instructed by Messrs Denton Wilde Sapte, for the Defendant. | ||||||||||||||||||||||||||||||||||||||||
Further hearings and rulings under HCCT 53/1999 and HCA 7968/1999