Kung Shing Investment Ltd v. The Sunbeam Manufacturing Co Ltd
Read the full judgment text of DCCJ 4093/2002 on BabelCite. This District Court judgment.
12. (iv) The 2 nd Defendant do pay the costs of repair in the sum of $14,200.00 to the Plaintiff within 30 days. Interest on this sum at judgment rate from the date of the service of the writ up to the date of the payment of the said sum of $14,200.00.
|
DCCJ4093/2002 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO.4093 OF 2002 ----------------------- BETWEEN
-------------------- Coram: His Honour Judge Chow in Court Dates of Hearing: 23rd - 25th June 2004, 28th June 2004 and 9th July 2004 Date of Handing down Judgment: 26th August 2004 ___________________ Corrigendum ___________________ Sub-paragraph (iv) of paragraph 12 has been amended to read as follows:
Dated this 30th day of September 2004
|
Further hearings and rulings under DCCJ 4093/2002