The Incorporated Owners of Tak Tai Building v. Leung Yau Building Ltd

Case No.HCCT24/2004
Court
高等法院原訟法庭
Date21 Jun 2004
JudgeDeputy High Court Judge Poon
Case Document
100%

HCCT24/2004

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

CONSTRUCTION AND ARBITRATION PROCEEDINGS

NO.24 OF 2004

___________________________

  IN THE MATTER OF THE ARBITRATION ORDINANCE CAP. 341
  and
  IN THE MATTER OF AN ARBITRATION

___________________________

BETWEEN

  THE INCORPORATED OWNERS OF TAK TAI Applicant
  BUILDING (Respondent in Arbitration)
  and  
  LEUNG YAU BUILDING LTD Respondent
    (Claimant in Arbitration)

___________________________

Before : Deputy High Court Judge Poon in Chambers

Dates of Hearing : 29 March, 3 April and 21 June 2004

Date of Judgment : 21 June 2004

Date of Handing Down Reasons for Judgment : 28 June 2004

___________________________

C O R R I G E N D U M

___________________________

Please kindly note the following amendment:

1.In paragraph 39, the sentence “Thus, the applicant was at the outset of these proceedings…”, “these proceedings” should read as “the hearing before me”.

Date: 24th August 2004

  (A.Lam)(Miss)
Clerk to Deputy High Court Judge Poon

Summaries and metadata are generated from the judgment. Report an error