Wong Leung Chi v. Luen Fat Civil Engineering Ltd and Another
Read the full judgment text of HCPI 975/2002 on BabelCite. This High Court CFI judgment.
1. Judgment was delivered in this matter on 25 August 2004. In paragraph 38 of the judgment I set out a summary of the damages award. The parties have now drawn attention to the fact that there were certain errors in that summary. The parties have, sensibly, agreed the correct summary which I now set out.
|
HCPI975/2002 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE PERSONAL INJURIES ACTION NO. 975 OF 2002 ____________ BETWEEN
____________ Before: Deputy High Court JudgeSaunders in Court _____________ CORRIGENDA _____________ 1.Judgment was delivered in this matter on 25 August 2004. In paragraph 38 of the judgment I set out a summary of the damages award. The parties have now drawn attention to the fact that there were certain errors in that summary. The parties have, sensibly, agreed the correct summary which I now set out. 2.Summary of damages awarded:
3.By consent, the costs of the action after the plaintiff, to be taxed on a party in party basis if not agreed, with the Plaintiff's costs to be taxed in accordance with Legal Aid Regulations.
Ms Phillis Loh (16 & 17 August 2002), instructed by Messrs Donald Yap, Cheng & Kong, for the Plaintiff Mr Dennis Law instructed by Messrs W K To & Co., for the 1st and 2nd Defendants Mr Andy Hung instructed by Messrs Pansy Leung, Tang & Chua, for the Third Party |
Further hearings and rulings under HCPI 975/2002