Lam Geotechnics Ltd v. Wong Kai Hung
Read the full judgment text of DCEC 322/2005 on BabelCite. This District Court judgment.
1. In this action, the Applicant applies to the Court under section 16B of the Employees Compensation Ordinance for cancellation of the Review of Compensation Assessment (Form 6) issued to the Respondent out of time.
Cited by 1 case · Cites 2 cases
|
DCEC 322/2005 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION EMPLOYEES’ COMPENSATION CASE NO. 322 OF 2005 --------------------- IN THE MATTER OF AN APPLICATION BETWEEN
------------------- Coram: Her Honour Judge C.B. Chan in Court Dates of Trial: 27th & 28th February 2006 Date of Handing Down Judgment: 13th April 2006 ______________________ JUDGMENT ______________________ 1.In this action, the Applicant applies to the Court under section 16B of the Employees Compensation Ordinance for cancellation of the Review of Compensation Assessment (Form 6) issued to the Respondent out of time. 2.The Respondent made an application in DCEC 110 of 2005 under section 16A(8) of the Employees Compensation Ordinance on 3rd February 2004 in DCEC110 of 2004 that the Form 6 be made an Order of the Court. In that action the parties entered into a Consent Summons on 2nd February 2005 that leave be granted to the Applicant herein to apply under section 16B of the Ordinance for cancellation of the Form 6 out of time. Hence this action was taken out by the Applicant herein. 3.The circumstance in which the Applicant relies are:-
4.On the 28th October 2005 by Order of H.H. Judge Ng, it was ordered that the two actions be tried and heard at the same time. This judgment arises from the trial. Undisputed Facts 5.The following facts were undisputed:
6.In his claim in DCEC 110 of 2005, the Respondent claims the balance of the compensation in the sum of HK$184,112.00. The Applicant denies that he was the principal contractor of the Respondent at the material time. The Respondent’s case at the trial was that he had only received the sum of HK$110,000.00 from Johnwing. The balance of HK$184,112.00 had not been paid to him but Johnwing gave him a cheque for this sum which was dishonoured. The Respondent was informed by Johnwing that the cheque was dishonoured because the Applicant did not pay this sum to Johnwing. The Applicant contended at the commencement of trial that Johnwing had paid the Respondent the full sum of the compensation because the Respondent had signed receipt of the full sum to Johnwing. The Respondent explained that he signed receipt for the entire sum to Johnwing because he was told by Johnwing that it was upon production of this receipt that the Applicant would reimburse the compensation to him. Johnwing would only be able to pay compensation to the Respondent upon receipt of this from the Applicant. At the conclusion of the trial Mr. Li Sin Keung the witness of the Applicant admitted that he had been informed by Johnwing that the Respondent had only been paid the sum of of HK$110,000.00 in compensation that the balance had not been paid. The Applicant then conceded that the only issue of the trial is whether the Applicant was the principal contractor of Johnwing and/or whether Johnwing was the subcontractor of the Applicant in this project. Evidence of the Respondent 7.The Respondent’s case is that the Applicant was the principal contractor of Johnwing. When the Applicant filed the Form 2 stating that it was the principal contractor, it considered its position and came to the conclusion that the Applicant was a principal contractor before Mr. Sin Chi Fai prepared and signed the Form 2. The Respondent adduced his Witness Statement dated 11th June 2004 and Second Witness Statement dated 21st June 2005 into evidence and confirmed it to be true. The Respondent stated that the Applicant had taken no step to inform the Labour Department that it was not the principal contractor until its application in this Court even though there is provision to do so. 8.The Respondent stated that at the site, he did the work of demolition of partition walls and removal of electrical wires. He was responsible for removal of the electrical appliances. After his accident, Johnwing told him that he had signed a contract with the Applicant for the works in question. To his knowledge, the Applicant was the principal contractor who subcontracted all the works on the site. Johnwing gave him instructions to work on the site. Evidence of the Applicant 9.The Applicant called Mr. Li Sin Keung a Senior Quantity Surveyor of the Applicant to give evidence. He adduced his witness statement at pages 1 to 8 of Section B of the Bundle of Witness Statements. 10.He stated in his witness statement that the Applicant had rented from Topsail Estate Limited Flat No. 6 with Carpark No. L8 on the Ground Floor of Topsail Plaza situate at No. 11 On Sum Street, Shatin, New Territories, Hong Kong for two years from 1 August 1999 to 31 July 2001 at the rental of HK$37,932.00 per month. The Applicant used these premises as its office and workshop and to store consumable materials and spare parts of the machines used in construction projects. The Applicant also repaired and maintained plant and machinery at the Premises. The Applicant was required to return the said premises to its landlord in a bare shell condition which was the condition when the Applicant moved in. Hence the Applicant engaged a demolition and clearance contractor Johnwing Engineering Company to carry out the demolition and clearance work for this. 11.Under the reinstatement contract, Johnwing had to provide labourers to carry out the work for the Applicant. All the workers were under the direct supervision and control of Johnwing. Johnwing charged the Applicant a total sum of around HK$32,000.00 for the reinstatement work. 12.The Respondent twisted his ankle when moving a chiller installed by the Applicant as a fixture on the said premises. 13.He stated that after the Applicant was notified of the accident, Mr. Sin Chi Fai, the Safety Consultant of the Applicant and Mr. Leung Man Kit, the Plant and Logistics Manager of the Applicant mistakenly believed that the role of the Applicant was a principal contractor whilst Johnwing was a sub-contractor. 14.Mr. Sin Chi Fai submitted the Form 2 naming the Applicant as the principal contractor. He stated that this was in fact a mistake. He lodged this in the Labour Department purely because of his misconception that Johnwing was a sub-contractor of the Applicant. Was the Applicant a Principal Contractor 15.The Respondent’s Counsel argues that the Form 2 is an important document enacted under the Ordinance. Mr. Sin Chi Fai who signed it was a Safety Officer or Consultant of the Applicant at all material times. Mr. Sin Chi Fai had discussed with Mr. Leung Man Kit, the Plant & Logistics Manager of the Shatin Workshop at the material time before the completion of Form 2. He must have thoroughly considered whether the Applicant was a principal contractor before he stated that in the Form 2. Mr. Sin’s great care can be seen by the fact that on 14 August 2001, 10 days after the filing of Form 2, Mr. Sin Chi Fai wrote to the Labour Department to amend the Form 2 to state that the Respondent did not work on Sundays. A Safety Officer is regulated under the Factory & Industrial Undertakings (Safety Officers and Safety Supervisors) Regulations, cap 59Z. His work is subject to statutory control. He submitted that Mr. Sin must have double-checked with Mr. Leung Man Kit before coming to the conclusion that the Applicant was a principal contractor. 16.The Respondent’s Counsel also submitted that, in the course of cross-examination, Mr. Li Sin Keung stated that the Applicant had thought it was the principal contractor from the date of the accident up to the time they sought legal advice. It was only upon legal advice that the Applicant changed its position to state that the Applicant was not a principal contractor. In fact, the Applicant had submitted to its insurer, Tugu Insurance Co. Ltd. in the capacity of a principal contractor, receipts of payment signed by the Respondent to Johnwing. The Applicant had also adopted the capacity of a principal contractor to discuss with Johnwing about the compensation arising from the accident. 17.The Applicant is also a special contractor registered with the Buildings Department in ground investigation field works. Their staffs are men in the trade and must know what being a principal contractor entails. He therefore submits that it is incredible that a Safety Officer as senior and experienced as Mr. Sin Chi Fai could have made such a simple mistake to state that the Applicant is a principal contractor if it is not. 18.The Respondent’s Counsel also submits that Form 2 is a legal document or is a document that has legal effect. The Respondent’s Counsel relied on the case of Jumbo King Limited v. Faithful Properties & Others (1999) 2 HKCFAR 279, at 296, where Lord Hoffman NPJ stated that,
19.The Respondent’s Counsel submits that the Form 2 is a document with legal effect as it is a form enacted in the Ordinance. 20.He also relies on United Ford Development Ltd. t/a King Ford Mahjong Club v Fung Yin Yee Shirley & Others [1993] 2 HKLR 290. It is a case where 4 employees of a Mahjong Club died from excessive smoke when robbers robbed the cashiers downstairs. The words of the trial Judge, H.H. Judge Downey were repeated in the judgement of the Court of Appeal as follows:
21.He submitted that the Court is perfectly entitled to draw reasonable inference from the simple admission in the Form 2 that the Applicant was a principal contractor. 22.Further, the Applicant failed to tender the two crucial witnesses, Mr. Sin Chi Fai and Mr. Leung Man Kit for cross-examination as regards how they came to the conclusion that the Applicant was a principal contractor when considering how to complete Form 2 and how they could have been mistaken as regards this. Mr. Li Sin Keung did not offer any credible explanation as regards how such a fundamental mistake could have been made. 23.He submitted that if there is an issue of doubt, the issue of doubt should be resolved in favour of the injured worker to fulfil the legislative intention which is for the protection of injured workers. 24.The Applicant’s Solicitor seeks to rely on the definition of “principal contractor” in the Ordinance and in particular the definition stated in section 24 (1) of the Ordinance. It states:
25.The Applicant’s Solicitor refers to Poon Hau Kei v Hsin Cheong Construction Co. Ltd. v Taylor Woodrow International Ltd. Joint Venture [2000] 1 HKC 324 where the words “work undertaken by the principal contractor” in section 24(1) of the Ordinance is clarified in the judgment of Lord Hoffman. At page 346 D, it states, “‘Work undertaken’ therefore means work which is the subject of a contract to be performed either personally or vicariously.” 26.He submits that from the evidence of Mr. Li Sin Keung, it is clear the work for which Johnwing was contracted related to reinstatement of the said Premises before it would be returned to its landlord. The Applicant did not undertake any work, which was the subject of a contract to be performed either personally or vicariously. Therefore, the Applicant could not have been a principal contractor according to section 24(1) of the Ordinance. 27.He also referred to authorities to show that descriptions contained in Form 2 could not be binding or conclusive as against the Applicant but the question as regards whether the Applicant was a principal contractor is an issue of fact to be decided by the Court upon the evidence. The authorities relied on are: (1) Lung Yui Man v Yee Hing Kee Plumbing Works Company Limited and Another [2000] HKEC 130, where Deputy Judge Li said,
(2) Chan Sik Pan & Another v Wylam’s Services Ltd. & Others (2001) 4 HKCFAR 308 where the Applicant filed a Form 2 admitting itself to be the employer, gave periodical payments to the appellant and made objection to the Commissioner of Labour’s assessment of compensation. The Applicant subsequently denied that it was the employer. The trial judge relied on the contents of Form 2 and did not allow the Applicant to give evidence. The Court of Final Appeal ordered a new trial by reason of the trial Judge’s violation of the principle of natural justice. Bokhary PJ stated at page 316 G, as follows:
28.The Applicant’s Solicitor therefore submits that if the Form 2 were binding and conclusive, the Court could just rely on the Form 2 alone to decide who was the employer and there should be no need for a new trial. 29.I am of the view that the description of the Applicant as principal contractor in the Form 2 should not be treated as binding or conclusive as regards the status of the Applicant as against Johnwing and the Respondent. 30.Lord Hoffman’s definition of the words “work undertaken” in section 24(1) clearly states that such work has to be the subject of a contract to be performed by the principal contractor either personally or vicariously. In this case, the evidence does not point to the fact that the work contracted by the Applicant to Johnwing was work that was the subject of a contract to be performed by the Applicant either personally or vicariously. The very nature of a contract requires that the Applicant contract with another party in respect of the work undertaken which was the subject of work contracted to Johnwing. The Applicant it seems entered into the contract with Johnwing because it was under contractual obligation in the Tenancy Agreement with its landlord to surrender the premises after reinstatement. The Applicant had not entered into a contract to perform the subject work either personally or vicariously with another party. 31.Having considered the aforesaid, I come to the conclusion that the Applicant was not the principal contractor of Johnwing in relation to the work contracted to Johnwing. 32.I therefore grant the Applicant’s application to cancel the Respondent’s Form 6. It is hereby ordered that the Certificate of Review of Compensation Assessment (Form 6) issued on 18 June 2003 is cancelled. I grant an order nisi for costs of the action to the Applicant to be taxed if not agreed.
Representation: Mr. Ng Man Kin of Messrs Kwok, Ng & Chan for the Applicant. Mr. Andy Lam instructed by Messrs Ivan Tang & Co. for the Respondent. |
Cases cited in this judgment
Other judgments that cite this case