Ma Chung Lam and Others v. Citybase Property Management Ltd
Read the full judgment text of CACV 248/2005 on BabelCite. This Court of Appeal judgment was delivered on 25 May 2006.
1. The applicants are the owners of Flat A, 5/F, Block 7 Monte Vista, No. 9 Sha On Street, Shatin, New Territories (“Flat 5A”).
Cited by 3 cases · Cites 3 cases
|
CACV 248/2005 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 248 OF 2005 (On appeal from Lands Tribunal Application No. LDBM 334 of 2004) ______________ BETWEEN
______________
Before: Hon Woo VP, Yuen and Tang JJA in Court Date of Hearing: 11 May 2006 Date of Judgment: 25 May 2006 _______________ J U D G M E N T _______________
Hon Tang JA (giving the judgment of the Court): 1.The applicants are the owners of Flat A, 5/F, Block 7 Monte Vista, No. 9 Sha On Street, Shatin, New Territories (“Flat 5A”). 2.The respondent is the manager of Monte Vista (“the Manager”). 3.By application dated 20th October 2004, the applicants claimed against the respondent in the Lands Tribunal for damages for breach of the respondent’s duties as manager under the Deed of Mutual Covenant and Management Agreement (“the DMC”) dated 22 June 2000. 4.The claim arose out of the flooding of Flat 5A. The flooding was caused by the overflowing of water from the common drain pipes which were connected to the two split type air-conditioning units installed inside Bedrooms Nos. 1 and 2 in Flat 5A. 5.The applicants were out of Hong Kong from 29 April 2004 to 24 July 2004. 6.The flooding probably started on or before 16 June 2004 when the occupier of Flat 3A, which was directly below Flat 5A (there was no 4/F), noticed that water was dripping from the ceiling above the dining room which was near the kitchen and the main entrance. 7.The flooding was not stopped until 23 July 2004. 8.Mr K M Chong, who appeared for the applicants, submitted that the respondent’s liability could be put on two different bases:
9.The provisions of the DMC relied on in the Statement of Claim are the following:
10.The Manager’s duties are not absolute duties. In Lo Yuk Chu v Hang Yick Properties Management Ltd [1996] 4 HKC 278 where a registered owner sued the manager for negligent breach of DMC for consequential loss caused by flooding as a result of a blocked sewage pipe, Power Ag CJ (as he then was) giving the judgment of Court of Appeal, said at page 282:
11.Mr Chong submitted that under section VI, (B)1(1) of the DMC, the Manager should have undertaken regular inspection. 12.The evidence is not clear but it seems that we are concerned with a closed system of drainage for condensation from split type air-conditioners. There was no evidence that it was in accord with proper maintenance practice for inspections to be carried out regularly or periodically. Indeed the fact that the blockage in this case was not discovered until after scaffoldings were erected outside Flat 5A and the pipe exposed makes it unlikely that the pipes were designed to require regular inspection. 13.That view is supported by the evidence of Mr Peter W T Wong, Managing Director of Toplis and Harding Risk Management Ltd, who was relied upon as an expert by the applicants. 14.Mr Wong said in chief:
15.Mr Chong also submitted that proper action should be taken if there was any indication of malfunction. Mr Chong said that according to the evidence of Ms Ko Mee Ling Annie, who is an Assistant Property Officer in the employ of the respondent, there were past episodes of water dripping from air-conditioners. 16.This is what she said under cross-examination at page 56 of the transcript:
17.But as Ms Audrey Eu SC, counsel for the Manager, pointed out, the matter was not explored in cross-examination and it is not known what was the cause of the water dripping mentioned by Ms Ko in her evidence. 18.The fact that the matter was not explored came as no surprise. It was never pleaded on behalf of the applicants that the duty of the Manager to inspect arose out of indications of malfunction or complaints in the past. 19.It follows from the above that we are of the view that the claim by the applicants that the Manager was under a duty to inspect the drainage pipes regularly or as a result of indication of malfunction has not been established. 20.As for the cause of the overflowing of water, according to the report of Mr Peter W T Wong, dated 25 August 2004:
21.In his oral evidence, Mr Wong confirmed his report. In his evidence, he elaborated on the first cause, namely, the blockage was caused by dust or dirt accumulated over time. This is what he said at page 27 of the transcript:
22.The Deputy Judge held that on the evidence before him he was not satisfied that the flooding was caused by the blockage of the pipes. Mr Chong submitted that the Deputy Judge was wrong. We do not believe it is necessary to decide this point, having regard to our view that, no case of breach of duty has been made out against the Manager. 23.Mr Chong submitted that the applicants have an alternative claim based on common law negligence. 24.Even if that cause of action could be said to have been pleaded, it was expressly abandoned when the Deputy Judge raised the question of lack of jurisdiction of the Tribunal over such a claim. No argument was addressed to us on the jurisdiction of the Tribunal over such a claim. In any event, the duties of the manager at common law could not be wider than as stated in Lo Yuk Chu. 25.We turn to consider whether the loss and damage suffered by the applicants could wholly or in part be attributed to the failure of the Manager to take proper remedial action after the commencement of the overflowing. 26.As noted above the flooding probably started on or before 16 June 2004. On 16 June 2004, the occupier of Flat 3A, which was directly below Flat 5A, noticed that water was dripping from the ceiling above the dining room, which was near the kitchen and the main entrance. That matter was reported to the security office of the Manager. The Manager tried to gain access to Flat 5A. But as Flat 5A was unoccupied, they were unable to gain access. They tried the emergency numbers given by the applicants to the Manager, but there was no answer. The same day, they turned off the fresh water supply to Flat 5A. 27.On 17 June, the Manager tried again to contact the applicants through their emergency numbers without success; they issued two “awaiting your return” notices to the applicants. They also inserted newspapers into the applicants’ flat and could detect no water on the floor. 28.On 19 June, they invited contractors to put in tender for the following work:
29.The contractors were required to put in tender on the same day. 30.On 21 June 2004, flush water supply at Block 7 was cut off from 4 pm to 9:30 am, flush water supply to Flat 5A could not be cut off individually before the contractor Vicki Engineering Ltd completed its work. 31.We would add that in order to find out the source of the leakage, the Manager also tried to gain access into 6A. However, the owner of 6A was unwilling to allow the Manager to have access. Also, in an effort to contact the applicants, the Manager contacted the bank through whom management fees for Flat 5A were paid to see if there were ways of contacting the applicants. However, the Manager was told by the bank in question that there was no way in which the applicants could be contacted. 32.Mr Chong submitted that 21 June 2004 was the watershed and that the manager should have realised after that date that the water was coming from the air-conditioners in the bedroom. 33.Ms Eu has supplied us with a helpful summary of actions taken by the Manager:
34.It is on the basis of the evidence narrated above that one should consider whether it could be said that the Manager had failed to take proper remedial action. We do not believe that could be said at all. Nor do we believe it has been established that the manager should have realised by 21 June 2004 that the water was coming from the air-conditioners in the bedrooms. 35.Mr Chong argued that in the circumstances what the Manager should have done was to have broken into Flat 5A. He said there was power to do so under section 40 of the Building Management Ordinance, Cap. 344. 36.The Deputy Judge was of the view that the Manager should have broken into the unit to inspect and to carry out the repair work and that the Manager was guilty of wilful default in failing to do so. He said at para. 26:
37.The Deputy Judge referred to the fact that the Manager could have invoked section 40 of the Building Management Ordinance. 38.Section 40 provides as follows:
39.There was no management committee; so section 40 could not have been invoked. Nor do we believe that in the circumstances of this case, a magistrate would have authorized breaking into Flat 5A. 40.Mr Chong also referred to Section III B of the DMC which provides as follows:
41.This was not relied on below. In any event, we do not believe that a case of emergency has been made out. In this respect, it is useful to look at the contemporaneous record kept by the Manager. It is clear from the entry made on 25 June 2004, that the quantity of water leaked was half a bucket every 12 hours before 25 June 2004, which was reduced to a quarter of a bucket every 12 hours.
42.We do not believe that this would qualify as an emergency justifying breaking into Flat 5A. The power given under DMC has to be read together with section 40 of the Building Management Ordinance, which required a court order before any premises could be broken into. We believe that “emergency” in the context must refer to an event or incident involving serious danger to persons or property which would brook no delay. As Ms Eu has pointed out, in the New Shorter Oxford English Dictionary, under “emergency” these entries appear:
43.We believe that there was no emergency. For the same reason we believe no magistrate would have made an order under section 40. 44.Furthermore, we do not believe that even if the circumstances were such that the Manager could have invoked the emergency power, a case of wilful default has been made out. 45.In Hoi Kong Container Services Co Ltd v Bewise Motors Co Ltd [1997] 2 HKC 615 it was held that one is not guilty of wilful negligence “unless he knows that he is committing, and intends to commit, a breach of his duty, or is recklessly careless in the sense of not caring whether his act or omission is or is not a breach of duty”. (at 626 - 627) 46.The Deputy Judge has not explained why he thought the failure to use such emergency power amounted to wilful default. We see no evidence of wilful default. Indeed we find that the manager has throughout acted with commendable professionalism. 47.For the above reasons, the appeal is dismissed. 48.We also make an order nisi that the respondent is to have the costs of the appeal, to be taxed if not agreed.
Mr K M Chong and Mr Stephen Fong, instructed by Messrs Damien Shea & Co., for the 1st and 2nd Applicants (Appellants). Ms Audrey Eu, SC and Mr Herbert Au-Yeung, instructed by Messrs Clyde & Co., for the Respondent. |
Cases cited in this judgment
Other judgments that cite this case