Skk (Hong Kong) Co Ltd v. Cheong Shing Repair & Maintenance Ltd
Read the full judgment text of DCCJ 4734/2003 on BabelCite. This District Court judgment was delivered on 2 March 2006.
103. “There should be judgment in favour of the Plaintiff and against the Defendant in the sum of $518,066.17. The Defendant's counterclaim is dismissed.”
Cited by 1 case
|
DCCJ4734/2003 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISISTRATIVE REGION CIVIL ACTION NO. 4734 OF 2003 ___________ BETWEEN
__________ Coram: Deputy District Judge J. Ko in Court Dates of Hearing: 31st October, 1st - 3rd November and 1st - 2nd December 2005 Date of Plaintiff's Written Reply: 9th December 2005 Date of Handing Down Judgment: 11th February 2006 C O R R I G E N D U M 103. “There should be judgment in favour of the Plaintiff and against the Defendant in the sum of $518,066.17. The Defendant's counterclaim is dismissed.” should be read as: -
Dated the 2nd day of March 2006
|
Other judgments that cite this case
Further hearings and rulings under DCCJ 4734/2003