Sunley Engineering & Construction Co Ltd v. Ngo Kee Construction Co Ltd

Case No.HCCT 49/2002
Court
高等法院原訟法庭
Date13 Dec 2006
JudgeThe Honourable Mr Justice Burrell
Case Document
100%

HCCT 49/2002

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ONSTRUCTION AND ARBITRATION PROCEEDINGS NO. 49 OF 2002

----------------------------

BETWEEN

  SUNLEY ENGINEERING & CONSTRUCTION CO. LTD. Plaintiff
  and  
  NGO KEE CONSTRUCTION COMPANY LTD. Defendant

------------------------

Before : The Honourable Mr Justice Burrell in Court

Dates of Hearing : 3 – 6, 9 – 12 October 2006

Date of Submission of Written Final Submissions : 3 November 2006

Date of Judgment :  13 December 2006

----------------------

CORRIGENDA

----------------------

Kindly note the following corrections in the aforesaid Judgment:

(1)     At page 22, paragraph 74, after item (13) add the following:

“(14)   Agreed variations           517,018”

(2)     At page 22, paragraph 74, line P, the sum “7,592,858” should read “8,109,876”.

(3)     At page 35, paragraph 115, line S, the figure “$6,843,309” should read “$7,360,327”.

(4)     At page 35, paragraph 115, line T, the date “21 June 2001” should read “2 June 2001”.

(5)     At page 36, paragraph 115, line B, the figure “$2,571,583” should read “$2,764,659.81”.

(6)     At page 36, paragraph 115, line C, the figure “$1,687” should read “$1,764.46”.

Dated the 10th day of January, 2007.

  (Eva LEE) (Ms)
Clerk to Hon Burrell J