Zhang Qiyun v. Shun Shing Construction & Engineering Co Ltd

Case No.HCA 1155/2007
Court
High Court CFI
Date15 Mar 2010
Judge
Case Document
100%

HCA 1155/2007

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

ACTION NO. 1155 OF 2007

____________

BETWEEN

  ZHANG QIYUN Plaintiff
  and  
  SHUN SHING CONSTRUCTION &
ENGINEERING CO LTD
Defendant

____________

Before:     Hon Saunders J in Chambers

Date of Hearing:     11 February 2010

Date of Decision:     15 March 2010

__________________

CORRIGENDA

__________________

Please note the following corrigenda in the Decision of the above-mentioned case handed down on 15 March 2010:-

Page 7, between line
(D) and line (F)
“but in complicated building contract contractor should be allowed to choose the employer which was working for or to whom it was providing services” should be substituted by “that in complicated building contracts, the contractor should be allowed to choose the employer who he was working for or to whom he was providing services”
   
Page 9, line (D) “rights to all” should be substituted by “rights at all”
   
Page 9, line (N) “concerns” should be substituted by “serves”

Dated the 25th day of March 2010.

  (Vicky Wong) (Ms.)
Clerk to The Hon. Saunders J
Other Judgments in This Case

Further hearings and rulings under HCA 1155/2007