The Queen v. Sime Darby Property Services Ltd
|
MA No. 239 of 1993 ------------------- HEADNOTE ------------------- Construction Sites Safety Regulations Cap.59 - Air-conditioning cooling towers not part of building - not construction site. IN THE SUPREME COURT OF HONG KONG (Appellate Jurisdiction) MAGISTRACY APPEAL NO. 239 OF 1993 ------------------- BETWEEN
------------------ Coram : Hon Bewley, J. in Court Date of hearing : 18th June 1993 Date of delivery of judgment : 9th June 1993 ----------------------- J U D G M E N T ----------------------- 1. The appellant was convicted by Mr Tam in Tsuen Wan Magistrate’s Court on 26th February 1993 on an information which was in these terms :-
2. The appellant was fined $48,000 and now appeals against both conviction and sentence. 3. The following facts were admitted :-
4. The only prosecution witness was a factory inspector who testified, as an expert, that there should be railings along the workers’ route to the cooling tower. In particular he said that a railing might prevent a slip from the 30˚ slope to the asbestos roof. If it was raining the risk of this was much greater. 5. The General Manager of the appellant, Lam Kit-leung, gave evidence for the defence. He said that there were seven sets of air conditioning plants in the building and each had a “cooling tower or condenser” on the roof. The cooling towers could also be placed outside a window on a frame. He also said, rather strangely, condenser and cooling tower doing same function - only difference is power - one by water one by air.” He also said that the demolition of all cooling towers and the installation of window-type air-conditioners would not affect the building at all. He was not cross-examined. 6. In his statement of findings the magistrate, after setting out the prosecution and defence cases, said he was satisfied that, so far as was reasonably practicable, suitable and sufficient safe access to and egress from the cooling towers on the roof of the building was not properly maintained. 7. That sentence triggers the first ground of appeal, namely that the appellant was charged with failure to provide, not with failure to maintain, such access and egress. The magistrate has addressed the wrong charge. In the absence of any findings relating to the actual charge, the appeal must be allowed and the conviction quashed. As the question of a retrial arises, it is necessary to consider the remaining grounds of appeal. 8. Mr Macrae, who appears for the appellant, submits that the magistrate erred in holding that maintenance of the cooling tower on the roof amounted to maintenance of the building. 9. The appellant’s liability is as a contractor responsible for a construction site. That, according to Regulation 2, means a place where construction work is undertaken. “Construction work” is defined in section 2 of the ordinance as, inter alia, repair or maintenance of any structure or works specified in the Third Schedule. This includes :-
10. It is admitted that the cooling towers were part of the air conditioning plants. Item 10 draws a distinction between plant and structure. Is an air conditioning plant an integral part of a building? There is no evidence to that effect. 11. The magistrate held :-
12. In Hutchison v. Cocksedge and Co Ltd (1952) 1 AER 696 it was held that the defendants were engaged not “in the construction ... repair or maintenance of a building” within the regulations, but in providing plant for a building, and therefore there was no breach of any statutory duty by them. Mr Macrae argues that, on this authority, maintaining plant is not maintaining a building. 13. In Price v. Claudgen Ltd (1967) 1 AER 695, the appellant, an electrician, was on the roof of a cinema, leaning over the edge and joining electric wires of a neon lighting installation, which was on the face of the building, in order to remedy a defect. The installation consisted of neon tubes outlining the features of the outside of the front of the cinema. The installation had been fixed and was maintained by the appellant’s employers; it was held in place by clamps attached to pins driven into the masonry. The current was suddenly switched on from inside the building. The appellant received a shock, fell off the roof and was injured. On appeal in an action by him against his employers for alleged breach of duty under reg.24 of the Building (Safety, Health and Welfare) Regulations, 1948, it was held that the operation on which the appellant was engaged was not repair or maintenance of a building within reg.2(1) of the regulations, since the neon installation was not part of the building but was something that was on the building; accordingly the regulations did not apply and no breach of statutory duty was established. 14. Lord Morris of Borth-Y-Gest said at p.698 :
15. However he was careful to say that the decision rested on the particular facts and concluded :-
16. I agree with Mr Macrae that it depends on the degree of attachment and the ease of removal. Mr Lam’s unchallenged evidence that the cooling towers could be placed on a frame outside a window and that window-type air conditioning could be installed instead persuades me that the removal of the cooling towers would not affect the nature of the building. The workers were therefore not repairing or maintaining a building. 17. The magistrate also found that the cooling towers fell into the category of water installation, included in Item 9 of the Third Schedule, and thus brought the maintenance work within the definition of “construction work”. His reasoning ran thus :-
18. There was no evidence that the cooling towers stored water. Nor was there evidence about the working of an air conditioning unit. It is certainly -to a layman - a complicated process involving gas, electricity, air and water. In the absence of such evidence I consider that the magistrate was not justified in coming to his conclusion. 19. Moreover, if it had been intended that air-conditioning plant should be a “specified structure or work” it would have been included in Item 9 of the Third Schedule. 20. I conclude that the appellant could not properly be convicted on an information laid under regulation 38A. The appeal is allowed and the conviction quashed. The fine if paid should be repaid to the appellant.
Miss Opai, Crown Counsel, for Crown Mr Macrae, instructed by M/s Fairbarin Catley Low & Kong, for appellant |
Other judgments that cite this case