Lin Yanjin v. Smart Billion Engineering Ltd

Case No.HCPI 739/2009
Court
High Court CFI
Date10 Aug 2011
Judge
Case Document
100%

HCPI 739/2009

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

PERSONAL INJURIES ACTION NO. 739 OF 2009

_________________________

BETWEEN

  LIN YANJIN Plaintiff
  And
  SMART BILLION ENGINEERING LIMITED Defendant

_________________________

Coram : Before Master Marlene Ng in Chambers (open to the public)

Dates of Hearing : 26 July 2011 and 4 August 2011

Date of Handing Down Decision : 10 August 2011

_____________________

C O R R I G E N D A

_____________________

Kindly note the following corrigenda in the Decision handed down on 10 August 2011:-

at page 65, paragraph 148, line 21

“…refusing to defer such costs for argument (ie which contrary contention by the Plaintiff Defendant is tantamount to leaving the matter of liability for such costs wholly at large) is not unreasonable…”

Dated 22 August 2011

(Ms T Au)
Clerk to Master Ng