Sne Engineering Co Ltd v. Chim Kee Machinery Co Ltd
Read the full judgment text of HCA 1313/2012 on BabelCite. This High Court CFI judgment was delivered on 23 August 2012.
1. This decision on costs concerns the costs of and occasioned by:
Cites 1 case
|
HCA 1313/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 1313 OF 2012 ____________
Before: Hon Chung J in Chambers Date of Hearing: 10 August 2012 Date of Decision on Costs: 23 August 2012 ___________________________ DECISION ON COSTS ___________________________ Introduction 1.This decision on costs concerns the costs of and occasioned by:
2.The main issues raised by the defendant during the hearing on 10 August were:
Background 3.It is common ground the dispute in this action was concerned with an MTR Corporation Ltd. (“MTR”) construction site known as “Nam Cheong Property Foundation Removal and Reprovisioning site — the Express Rail Link 802” (“the Site”). 4.MTR was the Site’s employer and Hsin Chong Construction Co Ltd (“Hsin Chong”) was its main contractor. The plaintiff was one of Hsin Chong’s sub-contractors. The plaintiff entered into a machinery hire agreement with the defendant for the supply of some of the equipment and machinery needed by the plaintiff (“the hiring agreement”). 5.The injunction order (as amended) in short compelled the defendant to remove certain construction equipment and machinery (“the deft’s machines”) from the plaintiff’s part of the Site. Material non-disclosure 6.At the ex parte hearing, the plaintiff lodged with court a 4-page skeleton argument. There was also a supporting affirmation of about 12 pages; attached to this were over 370 pages of documentary exhibits. 7.The ex parte skeleton argument has the following headings:
8.The plaintiff’s case set out in the part of the skeleton argument at para 7(e) above can be summarized as follows. The defendant has no right to be present at the Site since 3 July 2012, the date of termination of the hiring agreement. Any continued presence of the defendant would (at worst) cost the plaintiff its contract with Hsin Chong, and (at best) cause delays to the works at the Site. 9.The history leading to the ex parte application was more complicated than that set out in the plaintiff’s skeleton argument. Parts of the history can be found in the plaintiff’s supporting affirmation:
10.In relation to para 9(10) above, at the 10 August hearing the plaintiff fairly accepted it asked Hsin Chong if permission to remain had been given because it suspected a secret agreement might have been reached between Hsin Chong and the defendant. 11.The latter parts of the supporting affirmation then narrated the subsequent correspondence between the plaintiff, the defendant, the Hsin Chong’s project manager concerning the steps to be taken for the removal of the deft’s machines, such as the provision of a demobilization schedule, obtaining MTR’s consent for demobilization, and the plaintiff’s repeated requests for Hsin Chong to withdraw its earlier threat to terminate the sub-contract between itself and the plaintiff. 12.The court records show that the ex parte hearing on 24 July lasted for about 8 to 10 minutes. 13.The principles relating to the applicant’s duty to make full and frank disclosure at ex parte applications are trite. Hong Kong Civil Procedure 2012, Vol 1 says:
14.Hong Kong Civil Procedure 2012 also says:
15.The decision of the English court of appeal in National Bank of Sharjah v Dellborg (1992) The Times (24 December 1992) was cited as the authority for the last-mentioned legal proposition. The court also said in that decision:
16.As stated above, the supporting affirmation disclosed a history which was much more complicated than that stated in the plaintiff’s ex parte skeleton argument. In addition, three matters have not been disclosed at the ex parte hearing (at the very least, they were not properly and/or sufficiently brought to the court’s attention):
17.Finally, the need for the plaintiff to make the application ex parte was the imminence of Hsin Chong’s threat to terminate its sub-contract with the plaintiff (Hsin Chong’s letter of 18 July giving the plaintiff 7 days’ notice to rectify its defaults):
18.Further to the need in the plaintiff’s skeleton argument to draw the court’s attention at the ex parte application to the more complicated history summarized in para 9 above, the plaintiff should also have made proper disclosure of the matters set out in para 16 above. 19.By reason of the above matters, I am satisfied that there has been material non-disclosure on the plaintiff’s part. 20.It ought to be mentioned (though this did not affect the determination of this aspect) in a letter dated 27 July 2012, MTR expressed certain surprise about the plaintiff’s action:
Need for ex parte application 21.The ex parte application was not made on the basis that there was a need to keep the legal proceedings confidential and without warning to the defendant. Thus, the only basis for so applying must be urgency which justified a departure from the normal mode of application (by way of inter partes hearing). 22.I also agree with the defendant the plaintiff has failed to establish a proper/sufficient case of urgency. 23.The matter put forth by the plaintiff as constituting urgency was Hsin Chong’s threat to terminate the sub-contract with the plaintiff (para 8 and 17 above). But any urgency so arising was at least partly caused by the plaintiff:
24.This is particularly so taking into account Hsin Chong’s threat made in early July (para 9(6) and (7) above). 25.Moreover, in a letter dated 19 July 2012, the defendant’s solicitors expressly informed the plaintiff the defendant intended to vigorously defend any application for injunction which the plaintiff might make. Regrettably, this has apparently been ignored by the plaintiff. 26.Finally, as must have been well known to legal practitioners, a “summons day” is available practically every Friday to deal with interlocutory injunction applications (the Friday following 3 July (para 8, 9(5) and 23(1) above) was 6 July, that following 11 July (para 9(8) and 23(2) above) was 13 July and that following 24 July was 27 July). Conclusion 27.By reason of the matters above, both the ex parte injunction order and the inter partes injunction order should have been discharged. 28.Accordingly, this is an appropriate case for the costs of and occasioned by those orders to be paid by the plaintiff to the defendant to be taxed if not agreed. Other matters 29.Events subsequent to the grant of the injunction orders (whether in the original or the amended version) have overtaken the need for the injunction orders. The parties have thus sensibly consented to their discharge at the 10 August hearing. 30.The relief sought in the action (which was substantially the same as that sought in the ex parte and inter partes hearings) is likewise rendered academic by now. The plaintiff has again sensibly sought leave to withdraw this action with costs to the defendant to be taxed if not agreed.
Mr James Sherry, instructed by Robert Lee Law Offices, for the plaintiff Mr Jonathan Wong, instructed by Tsui & Co, for the defendant Please refer to HCMP2863/2012 for the relevant appeal(s) to the Court of Appeal. | |||||||||||||||||
Cases cited in this judgment
Further hearings and rulings under HCA 1313/2012