Sne Engineering Co Ltd v. Chim Kee Machinery Co Ltd
Read the full judgment text of HCA 1313/2012 on BabelCite. This High Court CFI judgment was delivered on 6 December 2012.
1. This is the plaintiff’s application for leave to appeal to the court of appeal. The subject-matter of the intended appeal was the costs order I made on 23 August 2012 (“ the said costs order ”). By the said costs order, costs of the ex parte injunction order and the inter partes injunction order were awarded against the plaintiff.
Cited by 3 cases · Cites 6 cases
|
HCA 1313/2012 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 1313 OF 2012 ____________
____________
______________ D E C I S I O N ______________ INTRODUCTION 1.This is the plaintiff’s application for leave to appeal to the court of appeal. The subject-matter of the intended appeal was the costs order I made on 23 August 2012 (“the said costs order”). By the said costs order, costs of the ex parte injunction order and the inter partes injunction order were awarded against the plaintiff. BACKGROUND 2.The background leading to this action has been briefly stated in the decision on costs handed down on 23 August 2012 (“the 23 August decision”). The background leading to this application is briefly stated below. 3.This action arose from a sub-contract concerning a construction site the owner of which was the MTR Corporation Ltd (“MTR”) and the main contractor of which was Hsin Chong Construction Co Ltd (“Hsin Chong”) (“the said site”). The plaintiff was one of Hsin Chong’s sub-contractors whereas the defendant was one of the plaintiff’s sub-contractors. The defendant was to supply certain machinery to the plaintiff for use at the said site (“the said machinery”). 4.This action was commenced in July 2012. Shortly before the issuance of the writ herein, the plaintiff sought, and was granted, an ex parte injunction order in short enjoining the defendant to immediately remove the said machinery from the said site. 5.By 30 July 2012 (the hearing of the defendant’s application to discharge the ex parte order), however, Hsin Chong has earlier (on 25 July (according to the plaintiff) or 26 July (according to the defendant)) taken back a major part of the said site from the plaintiff. Further, Hsin Chong has engaged the defendant to supply the said machinery to itself (on 27 July). The ex parte order has to be, and was, varied on 30 July as a result. 6.Further, by the time of the hearing leading to the said costs order (10 August 2012), the ex parte order and the inter partes injunction order no longer served any useful purpose. They were discharged by the parties’ consent. 7.Finally, by the time of hearing of this application, there was the unusual situation that it was the defendant (and not the plaintiff) who remained at the said site. THE SAID COSTS ORDER 8.In gist, the said costs order was premised on:
As will be made apparent below, the above two aspects were related. THIS APPLICATION (a) Full and frank disclosure 9.The plaintiff’s first main complaint is that full and frank disclosure has been made in its supporting affirmation used at the ex parte application. This, so it is argued, shows that the part of the 23 August decision summarized in para 8(a) is wrong. 10.The fact referred to in the above complaint has not been overlooked in the 23 August decision; in fact, it was expressly dealt with there (para 6 to 9, 11 and 16 thereof). The criticism in the 23 August decision was in essence directed at the 4-page ex parte skeleton argument not having fairly put forth the rather complicated factual background which preceded the ex parte application. The summary given therein at para 7 to 8 (concerning the said skeleton argument) and that given at para 9 and 11 (concerning the supporting affirmation and some of its exhibits) shows the main differences between them. 11.The plaintiff has obtained, and relies heavily on, the transcript of the ex parte hearing at this application (it was not available at the earlier hearing before me, though the 23 August decision already noted that the ex parte hearing lasted for about 8 minutes only (para 12 thereof)). The transcript confirms the length of the ex parte hearing. 12.Before discussing this complaint further, it should be mentioned that two things are shown by the transcript:
13.The plaintiff emphasized the part of the transcript (at the beginning of the ex parte hearing) where the court indicated it has read “the papers” (referring to the court documents placed before the court (which would include the skeleton argument, the supporting affirmation and the exhibits)). 14.It is true the court made that indication. However, there were two remarks made by the court almost immediately afterwards which should reasonably have alerted the plaintiff to its duty of full and frank disclosure. 15.First, the court then said:
Thus, it must be obvious to the plaintiff the court thought it to be a simple case of trespass. 16.As has been observed in the 23 August decision, the case was more complicated than that:
17.Para 16(a) above can affect the ex parte court’s assessment of the plaintiff’s case in trespass. Para 16(b) above is relevant to the grant of relief (for example, whether the removal of the said machinery should be immediate and/or whether such removal should be subject to the consent and/or direction of Hsin Chong and/or the MTR, and so on); this may also be relevant to the suitability of an ex parte application (see para 34 to 35 and 36(4) below). 18.If it is said that the court’s remark quoted at para 15 above was not sufficiently obvious to the plaintiff, the second remark ought to be. The court also said at the ex parte hearing:
The query was very probably about Hsin Chong’s notice to terminate the plaintiff’s sub-contract (judging from the plaintiff’s reply at the ex parte hearing, it was probably also how the plaintiff understood the query). 19.The plaintiff’s justification for making the application on an ex parte basis was built wholly on Hsin Chong’s imminent termination of its sub-contract. This is made apparent by the plaintiff’s ex parte skeleton argument (para 3 to 6 thereof (under the heading “Ex Parte application for Mandatory injunction”) and para 14 and 16 (“Background”)). 20.As has been noted in the 23 August decision, the said skeleton argument was a short 4-page document (para 6 thereof). The skeleton argument says this about the risk of sub-contract termination:
(emphasis supplied) 21.The significance of the above quotes is that they made clear the sub-contract between Hsin Chong and the plaintiff provided for a 2-stage procedure for termination: a 7-day notice of intention to do so, followed by the actual notice of termination (the supporting affirmation and the exhibits for use at the ex parte hearing are consistent with that; Hsin Chong’s said notice of intention to terminate was referred to at para 25 to 26 of the supporting affirmation (a 12-page document (consisting of 41 paragraphs)) (para 6, the 23 August decision)). They also made clear that the earliest time for Hsin Chong to exercise its termination right would be 25 July (the day following the ex parte hearing). 22.What the query ought to have shown to the plaintiff was that the court might not have fully understood the said 2-stage procedure (perhaps because the court documents were read within a short time period). This should alert the plaintiff to the real possibility the court might not have had the opportunity to read the rest of the court documents as thoroughly as desired. 23.Having been so alerted, and bearing in mind the duty to make full and frank disclosure, the plaintiff ought to have given more assistance to the court in the manner set out below. 24.As observed in the 23 August decision, the duty of full and frank disclosure is trite (para 13 to 15 thereof). Ultimately it rests on the rationale that, appearing as the only litigant, an applicant must act with the highest good faith (see also, for example, NCS Co Ltd v Bao Harvest Holding Ltd [2012] 5 HKLRD 138, para 30). 25.In Falcon Private Bank Ltd v Borry Bernard Edouard Charles Ltd and Another HCA1934/2011 (9 July 2012), it was said this duty will entail (among other things):
26.The plaintiff also argues in this application that the quantity, size and weight of the said machinery have specifically been drawn to the court’s attention at the ex parte hearing. But I notice that the submission was made apparently with a view to justify the need for a mandatory injunction (rather than to drew the court’s attention to the matters mentioned in para 17 above). 27.In view of the above, I consider that:
28.Finally, although the passages in Hong Kong Civil Procedure 2012, Vol 1 (quoted in the 23 August decision (para 13 to 15)) referred to disclosing the material facts in the supporting affidavit (as opposed to its exhibits), I do not consider the learned authors to be saying that the law limits the applicant’s duty to do only that; rather, that was only meant to be an instance of his broader duty of highest good faith. What the law requires of him is to present the case in the fairest possible manner (see para 24 to 25 above). As to what precisely needs to be done is a matter which varies with the circumstances of each case. (b) Urgency 29.Before considering this aspect, the underlying legal principles should be re-stated. During the hearing of this application, the parties’ attention has specifically been drawn to the following authorities (in chronological order):
30.The court in the Seapower decision made a graphic description of what “urgency” should mean in this context:
31.The court in effect echoed this in the Slik Hong Kong decision:
32.The L v C decision contains quotes from the English authorities TRP Ltd v Thorley (unrep) (English court of appeal, 13 July 1993) and Re First Express Ltd [1991] BCC 782, 785. Thus,
The quoted passages were probably the origin from where the courts’ observations (also quoted above) in the Seapower decision and the Slik Hong Kong decision were founded. 33.In this connection, the following part of the plaintiff’s submission in this application is also relevant:
34.It is unclear from the quoted passage if the plaintiff is agreeable to such a period being given to the defendant for complying with the ex parte order (despite the use of the word “immediate” in the order). As a matter of reality (that is, considering the quantity, size and weight of the said machinery), it seems the plaintiff would have not much choice but to so agree. 35.In any event, since it is the plaintiff’s own case Hsin Chong regarded the failure to secure the removal of the said machinery as a contractual breach, any removal commencing from 25 July would not necessarily have prevented Hsin Chong from terminating the contract (Hsin Chong having served the notice of intention to do so earlier); this is because, by then, the breach would have already taken place. 36.Despite the plaintiff’s arguments in this application, I do not find any substance in the complaint to the effect I erred in concluding there was no “such extreme urgency that there is literally no time to warn the defendant”:
37.This aspect of this application thus has no reasonable prospect of success at the intended appeal either. CONCLUSION 38.Accordingly, this application for leave is refused. COSTS ORDER 39.The plaintiff agrees that the costs of this application should be awarded to the defendant if this application is refused. There will thus be an order that those costs be paid by the plaintiff to the defendant. 40.I consider summary assessment of costs to be appropriate. The above costs shall be so assessed. For this purpose:
Mr Anthony James Sherry, instructed by Robert Lee Law Offices, for the plaintiff Mr Sam Tsui, of Tsui & Co, for the defendant Please refer to HCMP2863/2012 for the relevant appeal(s) to the Court of Appeal. | |||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCA 1313/2012