Konwall Construction & Engineering Co Ltd v. Strong Progress Ltd
Read the full judgment text of HCA 1871/2010 on BabelCite. This High Court CFI judgment was delivered on 28 June 2013.
1. By this action, the Plaintiff as buyer sues the Defendant as seller damages for non-delivery of steel bars under a contract.
Cited by 2 cases · Cites 3 cases
|
IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE HIGH COURT ACTION NO. 1871 OF 2010 ____________
_______________ J U D G M E N T _______________ A. THE CLAIM 1.By this action, the Plaintiff as buyer sues the Defendant as seller damages for non-delivery of steel bars under a contract. B. THE FACTS 2.Most of the facts are not in dispute. The main issues of the case relate to the interpretation of the contract concerned, and the existence or otherwise of certain alleged implied terms. I set out the undisputed facts as follows. I will at the same time highlight some of those facts that are in dispute. They are confined to certain specific factual issues relevant to the “factual matrix” against which the contract should be construed. I will consider those disputed facts separately in latter parts of this judgment. 3.The Plaintiff is a Hong Kong company carrying on, inter alia, a building contracting business. The Plaintiff avers that it also carries on trading business. This, however, is disputed by the Defendant. 4.The Defendant is a Hong Kong company which carries on business of trading steel bars. 5.In Hong Kong, as from April 1996, the Construction Standard CS2:1955 (“CS2”) on carbon steel bars for the reinforcement of concrete is adopted by the Buildings Department as an acceptable standard for compliance with the requirements in the Building (Construction) Regulations. The Standard incorporates the full product standard for such steel bars and the requirements for classification and certification of reinforcement by Quality Assured Stockists (“QA Stockists”) and the requirements for the testing of reinforcement by the end purchasers. According to paragraphs 9, 10 and 11 of the Foreword of CS2:-
6.There is no dispute between the parties that CS2 was applicable to the steel bars relevant to this case. 7.The Plaintiff was at all material times not a QA Stockist under CS2. The Defendant was. 8.The origin of the present disputes between the parties can be traced back to their disputes in respect of an earlier agreement entered into in February 2005 (namely Sales Contract No.SP-05006S (“the 2005 Contract”)) whereby the Plaintiff agreed to purchase from the Defendant 8,000 M/T of steel bars of various sizes to be delivered between 2 February 2005 and 31 January 2007. That agreement came about in the following way:-
9.By a letter of 20 September 2006, the Plaintiff wrote to the Defendant and sought some amendments to the 2005 Contract. The Plaintiff said:-
10.In reply, the Defendant by letter of 5 November 2006 agreed to extend the validity of the 2005 Contract. That letter also contained the following paragraph:-
11.Disputes subsequently developed over the performance of the 2005 Contract. Those disputes led to HCA 1707 of 2007 (“the 2007 Action”) in which the Plaintiff sued the Defendant for alleged breach of that contact. 12.The pleadings filed in the 2007 Action are relevant to the present proceedings:-
13.In 2010 the Plaintiff and the Defendant entered into a settlement agreement in respect of the 2007 Action. The terms of the settlement agreement were contained in the schedule (“the Schedule”) of a Consent Summons dated 11th January 2010. Paragraph 1 of the Schedule stipulated that “The Defendant shall supply to the Plaintiff a total quantity of 4,000 MT of steel bars by instalments on or before 31st December 2010 for use in reinforced concrete on the terms and conditions set out in the sales contract no.SP-09068S dated 15th December 2009 endorsed under a letter from the Plaintiff to the Defendant dated 23rd December 2009 (ref: MOC-09-188) and attached hereto”. I will refer to Sales Contract no.SP-09068S as “the Sales Contract”. 14.The Sales Contract contained, amongst others, the following express terms:
15.The express terms of the Sales Contract were arrived at after some negotiations between the parties. Both parties have adduced evidence on some details of those pre-contractual negotiations. Earlier draft terms of the Sales Contract have been produced. Witnesses were called during the trial to speak about them. I will not at this stage set out the relevant evidence in any detail, as its admissibility is in dispute. The consensus between Ms. Cruden and Mr. Maurellet, counsel respectively for the Plaintiff and the Defendant, was that the relevant evidence was adduced on a de bene esse basis, and that I would rule on the issue of admissibility at the end. I allowed that course to be adopted. I will come back to that issue of admissibility. 16.The Defendant does not dispute the validity of the Sales Contract. 17.During the period between April 2010 and August 2010, the Plaintiff pursuant to the Sales Contract ordered in total 89.996 M/T steel bars from the Defendant (“the Fulfilled Orders”). Particulars of those orders were as follows:-
18.The Plaintiff avers that the Defendant had only delivered 89.374 M/T of the Fulfilled Orders. The Defendant says 90.008 M/T had been delivered. That however is not the dispute in this action. The dispute relates to 8 further delivery orders (“the Subject Orders”) for a total of 3,909.927 M/T steel bars placed by the Plaintiff upon the Defendant in November and December 2010. They were placed within a week. Particulars of the Subject Orders were as follows:-
19.Dispute over the Sales Contract first surfaced on about 25 November 2010. According to Mr. Richard Deng, a Director of the Defendant, the Plaintiff suddenly and without any prior notice placed a delivery order on 25 November 2010 for 499.99 M/T of steel bars to be delivered on 30 November 2010. He had in that regard a telephone conversation with Mr. Nelson Kwok, a Project Manager of the Plaintiff. The contents of that conversation were recorded by the Plaintiff in its letter dated 26 November 2010 to the Defendant. In gist, Mr. Deng claimed that the Plaintiff’s delivery order of 25 November 2010 was too late, and that the Defendant could not confirm until 29 November 2010 whether the ordered steel would be ready for delivery on the required date. Mr. Deng further required the Plaintiff to supply the Defendant with the name of the project in which the required steel bars were to be used and a breakdown of sizes. In reply, Mr. Kwok said that the Plaintiff’s orders were in accordance with the terms of the Sales Contract and that a breakdown had been provided. He further said that the Plaintiff had no obligation to state the name of the site in which the steel bars were to be used. 20.On 29 November 2010, the Defendant wrote to the Plaintiff and said that “According to [the Sales Contract], the steel materials should be supplied to your current projects in Hong Kong. And as usual we also need to specify the project name and address in the stockist certificate.” The Defendant further said that “you are required to provide the above information before we arrange the delivery.” That letter was signed by Mr. Richard Deng. 21.What the Defendant said in that letter were disputed by the Plaintiff. In his letter of the same date in reply, Mr. Nelson Kwok said that there was no condition in the Sales Contract requiring that the steels bars should be used only for the Plaintiff’s current projects. He said unless the Defendant could state clearly the contractual basis of the request for the information, the Plaintiff would not provide the requested information to the Defendant. He further said that “[as] for the Stockist Certificate, we confirm you do not need to specify the Job Name on the said Certificate as you had previously done.” 22.In reply, the Defendant in its letter of 1 December 2010 reiterated that it only undertook to supply the steel bars to the Plaintiff’s projects in Hong Kong. They again asked for the Plaintiff’s project details, and said that unless the details were provided, they would not supply the steel bars. That letter was signed by Mr. Terrence Fung, the then Chairman of the Defendant. 23.The Plaintiff replied on the same day, denying again what the Defendant had said in its earlier letter. It was further said that “…it now appears to us that you intend to breach our Sales Contract. We respectfully remind you that we will hold you liable for any loss arisen [sic] from your breach.” 24.In its reply on 2 December 2010, the Defendant said that “We reiterate that we undertake to supply the steel bar to your projects in Hong Kong only, as clearly stated in the [Sales Contract]. For those delivery orders you placed recently without specified project names, we only confirm your intention of delivery order and those orders are ALL incomplete delivery orders. Unless such details are provided, we would not supply the steel bar to you.” 25.On 8 December 2010, the Plaintiff wrote again to the Defendant, but this time through its solicitors (Messrs. Wong & Fok (“W&F”)). What had been said by the Plaintiff in its previous letters were reiterated. Deliveries of the steel bars ordered under the Subject Orders were again demanded. Two points raised in that letter should however be specifically noted:-
26.The Defendant through its solicitors (Messrs. Ho & Ip (“H&I”)) replied on 13 December 2010. The Defendant’s position was reiterated. In particular, it was said that “in accordance with the terms and conditions of the Sales Contract, the steel bars to be supplied by our client are intended to be used ‘under various projects in Hong Kong’. Given the fact that at all material times your client is in the business of contracting, rather than trading of steel bars, this expression in the Sales Contract was clearly meant to refer to various projects in Hong Kong undertaken by your client”. It was further said that apart from for the purpose of issuing stockist certificates, the information requested was required to enable the Defendant to ascertain whether it was obliged to supply the steel bars as ordered. In respect of the Fulfilled Orders, the following were said, that “our client appreciates for your client’s assistance in drawing our client’s attention to such omission. Your client is requested to return those certificates to our client together with the name(s) and address(es) of the project(s) in which the steel bars in question had been used so that our client may re-issue appropriate stockist certificates to your client.” They also objected to the disclosure by W&F of the Settlement Offer in its previous letter. 27.W&F replied on 14 December 2010. H&I’s interpretation of the term ‘under various projects in Hong Kong’ was denied. The Plaintiff’s business was said to cover contracting and trading. In respect of the stockist certificates issued in respect of the Fulfilled Orders, W&F said that the Defendant at all times was fully aware of the absence of project particulars thereon, and that their absence was not the result of any omission. It was maintained that the Defendant had no justification in demanding particulars on the projects prior to delivery. However, W&F then on “an entirely without prejudice basis” proceeded to provide to the Defendant the project name, which was “37-47 Nam On Street / 311-331 Shau Kei Wan Road, Hong Kong”. The Defendant was then required to confirm by 15 December 2010 whether it would make the deliveries. In respect of the Settlement Offer, W&F commented that the offer had never been expressed to be made on any without prejudice basis. 28.H&I replied on 15 December 2010. Arguments were put forward in reply to those raised by earlier by W&F. Additional information on the projects was also sought. In particular, having referred to the project information provided by W&F in its earlier letter, H&I said:-
29.W&F replied on 16 December 2010. I will not repeat all the arguments raised therein by them on the Plaintiff’s behalf. It is noteworthy however that the Plaintiff refused to provide any of the additional project information requested. It was said that “[our] client regrets to note that despite its provision of the project name/address to your client on a without prejudice basis, your client has continuously refused to deliver the steel bars ordered by our client by purported seeking additional information”. The refusal on the part of the Defendant to deliver was commented to be unjustified, and an ultimatum was given that unless the Defendant confirmed by 5:00 pm on 17 December 2010 that it would deliver the steel bars, the Plaintiff would accept the Defendant’s repudiation of the Sales Contract. 30.Ultimately, the Sales Contract was terminated by W&F’s letter of 20 December 2010 whereby the Plaintiff claimed to accept the Defendant’s alleged repudiation. Prior to such termination, the Defendant had only delivered a total of 35.984 M/T under the Subject Orders. 31.According to the Single Joint Expert Report of Mr. Cheung Tat Tong filed for the purpose of these proceedings, the net average market prices in November and December 2010 of the type of steel bars ordered under the Subject Orders were HK$5,778.5 per M/T and HK$5,875.5 per M/T respectively. That represented a substantial rise from the contract prices set out in the Sales Contract, which were, depending upon the type of steel bars, between HK$3,500 per M/T and HK$3,900 per M/T. C. THE PLAINTIFF’S CASE 32.As observed above, the validity of the Sales Contract is not in dispute. The Subject Orders have indeed been placed. On the face of those orders, they were validly placed. Deliveries have been refused. 33.Section 53(1) of the Sales of Goods Ordinance (which Ms. Cruden relies upon) stipulates that:-
D. THE DEFENCE 34.The Defendant does not dispute the validity of the Sales Contract. It also accepts that it has only delivered 35.984 M/T of the Subject Orders. It avers that it was not liable to deliver the balance. The crux of its defence turns upon the interpretation of the Sales Contract and the existence or otherwise of certain alleged implied terms. Its case is this, that:
35.Upon the basis of its case as summarised above, the Defendant avers that prior to 25 November 2010, the Plaintiff had only ordered a small quantity of steel bars. Then, on and after 25 November 2010, and within a week, the Plaintiff placed the Subject Orders. Apart from the address of the project, which the Plaintiff provided on 14 December 2010 on a without prejudice basis, the Plaintiff had failed to provide to the Defendant the additional information as requested so as to enable the Defendant to determine whether the Defendant would be obliged to supply the steel bars ordered. In the circumstances, the Plaintiff was in breach of the Implied Notification Term. On the other hand, if the steel bars were all to be used in the project at the address provided by the Plaintiff on 14 December 2010, the Plaintiff would have been in breach of the Sales Contract in failing to give one month notice to the Defendant prior to delivery. Further, it is averred that in breach of the Implied Delivery Term, the Plaintiff’s notices requiring delivery of the Subject Steel Bars were manifestly unreasonable, such that the Defendant was not obliged to comply with the same. E. THE ISSUES 36.The main issues are as follows:-
F. ADMISSIBILITY OF CERTAIN EVIDENCE 37.I consider first of all the Admissibility of the evidence on (1) the pre-contractual negotiations leading to the conclusion of the Sales Contract, and (2) the Settlement Offer.
38.I refer first of all to Prenn v. Simmonds [1971] 1 WLR 1381, where Lord Wilberforce, having referred to the prolonged negotiations between the parties and their exchanges of draft clauses, observed at p.1384G-1385A and p.1385H that:-
39.In Investors Compensation Scheme Ltd. v West Bromwich Building Society [1998] 1 WLR 896 at 912H-913F Lord Hoffmann summarized the relevant principles as follows:
40.Lord Hoffmann made similar observations in Jumbo King Ltd. v Faithful Properties Ltd. (1999) 2 HKCFAR 279 at 296 D-I, that:
41.In my view, the law is quite clear. For the purpose of interpreting an agreement, the law excludes from the admissible background, or the matrix of facts, the previous negotiations of the parties and their declarations of subjective intent. Evidence of such negotiations is inadmissible. 42.I accordingly rule that all evidence in relation to the pre-contractual negotiations between the parties leading to the conclusion of the Sales Contract is inadmissible. Such pre-contractual negotiations do not form part of the factual matrix against which I construe the terms of the Sales Contract. F.2. Admissibility of evidence on the Settlement Offer 43.H&I on behalf of the Defendant objected to the disclosure of the Settlement Offer. I have summarised the objections expressed in the correspondence. On behalf of the Plaintiff, W&F had not sought to deny that the Settlement Offer was made by the Defendant with the aim of achieving a settlement. What they said in their letter of 14 December 2010 was that “the communication regarding your client’s offer had never been expressed to be made on without prejudice basis.” 44.I refer also to paragraph 15 of Mr. Fung’s witness statement, where he, having referred to the Settlement Offer, said that “that offer was made as a genuine attempt to settle the dispute arisen at that time between the parties…Although I did not expressly use the words ‘without prejudice’ in communicating the offer to Mr. Kwok, I believe it was well understood by him that the offer was made as a genuine attempt to try to settle the dispute between the parties and if the offer was not accepted by Konwall, it should not be disclosed and used against Strong Progress.” 45.Any discussion between the parties for the purpose of resolving the dispute between them are not admissible, even if the words “without prejudice” or their equivalent are not expressly used: Hong Kong Civil Procedure 2013, Volume 1 paragraph 24/5/41, and Chocoladefabriken Lindt & Sprungli AG v. Nestle Co Ltd [1978] R.P.C. 287 cited therein. I rule that all evidence in relation to the Settlement Offer is inadmissible. G. WITNESSES 46.The Plaintiff has called two, they being Kwok Yu Won Eric and Kwok Tai Yuen Nelson, respectively its Managing Director and project manager. 47.The Defendant also has called two, being Richard Deng Rong Hui and Fung Tak Lee, who were respectively a Director and the Chairman of the Defendant. 48.A joint expert, namely Mr. Cheung Tat Tong has also been called. His evidence is relevant to the market price of the steel bars concerned and the quantum of the Plaintiff’s claim. 49.As I have commented above, and as put by Mr. Maurellet when opening, the bulk of the dispute concerns the application of legal principles rather than dispute of facts. While the witnesses have been cross-examined, the areas subject to cross-examination are confined to specific factual matters relevant to, but not determinative of, the main issues, which are the interpretation of the Sales Contract and the existence or otherwise of the alleged implied terms. After all, as has been explained by Lord Hoffmann in Investors Compensation Scheme Ltd. v West Bromwich Building Society, declarations of subjective intent by the witnesses/parties, like pre-contractual negotiations, are inadmissible for the purpose of discovering what a reasonable person would have understand the parties to mean. 50.For the above reasons, I will consider the evidence and state my findings primarily on an issue-by-issue basis when I consider below the relevant “matrix of facts” against which the Sales Contract should be interpreted and construed. H. THE LAW 51.There is little dispute between the parts on the application legal principles. I summarize them as follows. 52.In respect of the law relevant to interpretation of contracts, I repeat the parts of the judgments from Investors Compensation Scheme Ltd. v West Bromwich Building Society and Jumbo King which I have cited above. In particular, I repeat Lord Hoffmann’s observations in Investors Compensation (at 912H), that
53.In Marble Holding Limited v. Yatin Development Limited, (2008) 11 HKCFAR 222, Mortimer NPJ observed at paragraph 20 of the judgment that:-
54.In respect of the law relevant to the implication of contractual terms, I have considered the following matters and authorities. 55.When an instrument does not expressly provide for what is to happen when some events occur, the first question is whether any term in that regard should be implied at all. As observed by Lord Hoffmann in Attorney General of Belize v. Belize Telecom Ltd [2009] 1 WLR 1988 at paragraph 17:-
56.There are however occasions when the court may accede to a party’s request to imply a term from the wording of a particular contract. The relevant principles are explained in Chitty on Contracts, 31st Edition, Volume 1, paragraph 13-004 (which the learned authors called the “Traditional principles”):-
57.That was the approach adopted by the Court of Final Appeal in Twinkle Step Investment Ltd v Smart International Industrial Ltd (1999) 2 HKCFAR 255. In that case, Ching PJ., having referred to Liverpool City Council v. Irwin [1977] AC 239, held (at 261I to 262A) that terms will be implied if it is necessary, in the business sense, to give efficacy to the contract. Reasonableness is however not a ground for doing so. In the same case, Bokhary PJ observed (at page 263D-E) that the question is whether the term contended for is one which the court must imply in order to establish what the contract is, the parties themselves not having fully stated the terms of their contract. 58.At paragraph 13-005 of Chitty, the learned authors explain what is called a “Broader Approach”, that:-
59.However, I do not understand Lord Hoffmann as meaning that the traditional approach should be abandoned altogether. That is quite obvious from what His Lordship has said at paragraph 17 of Belize (op. cit.). I refer also to Chitty (paragraph 13-005), where the learned authors also comment that “…it is clear that Lord Hoffmann did not intend in his broader approach to herald any fundamental change of attitude so as to enable terms to be more easily implied”. 60.In any event, if the approach propounded by Lord Hoffmann does represent a new approach different from that adopted by the Court of Final Appeal in Twinkle Step, I regard myself as being bound by Twinkle Step. 61.However, as I will explain below, I have reached the same decision whether I adopt the so-called “traditional principles” or the “broader approach”. 62.Miss Cruden has also referred me to a number of passages in Chitty relevant to those situations where, it is said, terms should not be implied:-
I. THE FIRST ISSUE - THE INTERPRETATION OF THE PROJECT CLAUSE I.1 Factual Findings 63.In her closing submissions, Ms Cruden approached the interpretation issues in a way as guided by the observations made by Lord Hoffmann in Jumbo King Ltd, namely “having regard, not merely to the individual words they have used, but to the agreement as a whole, the factual and legal background against which it was concluded and the practical objects which it was intended to achieve.” She submitted that all those regards support the Plaintiff’s case. The non-controversial facts I have set out above cover the factual matrix she sought to rely upon (except those pre-contractual negotiations which I have held to be inadmissible). Her position in respect of the 2005 Contract is this, that whilst it is not necessary to construe the same conclusive, it does form part of the factual matrix. 64.In his Closing Submissions, Mr. Maurellet set out his arguments on the First Issue as follows:-
65.Mr. Maurellet invited me to make a number of findings said to be relevant to this issue. I will consider them in the following paragraphs (except those relating to the parties’ pre-contractual negotiations, which I have held to be inadmissible). I find it convenient to consider at the same time also the factual issues said to be relevant to the Second and Third Issues. When considering the evidence, I will primarily consider the question of inherent plausibility or probability. I will also consider the consistency of the evidence. Having stated my findings, I will then come back to discuss their significance and implications during the Discussion Sections of this Judgment. 66.The business the Defendant held itself out to be in:-
67.The business the Plaintiff held itself out to be in:-
68.The durability of steel bars:-
69.The QA Stockist system under CS2:-
70.The 2005 Contract:-
71.The parties’ good business sense:-
72.The price of the steel bars at the time when the Sales Contract was made:-
73.The use of the steel bars under the Subject Orders:-
74.At the time the Disputed Orders were made, D had adequate steel bars in its warehouse to satisfy the Subject Orders:-
75.There are physical limits to the amount of steel that can be removed from D’s warehouse and be made ready for delivery or collection:-
76. The Defendant was interested in setting limits to the quantities of steel that P could obtain on credit:-
I.2 The First Issue - Discussion 77.I start with the textual background of the Sales Contract. 78.The Project Clause said “Under various projects in Hong Kong”. On the face of the Project Clause, there was no express limitation of the type contended for by the Defendant. 79.Nor did the Sale Contract as a whole contained any express limitation of the type contended for by the Defendant. 80.Further, and textually, what was “undertaken by the Plaintiff” intended to mean according to the Defendant’s case? Should that be confined to projects in which the Plaintiff actually carried out the construction works? Or did that include projects in which the steel bars were used by one of the Plaintiff’s sub-contractors? And how about the case of sub-sub-contractors? 81.It is also important to note that the interpretation contended for by the Defendant is not just that “various projects” means “various projects undertaken by the Plaintiff.” It is more detailed than that. According to Mr. Maurellet, the projects of the Plaintiff “would have to be ongoing projects or foreseeable projects in the near future which details are known”. What is “foreseeable projects” supposed to mean? And “near future”? Or does it mean that so long as “details are known”, the projects could be included? None of these appears on the face of the Sale Contract, and none has been defined. 82.Mr. Maurellet submitted that the use of the word “various” as opposed to “any” in the Project Clause supports his contention. I accept Ms. Cruden’s submissions in this regard. We are for the purpose of contractual interpretation concerned with what a reasonable person, but not a pedantic lawyer, would have understood the words to mean. Reading the Project Clause in its entirety (but not the words “various projects” in isolation), the meaning of “Under various projects in Hong Kong” and “Under any projects in Hong Kong” hardly has any difference. 83.Mr. Maurellet then submitted that the Plaintiff’s interpretation would seem to deprive the word “projects” of any purpose, and would render the Project Clause superfluous as a governing criterion. But the words “in Hong Kong” imposed a territorial restriction. Even without the limitation proposed by the Defendant, the Project Clause as a whole still was not superfluous. 84.Mr. Maurellet relied upon the word “projects”, which he submitted was more consistent with “consumption” than “resale”. He further submitted that if the parties had intended that the Plaintiff were allowed to resell the subject steel bars, it is difficult to see why either the Defendant or the Plaintiff could have cared at all about whether the subsequent purchaser had or had not any “project” in hand. These hardly assist the Defendant’s case. Upon resale, the steel bars would still in all probabilities be consumed in some projects by someone. It hardly supports the Defendant’s contention that the steel bars had to be used “under various projects undertaken by the Plaintiff”. 85.I next consider the factual matrix and the factual and legal background against which the Sale Contract was concluded, and the practical objects which it was intended to achieve. 86.The factual matrix I take into account comprises the facts I have recited in Section B and have found in Section I.1. above. 87.At all material times, the Defendant held itself out as a supplier of steel bars for contractors’ construction projects, and not a supplier of steel bars to other suppliers of steel bars for resale. Whilst that is true, it does not mean that the Defendant would necessarily be affected by or concerned about any resale by its customers. Commercial reality suggests that any resale price by the Defendant’s customers would in the normally course of events be higher than the price at which the Defendant sells the same steel, and it is mostly likely that any third party intending to buy would go to the Defendant direct. Permitting resale may not be a problem. Further, as Ms Cruden submitted, once the Plaintiff had become the owner of any steel bars, it would be entitled to do whatever it saw fit with its property. 88.In so far as the business of the Plaintiff is concerned, it did not hold itself out as a trader of steel bars. However, it does not mean that it had ruled itself out from the business of reselling. That was particularly so in respect of surplus steel bars. 89.Here, the case of Defendant runs into some difficulties. Was there any distinction, in so far as the user restriction argued to be imposed by the Project Clause was concerned, between resale of surplus steels and resale simpliciter? If so, where was that distinction drawn in the Sales Contract? How was that supposed to be regulated? These are unanswered queries the Defendant’s proposed interpretation faces. 90.Whilst the Plaintiff has not been a registered QA Stockist, it does not mean that it cannot sell steel bars. I have explained the QA Stockist system above. 91.In so far as the durability of steel bars are concerned, the evidence suggests that they that they could be stored for certain time, to the extent of 1 to 3 years. The evidence does not support the Defendant’s proposition that steel bars “would have to be used for ongoing or reasonably imminent projects”. The Defendant’s case also begs the question as to what “reasonably imminent” means. 92.In respect of the 2005 Contract, I have made my findings above. I do not accept that that contract contained any user restriction. 93.The parties developed disputes in respect of the 2005 Contract. As a result of the pleadings filed in the resulting action, the Defendant became aware that one of the Plaintiff’s complaints in the 2007 Action was that it had lost the opportunity to resell the steel bars concerned. 94.The Sales Contract was entered into to settle the 2007 Action. It was not a casual document. I attach some weight to this particular background fact. As observed by Lord Hoffman in ICS “we do not easily accept that people have made linguistic mistakes, particularly in formal documents” and in Jumbo King “in serious utterances such as legal documents, in which people are supposed to have chosen their words with care, one does not readily accept that they have used the wrong words”. 95.The resulting settlement agreement in the form of the Sales Contract did not contain any express user restriction contended for by the Defendant. Nor did it seek to define or set out the meaning of the words “undertaken by the Plaintiff”, not to mention further details like the meaning of “ongoing projects or foreseeable projects in the near future which details are known”. 96.The Sales Contract, as submitted by Ms. Cruden, was not a usual business contract between the parties. It was entered into to settle the 2007 Action. The 4000 M/T ordered there was not a genuine pre-estimate of the Plaintiff’s needs during the contractual period. The usual business good sense of the parties is hardly relevant. 97.As to the subsequent actual use of the steel bars order under the Subject Orders, I have made my observations above. In any event, I find such subsequent conduct to be of limited relevance when it comes to the question of interpretation. 98.In all the circumstance, I find the Defendant’s contention to be inconsistent with the words used in the Sales Contract as a whole, and in particular that of the Project Clause. It is also not supported by the factual matrix. I find that a reasonable person would not have understood the parties as meaning to impose the user restriction the Defendant is contending for. 99.Further, given the indefinite meaning of terms like “undertaken by the Plaintiff”, “ongoing projects” and “foreseeable projects in the near future”, I find the proposed interpretation too vague as to have been meant by the parties. 100.I reject the Defendant’s defence in this regard. J. THE SECOND ISSUE – INTERPRETATION OF THE SINGLE DELIVER CLAUSE 101.In respect of the Second Issue, Mr. Maurellet argued that “on a proper construction of the Sales Contract, the words “any single delivery equal to or over 1,000 M/T” plainly referred to “the delivery of steel bars to a single project with a total quantity equal to or in excess of 1,000 m/t such that with one month notice prior to delivery the Defendant would have sufficient time to procure the necessary stock of the steel bars required to be supplied for any particular project”, and failure to give such advance notice meant that D's obligation to deliver simply did not arise prior to the Plaintiff’s repudiation of the Contract”. That is also the pleaded case of the Defendant. 102.According to Mr. Maurellet, the term “single delivery” should be interpreted as meaning: -
J.1. The Second Issue – Factual Findings 103.I have in Section I.1 above dealt with the factual issues which Mr. Maurellet submitted to be relevant to this issue. J.2. The Second Issue - Discussion 104.I again start with the textual background of the Sales Contract. 105.Remark 1 provided that “Any single delivery is equal to or over 1,000mt, the buyer shall give the seller one month notice prior to delivery.” It did not expressly say what the Defendant now argues it should have read. 106.In particular, the Defendant’s proposed interpretation seeks to adopt the quantity of steel bars which a project required as a criterion to decide what “a single delivery” was. On the face of Remark 1, there is no reference to such a criterion. Nor is there such a reference in any part of the Sales Contract. 107.The Plaintiff’s case is simply that “the words “Any single delivery equal to or over 1,000 mt” were meant to refer to any single delivery equal to or over 1,000 mt at a time”. 108.Mr. Maurellet argued that on the Plaintiff’s interpretation, Remark 1 is required to be redrafted by deleting the word “Any” and by added the underlined words as follows:
109.I do not agree. The Plaintiff’s version in my view does not require any redrafting of Remark 1. 110.On the other hand, my view is that it is the version proposed by the Defendant which requires extensive redrafting by adding to Remark 1 words which were not there. 111.In particular, Mr. Maurellet contented that the scheme contemplated by the Defendant was that: -
112.The alleged scheme was not simple in its operation. There was no such scheme on the face of the Sales Contract. 113.I next consider the factual matrix. 114.I repeat my consideration of the factual matrix in the context of the First Issue. I have rejected the Defendant’s contention that “under various projects undertaken by the Plaintiff”. That conclusion is also relevant to the consideration of the Second Issue here. I have found that the Plaintiff was at liberty to resell the steel bars. That being the case, the Plaintiff might not be able to make any estimate as to how much steel its purchaser(s) would need in its (their) project(s). The scheme which, according to Mr. Maurellet’s arguments, was contemplated by the Defendant would not work. At least it might not. 115.Further, I agree with Ms Cruden’s submissions highlighting the background fact that the Sales Contract was entered into in settlement of the 2007 Action. The agreed quantity of 4,000 M/T was a compromise. It was not a pre-estimate of the Plaintiff’s actual or anticipated need for steel bars during the contract period. The scheme argued by Mr. Maurellet to have been contemplated by the Defendant is inconsistent with this important background fact. 116.Mr. Maurellet argued that the Defendant’s construction was “necessary due to physical limitation for delivery”. I have made my observations in this regard. There were too many variables for me to make any meaningful findings as to how much steel bars which the Plaintiff could remove per day. But in my view, the important point here is this, that the Defendant’s delivery obligation was simply to have the steel bars available as its warehouse. I refer to the Delivery Clause, which stipulated that “Goods to be collected by the buyer from the seller’s warehouse in New Territories”. The Plaintiff was obliged to arrange collection, and the Sales Contract did not contain any terms limiting the period of time the Plaintiff was allowed to take delivery. 117.The evidence suggests that the Defendant had sufficient steel bars in the Defendant’s warehouse to satisfy the Subject Orders. This evidence is inconsistent with the Defendant’s pleaded case that “any single delivery equal to or over 1,000 M/T” plainly referred to “the delivery of steel bars to a single project with a total quantity equal to or in excess of 1,000 m/t such that with one month notice prior to delivery the Defendant would have sufficient time to procure the necessary stock of the steel bars required to be supplied for any particular project”. 118.Mr. Maurellet further submitted that the Plaintiff’s version of interpretation would lead to absurdities, as the Plaintiff could easily circumvent the notice requirement by splitting up large orders. 119.In my view, the alleged absurdities have been exaggerated. The Defendant had enough stock in its warehouse to satisfy the Subject Orders. The Defendant did not require much time to procure supplies. Its obligations under the contract were merely to make the steel bars available ready for collection. The Plaintiff would have to collect them. There was no need to collect everything within one day. The bottom line is that the wording of the Sales Contract, and the threshold quantity of 1,000 M/T were all chosen by the parties. I do not see any sufficient basis to re-write them. 120.In all the circumstances, I find the Defendant’s contention to be inconsistent with the words used in the Sales Contract as a whole, and in particular those of Remark 1. It is also not supported by the factual matrix. Having interpreted the Sales Contract according to the applicable legal principles as discussed above, I reject the Defendant’s case in respect of the Second Issue. K. THE THIRD ISSUE – WHETHER THE SALES CONTRACT CONTAINED THE IMPLIED DELIVERY CLAUSE 121.In respect of the Third Issue, Mr. Maurellet submitted that “there is an implied term that the clause in the Contract under the heading “Delivery” which states that “… And the Defendant undertakes to supply by partial delivery the quantity of steel required by Plaintiff who shall notify the seller by fax 24 hours in advance notice” should be subject to the requirement of reasonableness, in that delivery would not be made by the Defendant, if “it would be manifestly unreasonable for [the Plaintiff] to require delivery within 24 hours by [Defendant] of the quantity of steel so specified” 122.This issue is closely linked to the Second Issue. They were in fact dealt with together in Mr. Maurellet’s Closing Submissions. 123.I repeat Sections I and J above, in particular paragraphs 118 and 119 above. I see no manifest unreasonableness involved. 124.I agree with Ms Cruden’s submissions that, for the following two main reasons, the Implied Delivery Clause should not be implied into the Sales Contract:-
125.Mr. Maurellet referred me to Treitel’s Law of Contract, 13th ed, pages 59-60 (discussing those cases “in which matters are to be resolved by the decision of one party”, but clear words are required to achieve that result) and Paragon Finance Ltd v Nash [2002] 1 WLR 685 at paragraph 36 (power which is conferred is limited by an implied term that it must not be exercised “dishonestly, for an improper purpose, capriciously or arbitrarily” where “such an implied term is necessary in order to give effect to the reasonable expectations of the parties”). Mr. Maurellet sought to draw an analogy with those cases. I do not find that analogy useful. In my view, the wording of the Sales Contract is clear. Further, as submitted by Ms Cruden, there is no issue of the Sales Contract having conferred upon the Plaintiff a power which might be used “dishonestly, for an improper purpose, capriciously or arbitrarily”. 126.In my view, the Implied Delivery Clause was not necessary to give business efficacy to the Sales Contract. That was also not what the Sales Contract, read as a whole against the relevant background, would reasonably be understood to mean. 127.Hence, whether under the approach adopted by the Court of Final Appeal in Twinkle Step, or under the so-called “broader approach” adopted in Belize, I refuse to imply the Implied Delivery Clause from the language of the Sales Contract. L. THE FOURTH ISSUE – WHETHER THE SALES CONTRACT CONTAINED THE IMPLIED NOTIFICATION CLAUSE 128.In respect of this issue, Mr. Maurellet’s main contention was this, that “it was an implied term of the Sales Contract that in giving advance notice to the Defendant for the supply of steel bars, the Plaintiff must identify the project in Hong Kong for which the steel bars are to be used”. 129.Mr. Maurellet made to me a number of submissions in support of his main contention. I am not going to deal with all of them. I form the view that his main contention fails at the threshold, in the sense that there is no basis for Mr. Maurellet’s primary submission that “it was the Plaintiff and the Defendant’s common understanding that a project/job/site name for construction projects the steel bars would be used had to be supplied to D for each delivery of steel bars taken by the Plaintiff.” 130.Mr. Maurellet’s contention presupposes that at the time when the Plaintiff placed an order for delivery, details of the name and location of the project/job/site name and location at which the steel bars would be used were known. 131.That pre-supposition is linked to the submissions Mr. Maurellet made in respect of the First Issue, namely, “The projects of the Plaintiff P would have to be ongoing projects or foreseeable projects in the near future which details are known, given the non-durable nature of steel bars, and given the need for the Plaintiff to ensure that there has been no resale of the steel bars supplied”. 132.I have rejected that submission. I have given my reasons why. I have also commented upon the vague natures of the terms concerned. I will not repeat them. 133.That pre-supposition is also inconsistent with the important background fact that the Sales Contract was entered into in settlement of the 2007 Action, that the agreed quantity of 4,000 M/T was a compromise, and that it was not a pre-estimate of the Plaintiff’s actual or anticipated need for steel bars during the contract period. 134.Mr. Maurellet sought to rely upon the obligation on the part of the Defendant to issue stockist certificates. The scope of the Defendant’s duties to issue stockist certificates was canvassed during the course of the hearing (in the context of Ms Cruden’s application to admit the 3rd Supplemental Witness Statement of Mr. Nelson Kwok). I refer to paragraph 4.1.4 of CS2 concerning stockist certificates for Class 2 reinforcement (which the Defendant was primarily concerned with). That paragraph provides that:-
135.Further, some of the steel bars ordered under the Fulfilled Orders had been ordered and supplied without particulars of the project/job/site at which they were intended to be use. The Defendant claimed that that was the result of its omission. But the evidence is inconsistent with at least the suggestion that the Plaintiff had the understanding that particulars of the project/job/site at which they were intended to be use had to be supplied when placing orders. That also suggests that the Sales Contract was still operable without the Implied Notification Clause. 136.It is true that the Project Clause said “Under various projects in Hong Kong”. However, that does not mean that the details of the projects would necessarily be known at the time when the orders were placed. The territorial limit sought to govern the use of the steel bars, which was an act subsequent to the act of ordering. There might be consequences if the steel bars ordered and delivered under the Sales Contract were subsequently found not to have been used in projects in Hong Kong. The parties have not canvassed what those consequences might have been, and I will not speculate. I however find force in Ms Cruden’s submission that even if the Plaintiff were obliged to provide project particulars and that the Defendant had not been satisfied with those provided, that still would not have excused the Defendant from delivering, as the Plaintiff’s failure would not have been fundamental breach, as it would not have gone to the root or essence of the Sales Contract. 137.I do not find that the Implied Notification Term is necessary to give business efficacy to the Sales Contract. I find the contrary, because as at the stage of placing an order, the Plaintiff might not have the particulars which would have been required for the fulfillment of the Implied Notification Term. 138.Further, in the light of the full facts as explained above, I am not satisfied that the Implied Notification Term spells out what the Sales Contract read against the relevant background would reasonably be understood to mean. 139.I reject also the Defendant’s case in respect of the Fourth Issue. 140.That being my conclusion, I do not find it necessary to deal with the issue raised by the Plaintiff that the Defendant has waived and/or is estopped from relying on the alleged implied terms. M. CONCLUSION ON LIABILITY 141.By reason of the above, I find that the Defendant had no legal basis to refuse delivery of the Subject Orders. I reject all the defence on liability raised by the Defendant. N. QUANTUM N.1. The Plaintiff’s case on quantum 142.On the applicable principles, Ms Cruden has referred me to Section 53 of the Sales of Goods Ordinance. She submitted that on the facts of this case, Section 53(3) applies. There is an available market for the steel bars concerned. The measure of damages is therefore prima facie to be ascertained by the difference between the contract price and the market price or current price of the steel bars at the time when the steel ought to have been delivered. Both Counsel have also referred me to various passages from Benjamin’s Sale of Goods, 8th Edition (“Benjamin”) (I note that section 51(3) of the Sales of Goods Act which is the same as s.53(3) of the Sales of Goods Ordinance):-
143.In respect of quantum the Plaintiff relies upon the Single Joint Expert Report dated 21st November 2011 of Mr Cheung Tat Tong. According to his expert opinion and calculations, the loss and damage suffered by the Plaintiff was assessed at HK$9,091,162.21. N.2. The Defendant’s case on quantum 144.On the question of quantum, the Defendant has raised a number of points. Mr. Maurellet has in his Closing Submissions helpfully crystalized them into three issues. I will deal with those points one by one. N.2.1 Whether the losses claimed too remote 145.The Defendant’s case in this regard is this, that the losses claimed are too remote, as the Plaintiff could only have used any steel bars supplied for its own building projects and not for resale purposes, so that it is not appropriate to claim losses based on the difference between the contractual price and the market price for steel bars. 146.Mr. Maurellet has cited to me Hadley v Baxendale (1854) Ex 341 at 354, where Alderson B held that: -
147.Hadley v Baxendale is not controversial. 148.It is however important to note that the Defendant’s case under this head is predicated upon a finding in its favour in respect of the interpretation of the Project Clause and Remark 1. This is clear from paragraph 140 of Mr. Maurellet’s Closing Submission, where he said that:-
149.As explained above, I have ruled against the Defendant in respect of the interpretation of the Project Clause and Remark 1. 150.On this question of remoteness, I accept Ms Cruden’s submission that s.53 of the Sale of Goods Ordinance applies. 151.In any event, I repeat the evidence in respect of the pleadings filed in the 2007 Action, and the consequential knowledge by the Defendant of their contents. In particular, Mr. Fung accepted that as a result of the pleadings, the Defendant knew that one of the Plaintiff’s complaints in the 2007 Action was that it had lost the opportunity to resell the steel bar concerned. I do not accept Mr. Maurellet’s submissions made orally in elaboration of his written Closing Submissions that as the issue of possible resale had only been pleaded once, the possibility of resale remains too remote. As I have found above, the fact that the Plaintiff was not a QA Stockist did not preclude it from reselling steel bars. This, coupled with the pleadings in the 2007 Action, render the possibility of resale by the Plaintiff within the reasonable contemplation of the parties in the Hadley and Baxendale sense. 152.I do not accept the Defendant’s case based upon alleged remoteness. N.2.2 Whether the Plaintiff has failed to mitigate its loss 153.It is the Defendant case in this regard that any loss suffered by the Plaintiff was caused by the Plaintiff’s own failure to mitigate its losses. As far as the law is concerned, Mr. Maurellet referred me to paragraphs 17-014 and 17-015 of Benjamin (which I have reproduced above). In so far as the facts are concerned, Mr. Maurellet relied upon the Settlement Offer. 154.I do not accept the Defendant’s case in this regard, for the following reasons:-
N.2.3 Calculation of the market price 155.Mr. Maurellet’s urges me to look at the figures relied on by the Plaintiff with circumspection. He isolated from the Joint Expert Report certain comparables. He suggested that some of those comparables might form a better basis for my assessment of the loss and damage. I do not favour that approach. The Joint Expert has considered all the comparables before he formed his conclusions. He has the expertise. The Court does not. That is the whole point of seeking his assistance. I have considered his report. I adopt the figures that he has reached. O. Conclusions 156.By reason of the above, I find and hold that the Defendant is liable to the Plaintiff for the sum of HK$9,091,162.21. I give judgment to the Plaintiff to that effect. 157.Applying the normal rule of costs follow event, there is an order nisi that the Defendant pays the costs of the Plaintiff (for avoidance of doubt, inclusive of the costs of and occasioned by the application for the admission of the 3rd Supplemental Witness Statement of Mr. Nelson Kwok) to be taxed if not agreed. 158.The Plaintiff also claims interest pursuant to sections 48 and 49 of the High Court Ordinance. I make an order nisi that the Defendant shall pay interest on the sum of HK$9,091,162.21 from the date of the Writ to date of judgment at the rate of HSBC prime plus 1%, and thereafter at judgment rate. 159.I thank counsel for their most able assistance.
Ms Liza Jane Cruden, instructed by Wong & Fok, for the plaintiff Mr Jose Antonio Maurellet, instructed by Ho & Ip, for the defendant | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case